Drainage Improvements FM2480
6502-56-001 · let Sep 2, 2026 · Cameron, Pharr · Routine Maintenance Project - Sealed
$1,348,043Low bid: DIGG COMMERCIAL, LLC+20.7% vs estimate $1,116,965
$46,599Left on the table3.5% gap to the second bid
2BiddersSpread 3% low to high
35Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DIGG COMMERCIAL, LLC | $1,348,043 | 20.7% | $46,599 | 8+$443,222 | 3-$1,529,769 | |
| 2 | LUCANIA CONTRACTORS LLC | $1,394,642 | +3.5% | 24.9% | 15+$550,235 | 5-$1,630,032 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
DIGG COMMERCIAL, LLC vs LUCANIA CONTRACTORS LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 110-7002 EXCAV (CHANNEL) | 8,613 CY | $40.00 | $12.00 | $16.69 | -$241,164 |
| 464-7007 RC PIPE (CL III)(30 IN) | 672 LF | $135.00 | $250.00 | $140.03 | $77,280 |
| 467-7345 SET (TY II) (30 IN) (RCP) (3: 1) (C) | 28 EA | $2,369.00 | $5,000.00 | $2,759.74 | $73,668 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $6,000.00 | $500.00 | $11,585.04 | -$66,000 |
| 400-7010 CEM STABIL BKFL | 83 CY | $800.00 | $150.00 | $138.14 | -$53,950 |
| 464-7005 RC PIPE (CL III)(24 IN) | 352 LF | $110.00 | $250.00 | $108.34 | $49,280 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 20,670 SY | $2.00 | $4.00 | $1.43 | $41,340 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $140,000.00 | $523,850.32 | $40,000 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $7,804.00 | $25,000.00 | $9,253.78 | $34,392 |
| 354-7018 PLANE & TEXT ASPH CONC PAV(1.5") | 6,792 SY | $5.00 | $10.00 | $1.85 | $33,960 |
| 400-7003 STRUCT EXCAV (PIPE) | 805 CY | $10.00 | $50.00 | $5.29 | $32,200 |
| 164-7018 HYDRO MULCH SEED (PERM_RURAL_CLAY) | 19,262 SY | $2.00 | $0.6000 | $0.5003 | -$26,967 |
| 467-7325 SET (TY II) (24 IN) (RCP) (3: 1) (C) | 8 EA | $1,724.00 | $4,500.00 | $1,927.30 | $22,208 |
| 496-7004 REMOV STR (SET) | 10 EA | $555.00 | $2,000.00 | $514.07 | $14,450 |
| 401-7001 FLOWABLE BACKFILL | 251 CY | $50.00 | $100.00 | $298.77 | $12,550 |
| 467-7472 SET (REMOV & REINSTALL) | 16 EA | $250.00 | $1,000.00 | $547.11 | $12,000 |
| 467-7305 SET (TY II) (18 IN) (RCP) (3: 1) (C) | 4 EA | $1,098.00 | $3,500.00 | $1,266.94 | $9,608 |
| 344-7064 SP MIXES SP-D SAC-A PG76-22 | 586 TON | $300.00 | $284.00 | $129.17 | -$9,376 |
| 250-7002 GEOGRID BASE REINFORCEMENT (TYPE 2) | 7,521 SY | $1.20 | $0.0100 | $1.65 | -$8,950 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 17 CY | $1,000.00 | $1,500.00 | $616.83 | $8,500 |
Positive: the low bidder was cheaper on that item. These 20 items account for $55,029 of the $46,599 gap.
DIGG COMMERCIAL, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7002 EXCAV (CHANNEL) | 8,613 CY | $40.00 | $16.69 | 2.40x | $200,735 |
| 344-7064 SP MIXES SP-D SAC-A PG76-22 | 586 TON | $300.00 | $129.17 | 2.32x | $100,105 |
| 400-7010 CEM STABIL BKFL | 83 CY | $800.00 | $138.14 | 5.79x | $54,934 |
| 164-7018 HYDRO MULCH SEED (PERM_RURAL_CLAY) | 19,262 SY | $2.00 | $0.5003 | 4.00x | $28,887 |
| 354-7018 PLANE & TEXT ASPH CONC PAV(1.5") | 6,792 SY | $5.00 | $1.85 | 2.70x | $21,377 |
| 530-7010 DRIVEWAYS (ACP) | 393 SY | $100.00 | $54.96 | 1.82x | $17,702 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 7,000 LF | $2.00 | $0.4757 | 4.20x | $10,670 |
| 666-7420 REFL PAV MRK TY I (Y)6"(BRK)(100MIL) | 3,500 LF | $3.00 | $0.4829 | 6.21x | $8,810 |
| 400-7008 CUT & RESTORE ASPH PAVING | 7,500 SY | $1.00 | $140.13 | 0.01x | -$1,043,479 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 401-7001 FLOWABLE BACKFILL | 251 CY | $50.00 | $298.77 | 0.17x | -$62,440 |
LUCANIA CONTRACTORS LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 344-7064 SP MIXES SP-D SAC-A PG76-22 | 586 TON | $284.00 | $129.17 | 2.20x | $90,729 |
| 464-7007 RC PIPE (CL III)(30 IN) | 672 LF | $250.00 | $140.03 | 1.79x | $73,900 |
| 467-7345 SET (TY II) (30 IN) (RCP) (3: 1) (C) | 28 EA | $5,000.00 | $2,759.74 | 1.81x | $62,727 |
| 354-7018 PLANE & TEXT ASPH CONC PAV(1.5") | 6,792 SY | $10.00 | $1.85 | 5.40x | $55,337 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 20,670 SY | $4.00 | $1.43 | 2.80x | $53,136 |
| 464-7005 RC PIPE (CL III)(24 IN) | 352 LF | $250.00 | $108.34 | 2.31x | $49,865 |
| 400-7003 STRUCT EXCAV (PIPE) | 805 CY | $50.00 | $5.29 | 9.46x | $35,993 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $25,000.00 | $9,253.78 | 2.70x | $31,492 |
| 467-7325 SET (TY II) (24 IN) (RCP) (3: 1) (C) | 8 EA | $4,500.00 | $1,927.30 | 2.33x | $20,582 |
| 530-7010 DRIVEWAYS (ACP) | 393 SY | $100.00 | $54.96 | 1.82x | $17,702 |
| 400-7008 CUT & RESTORE ASPH PAVING | 7,500 SY | $0.0100 | $140.13 | 0.00x | -$1,050,904 |
| 500-7001 MOBILIZATION | 1 LS | $140,000.00 | $523,850.32 | 0.27x | -$383,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $500.00 | $11,585.04 | 0.04x | -$133,021 |
| 401-7001 FLOWABLE BACKFILL | 251 CY | $100.00 | $298.77 | 0.33x | -$49,890 |
| 250-7002 GEOGRID BASE REINFORCEMENT (TYPE 2) | 7,521 SY | $0.0100 | $1.65 | 0.01x | -$12,367 |