Denton Cable Barrier Repair
6501-92-001 · let Sep 9, 2026 · Denton, Dallas · Routine Maintenance Project - Sealed
$105,850Low bid: MARCOM'S MOWING SERVICE, LLC-50.9% vs estimate $215,570
$20,495Left on the table19.4% gap to the second bid
4BiddersSpread 86% low to high
8Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | MARCOM'S MOWING SERVICE, LLC | $105,850 | -50.9% | $20,495 | 3+$18,552 | 2-$214,934 | |
| 2 | FIREMAN EXCAVATING, INC. | $126,345 | +19.4% | -41.4% | $53,620 | 2+$43,968 | 4-$225,622 |
| 3 | AUSTIN BARRICADE COMPANY, L.L.C. | $179,965 | +70.0% | -16.5% | $17,335 | 3+$109,653 | 4-$222,529 |
| 4 | TEXWAY WASTEWATER SERVICES, LLC | $197,300 | +86.4% | -8.5% | 3+$122,889 | 3-$219,947 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
MARCOM'S MOWING SERVICE, LLC vs FIREMAN EXCAVATING, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 771-7027 REPLACE LINE OR TERMINAL POST (BRIFEN) | 100 EA | $40.00 | $450.00 | $40.00 | $41,000 |
| 771-7030 CHECK AND RE-TENSION CABLE SYSTEM | 20 EA | $800.00 | $1.00 | $350.67 | -$15,980 |
| 771-7029 REPLACE CABLE RELEASE POST | 25 EA | $380.00 | $1.00 | $148.81 | -$9,475 |
| 771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL) | 350 EA | $200.00 | $215.00 | $176.83 | $5,250 |
| 771-7033 SPLICE CABLE | 5 EA | $1,100.00 | $500.00 | $342.77 | -$3,000 |
| 771-7031 REPLACE CABLE | 10 LF | $30.00 | $300.00 | $3.23 | $2,700 |
| 500-7002 MOBILIZATION (CALLOUT) | 250 EA | $1.00 | $1.00 | $600.85 | $0 |
| 505-7001 TMA (STATIONARY) | 300 DAY | $1.00 | $1.00 | $217.57 | $0 |
Positive: the low bidder was cheaper on that item. These 8 items account for $20,495 of the $20,495 gap.
MARCOM'S MOWING SERVICE, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7030 CHECK AND RE-TENSION CABLE SYSTEM | 20 EA | $800.00 | $350.67 | 2.28x | $8,987 |
| 771-7029 REPLACE CABLE RELEASE POST | 25 EA | $380.00 | $148.81 | 2.55x | $5,780 |
| 771-7033 SPLICE CABLE | 5 EA | $1,100.00 | $342.77 | 3.21x | $3,786 |
| 500-7002 MOBILIZATION (CALLOUT) | 250 EA | $1.00 | $600.85 | 0.00x | -$149,962 |
| 505-7001 TMA (STATIONARY) | 300 DAY | $1.00 | $217.57 | 0.00x | -$64,972 |
FIREMAN EXCAVATING, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7027 REPLACE LINE OR TERMINAL POST (BRIFEN) | 100 EA | $450.00 | $40.00 | 11.25x | $41,000 |
| 771-7031 REPLACE CABLE | 10 LF | $300.00 | $3.23 | 92.97x | $2,968 |
| 500-7002 MOBILIZATION (CALLOUT) | 250 EA | $1.00 | $600.85 | 0.00x | -$149,962 |
| 505-7001 TMA (STATIONARY) | 300 DAY | $1.00 | $217.57 | 0.00x | -$64,972 |
| 771-7030 CHECK AND RE-TENSION CABLE SYSTEM | 20 EA | $1.00 | $350.67 | 0.00x | -$6,993 |
| 771-7029 REPLACE CABLE RELEASE POST | 25 EA | $1.00 | $148.81 | 0.01x | -$3,695 |
AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL) | 350 EA | $420.00 | $176.83 | 2.38x | $85,109 |
| 771-7033 SPLICE CABLE | 5 EA | $3,000.00 | $342.77 | 8.75x | $13,286 |
| 771-7031 REPLACE CABLE | 10 LF | $1,129.00 | $3.23 | 349.89x | $11,258 |
| 500-7002 MOBILIZATION (CALLOUT) | 250 EA | $1.00 | $600.85 | 0.00x | -$149,962 |
| 505-7001 TMA (STATIONARY) | 300 DAY | $1.00 | $217.57 | 0.00x | -$64,972 |
| 771-7027 REPLACE LINE OR TERMINAL POST (BRIFEN) | 100 EA | $1.00 | $40.00 | 0.03x | -$3,900 |
| 771-7029 REPLACE CABLE RELEASE POST | 25 EA | $1.00 | $148.81 | 0.01x | -$3,695 |
TEXWAY WASTEWATER SERVICES, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL) | 350 EA | $400.00 | $176.83 | 2.26x | $78,109 |
| 771-7027 REPLACE LINE OR TERMINAL POST (BRIFEN) | 100 EA | $400.00 | $40.00 | 10.00x | $36,000 |
| 771-7029 REPLACE CABLE RELEASE POST | 25 EA | $500.00 | $148.81 | 3.36x | $8,780 |
| 500-7002 MOBILIZATION (CALLOUT) | 250 EA | $1.00 | $600.85 | 0.00x | -$149,962 |
| 505-7001 TMA (STATIONARY) | 300 DAY | $1.00 | $217.57 | 0.00x | -$64,972 |
| 771-7030 CHECK AND RE-TENSION CABLE SYSTEM | 20 EA | $100.00 | $350.67 | 0.29x | -$5,013 |