6501-91-001 · let Sep 8, 2026 · Fort Bend, Houston · Routine Maintenance Project
$732,902Low bid: CRACKSEAL OF TEXAS, LLC-11.9% vs estimate $832,244
$83,108Left on the table11.3% gap to the second bid
4BiddersSpread 57% low to high
3Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CRACKSEAL OF TEXAS, LLC | $732,902 | -11.9% | $83,108 | 0 | 2-$552,636 | |
| 2 | D & M CONTRACTORS, LLC | $816,010 | +11.3% | -2.0% | $200,880 | 0 | 2-$517,480 |
| 3 | BLACKSMITH VENTURES LLC | $1,016,890 | +38.7% | 22.2% | $130,139 | 0 | 2-$457,636 |
| 4 | ISI CONTRACTING, INC. | $1,147,029 | +56.5% | 37.8% | 1+$480,792 | 1-$508,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
CRACKSEAL OF TEXAS, LLC vs D & M CONTRACTORS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 705.18 LMI | $1,032.00 | $1,100.00 | $868.20 | $47,952 |
| 500-7001 MOBILIZATION | 1 LS | $5,000.00 | $40,000.00 | $523,850.32 | $35,000 |
| 505-7001 TMA (STATIONARY) | 156 DAY | $1.00 | $2.00 | $217.57 | $156 |
Positive: the low bidder was cheaper on that item. These 3 items account for $83,108 of the $83,108 gap.