Bid Tab X-ray: 6507-00-001

Sep 15, 2026 · Walker Sign up free
Set your company to personalize scores

FY27 - Huntsville AO Cutback - 09

6507-00-001 · let Sep 15, 2026 · Walker, Bryan · Material Maintenance Project

$122,880Low bid: MARTIN RESOURCE MANAGEMENT CORPORATION+3.8% vs estimate $118,400
$14,720Left on the table12.0% gap to the second bid
3BiddersSpread 19% low to high
4Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1MARTIN RESOURCE MANAGEMENT CORPORATION $122,8803.8% $14,720 0 0
2WRIGHT ASPHALT PRODUCTS COMPANY LLC $137,600+12.0%16.2% $8,720 0 0
3CLEVELAND ASPHALT PRODUCTS, INC. $146,320+19.1%23.6% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.

Where the job was won

MARTIN RESOURCE MANAGEMENT CORPORATION vs WRIGHT ASPHALT PRODUCTS COMPANY LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
8003-7016 RC-250 (DEL)(SITE 1)8,000 GAL $3.76$4.30$3.89 $4,320
8003-7017 RC-250 (DEL)(SITE 2)8,000 GAL $3.80$4.30$3.96 $4,000
8003-7018 RC-250 (DEL)(SITE 3)8,000 GAL $3.87$4.30$4.02 $3,440
8003-7019 RC-250 (DEL)(SITE 4)8,000 GAL $3.93$4.30$3.92 $2,960

Positive: the low bidder was cheaper on that item. These 4 items account for $14,720 of the $14,720 gap.