FY '26 Traffic Control KRAO
6502-16-001 · let Sep 9, 2026 · Kaufman, Dallas · Routine Maintenance Project - Sealed
$599,675Low bid: AWP SAFETY+18.8% vs estimate $504,850
$309,575Left on the table51.6% gap to the second bid
2BiddersSpread 52% low to high
19Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | AWP SAFETY | $599,675 | 18.8% | $309,575 | 6+$372,681 | 2-$53,533 | |
| 2 | FC TRAFFIC CONTROL, LLC | $909,250 | +51.6% | 80.1% | 6+$667,958 | 1-$10,237 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
AWP SAFETY vs FC TRAFFIC CONTROL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 275 DAY | $1,100.00 | $1,500.00 | $229.60 | $110,000 |
| 505-7001 TMA (STATIONARY) | 150 DAY | $900.00 | $1,500.00 | $217.57 | $90,000 |
| 500-7033 MOBILIZATION (EMERGENCY) | 50 EA | $250.00 | $2,000.00 | $844.81 | $87,500 |
| 500-7002 MOBILIZATION (CALLOUT) | 50 EA | $125.00 | $1,500.00 | $600.85 | $68,750 |
| 790-7045 LANE CLOSURE(HOURLY ONLY)(TYP 7) | 200 HR | $180.00 | $50.00 | $101.18 | -$26,000 |
| 790-7049 LANE CLOSURE(HOURLY ONLY)(TYP 11) | 200 HR | $145.00 | $50.00 | $89.75 | -$19,000 |
| 790-7040 LANE CLOSURE(HOURLY ONLY)(TYP 2) | 70 HR | $120.00 | $300.00 | $84.76 | $12,600 |
| 790-7043 LANE CLOSURE(HOURLY ONLY)(TYP 5) | 35 HR | $120.00 | $300.00 | $58.58 | $6,300 |
| 790-7051 LANE CLOSURE(HOURLY ONLY)(TYP 13) | 25 HR | $300.00 | $50.00 | $107.11 | -$6,250 |
| 790-7056 LANE CLOSURE(HOURLY ONLY)(TYP 18) | 85 HR | $120.00 | $50.00 | $35.34 | -$5,950 |
| 790-7039 LANE CLOSURE(HOURLY ONLY)(TYP 1) | 200 HR | $120.00 | $100.00 | $69.23 | -$4,000 |
| 790-7046 LANE CLOSURE(HOURLY ONLY)(TYP 8) | 25 HR | $190.00 | $50.00 | $63.03 | -$3,500 |
| 500-7003 MOBILIZATION (CALLOUT 1) | 3 EA | $1,000.00 | $2,000.00 | $599.93 | $3,000 |
| 790-7047 LANE CLOSURE(HOURLY ONLY)(TYP 9) | 10 HR | $250.00 | $50.00 | $36.37 | -$2,000 |
| 790-7052 LANE CLOSURE(HOURLY ONLY)(TYP 14) | 25 HR | $120.00 | $50.00 | $42.05 | -$1,750 |
| 790-7059 ADDITIONAL LANE CLOSURE ITEM(TYPE 21) | 50 HR | $80.00 | $50.00 | $58.00 | -$1,500 |
| 790-7044 LANE CLOSURE(HOURLY ONLY)(TYP 6) | 10 HR | $125.00 | $200.00 | $53.35 | $750 |
| 790-7060 ADDITIONAL LANE CLOSURE ITEM(TYPE 22) | 25 HR | $25.00 | $50.00 | $18.58 | $625 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 50 DAY | $100.00 | $100.00 | $87.82 | $0 |
Positive: the low bidder was cheaper on that item. These 19 items account for $309,575 of the $309,575 gap.
AWP SAFETY: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 275 DAY | $1,100.00 | $229.60 | 4.79x | $239,361 |
| 505-7001 TMA (STATIONARY) | 150 DAY | $900.00 | $217.57 | 4.14x | $102,364 |
| 790-7045 LANE CLOSURE(HOURLY ONLY)(TYP 7) | 200 HR | $180.00 | $101.18 | 1.78x | $15,763 |
| 790-7056 LANE CLOSURE(HOURLY ONLY)(TYP 18) | 85 HR | $120.00 | $35.34 | 3.40x | $7,196 |
| 790-7051 LANE CLOSURE(HOURLY ONLY)(TYP 13) | 25 HR | $300.00 | $107.11 | 2.80x | $4,822 |
| 790-7046 LANE CLOSURE(HOURLY ONLY)(TYP 8) | 25 HR | $190.00 | $63.03 | 3.01x | $3,174 |
| 500-7033 MOBILIZATION (EMERGENCY) | 50 EA | $250.00 | $844.81 | 0.30x | -$29,741 |
| 500-7002 MOBILIZATION (CALLOUT) | 50 EA | $125.00 | $600.85 | 0.21x | -$23,792 |
FC TRAFFIC CONTROL, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 275 DAY | $1,500.00 | $229.60 | 6.53x | $349,361 |
| 505-7001 TMA (STATIONARY) | 150 DAY | $1,500.00 | $217.57 | 6.89x | $192,364 |
| 500-7033 MOBILIZATION (EMERGENCY) | 50 EA | $2,000.00 | $844.81 | 2.37x | $57,759 |
| 500-7002 MOBILIZATION (CALLOUT) | 50 EA | $1,500.00 | $600.85 | 2.50x | $44,958 |
| 790-7040 LANE CLOSURE(HOURLY ONLY)(TYP 2) | 70 HR | $300.00 | $84.76 | 3.54x | $15,067 |
| 790-7043 LANE CLOSURE(HOURLY ONLY)(TYP 5) | 35 HR | $300.00 | $58.58 | 5.12x | $8,450 |
| 790-7045 LANE CLOSURE(HOURLY ONLY)(TYP 7) | 200 HR | $50.00 | $101.18 | 0.49x | -$10,237 |