6506-25-001 · let Sep 10, 2026 · Duval, Laredo · Material Maintenance Project - Sealed
$182,940Low bid: VULCAN CONSTRUCTION MATERIALS, LLC-2.1% vs estimate $186,870
$10,060Left on the table5.5% gap to the second bid
3BiddersSpread 31% low to high
2Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | VULCAN CONSTRUCTION MATERIALS, LLC | $182,940 | -2.1% | $10,060 | 0 | 0 | |
| 2 | BRAUNTEX MATERIALS, INC. | $193,000 | +5.5% | 3.3% | $46,380 | 0 | 0 |
| 3 | MARTIN MARIETTA MATERIALS, INC. | $239,380 | +30.9% | 28.1% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
VULCAN CONSTRUCTION MATERIALS, LLC vs BRAUNTEX MATERIALS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8000-7295 AGGR (TY PB GR 4) (DEL) (ST1) | 1,500 TON | $91.22 | $96.00 | $92.77 | $7,170 |
| 8000-7267 AGGR (TY PB GR 3) (DEL) (ST1) | 500 TON | $92.22 | $98.00 | $83.06 | $2,890 |
Positive: the low bidder was cheaper on that item. These 2 items account for $10,060 of the $10,060 gap.