Long Line Striping FY 27
6500-91-001 · let Sep 2, 2026 · Fayette, Yoakum · Routine Maintenance Project - Sealed
$1,246,093Low bid: TRP INFRASTRUCTURE SERVICES, LLC+5.4% vs estimate $1,182,215
$151,449Left on the table12.2% gap to the second bid
4BiddersSpread 34% low to high
12Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TRP INFRASTRUCTURE SERVICES, LLC | $1,246,093 | 5.4% | $151,449 | 0 | 3-$613,425 | |
| 2 | STRIPE LINES, INC. | $1,397,542 | +12.2% | 18.2% | $8,049 | 0 | 3-$626,175 |
| 3 | STRIPE-A-ZONE, LLC | $1,405,591 | +12.8% | 18.9% | $269,661 | 0 | 3-$631,425 |
| 4 | PAVEMENT MARKINGS INC. | $1,675,252 | +34.4% | 41.7% | 0 | 3-$622,900 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
TRP INFRASTRUCTURE SERVICES, LLC vs STRIPE LINES, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 666-7410 REFL PAV MRK TY I (W)6"(SLD)(090MIL) | 1,439,216 LF | $0.4200 | $0.4800 | $0.4886 | $86,353 |
| 666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL) | 905,113 LF | $0.4200 | $0.4800 | $0.5014 | $54,307 |
| 500-7001 MOBILIZATION | 1 LS | $25,000.00 | $10,000.00 | $523,850.32 | -$15,000 |
| 666-7292 TY I HIGH PERF PM (W)6"(SLD)(090MIL) | 123,642 LF | $0.4300 | $0.5300 | $0.6513 | $12,364 |
| 666-7304 TY I HIGH PERF PM (Y)6"(SLD)(090MIL) | 123,642 LF | $0.4300 | $0.5300 | $0.6851 | $12,364 |
| 505-7003 TMA (MOBILE OPERATION) | 250 DAY | $1.00 | $10.00 | $229.60 | $2,250 |
| 666-7419 REFL PAV MRK TY I (Y)6"(BRK)(090MIL) | 146,790 LF | $0.4900 | $0.4800 | $0.5412 | -$1,468 |
| 666-7017 REFL PAV MRK TY I (W)8"(DOT)(090MIL) | 4,136 LF | $1.20 | $0.8900 | $1.25 | -$1,282 |
| 666-7023 REFL PAV MRK TY I (W)8"(SLD)(090MIL) | 21,551 LF | $0.7100 | $0.7600 | $0.9036 | $1,078 |
| 666-7289 TY I HIGH PERF PM (W)6"(BRK)(090MIL) | 30,910 LF | $0.5000 | $0.5300 | $0.8121 | $927 |
| 666-7407 REFL PAV MRK TY I (W)6"(BRK)(090MIL) | 44,380 LF | $0.4900 | $0.4800 | $0.5397 | -$444 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $100.00 | $100.00 | $11,585.04 | $0 |
Positive: the low bidder was cheaper on that item. These 12 items account for $151,449 of the $151,449 gap.