CABLE BARRIER REPAIR KRAO FY'27
6503-17-001 · let Sep 9, 2026 · Kaufman, Dallas · Routine Maintenance Project - Sealed
$272,475Low bid: FIREMAN EXCAVATING, INC.-41.1% vs estimate $462,963
$179,225Left on the table65.8% gap to the second bid
2BiddersSpread 66% low to high
12Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FIREMAN EXCAVATING, INC. | $272,475 | -41.1% | $179,225 | 0 | 4-$165,829 | |
| 2 | TEXWAY WASTEWATER SERVICES, LLC | $451,700 | +65.8% | -2.4% | 2+$38,249 | 3-$186,877 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
FIREMAN EXCAVATING, INC. vs TEXWAY WASTEWATER SERVICES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL) | 1,500 EA | $120.00 | $240.00 | $176.83 | $180,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 100 EA | $800.00 | $1.00 | $600.85 | -$79,900 |
| 771-7025 REPLACE LINE OR TERMINAL POST (VALTIR) | 50 EA | $50.00 | $700.00 | $215.97 | $32,500 |
| 771-7029 REPLACE CABLE RELEASE POST | 40 EA | $100.00 | $500.00 | $148.81 | $16,000 |
| 771-7030 CHECK AND RE-TENSION CABLE SYSTEM | 350 EA | $10.00 | $50.00 | $350.67 | $14,000 |
| 771-7033 SPLICE CABLE | 50 EA | $10.00 | $200.00 | $342.77 | $9,500 |
| 772-7007 POST AND CABLE FENCE (REMV/ REPL CABLE) | 25 LF | $3.00 | $100.00 | $8.34 | $2,425 |
| 771-7031 REPLACE CABLE | 600 LF | $1.00 | $5.00 | $3.23 | $2,400 |
| 772-7008 POST AND CABLE FENCE (REPAIR) | 100 LF | $5.00 | $20.00 | $10.99 | $1,500 |
| 772-7005 POST AND CABLE FENCE(REMV / REPL POSTS) | 10 EA | $45.00 | $100.00 | $81.29 | $550 |
| 772-7006 POST AND CABLE FENCE(RMV/REPL CNC ANCH) | 5 EA | $50.00 | $100.00 | $101.18 | $250 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $1.00 | $217.57 | $0 |
Positive: the low bidder was cheaper on that item. These 12 items account for $179,225 of the $179,225 gap.
FIREMAN EXCAVATING, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7030 CHECK AND RE-TENSION CABLE SYSTEM | 350 EA | $10.00 | $350.67 | 0.03x | -$119,235 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |
| 771-7033 SPLICE CABLE | 50 EA | $10.00 | $342.77 | 0.03x | -$16,639 |
| 771-7025 REPLACE LINE OR TERMINAL POST (VALTIR) | 50 EA | $50.00 | $215.97 | 0.23x | -$8,298 |
TEXWAY WASTEWATER SERVICES, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7025 REPLACE LINE OR TERMINAL POST (VALTIR) | 50 EA | $700.00 | $215.97 | 3.24x | $24,202 |
| 771-7029 REPLACE CABLE RELEASE POST | 40 EA | $500.00 | $148.81 | 3.36x | $14,048 |
| 771-7030 CHECK AND RE-TENSION CABLE SYSTEM | 350 EA | $50.00 | $350.67 | 0.14x | -$105,235 |
| 500-7002 MOBILIZATION (CALLOUT) | 100 EA | $1.00 | $600.85 | 0.00x | -$59,985 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |