CRP_US 181_TAR_CableBarrier_2027
0101-01-070 · let Sep 3, 2026 · Bee, Corpus Christi · Safety Improvement Projects
$1,866,377Low bid: ROADWAY SPECIALTIES, INC.+26.9% vs estimate $1,470,997
$191,767Left on the table10.3% gap to the second bid
5BiddersSpread 25% low to high
27Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ROADWAY SPECIALTIES, INC. | $1,866,377 | 26.9% | $191,767 | 1+$13,646 | 4-$519,916 | |
| 2 | GRATIOT CONSTRUCTION, LTD. | $2,058,143 | +10.3% | 39.9% | $89,482 | 0 | 4-$477,377 |
| 3 | SCR CIVIL CONSTRUCTION, LLC | $2,147,625 | +15.1% | 46.0% | $41,766 | 1+$207,075 | 2-$488,321 |
| 4 | SCOUT 5 CONSTRUCTION LLC | $2,189,391 | +17.3% | 48.8% | $150,951 | 3+$212,857 | 1-$473,839 |
| 5 | MASSANA CONSTRUCTION INC. | $2,340,342 | +25.4% | 59.1% | 0 | 3-$137,865 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ROADWAY SPECIALTIES, INC. vs GRATIOT CONSTRUCTION, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 432-7014 RIPRAP (MOW STRIP)(5 IN) | 2,675 CY | $328.76 | $401.00 | $480.77 | $193,242 |
| 543-7018 CABLE BARRIER TERM SEC (INSTL)(TL-4) | 64 EA | $2,779.25 | $3,400.00 | $2,822.11 | $39,728 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $2,771.63 | $7,200.00 | $11,585.04 | $30,999 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $250.00 | $1.00 | $217.57 | -$29,880 |
| 543-7002 CABLE BARRIER SYSTEM (INSTALL)(TL-4) | 56,920 LF | $9.51 | $9.00 | $12.40 | -$29,029 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 65 DAY | $297.76 | $1.00 | $87.82 | -$19,289 |
| 500-7001 MOBILIZATION | 1 LS | $188,166.37 | $195,000.00 | $523,850.32 | $6,834 |
| 505-7003 TMA (MOBILE OPERATION) | 20 DAY | $250.00 | $1.00 | $229.60 | -$4,980 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 1,480 LF | $2.96 | $4.25 | $3.92 | $1,909 |
| 506-7043 BIODEG EROSN CONT LOGS (INSTL) (8") | 196 LF | $3.06 | $10.00 | $4.63 | $1,360 |
| 506-7041 TEMP SEDMT CONT FENCE (REMOVE) | 1,480 LF | $0.4600 | $1.00 | $1.02 | $799 |
| 506-7046 BIODEG EROSN CONT LOGS (REMOVE) | 196 LF | $0.6200 | $1.00 | $1.29 | $74 |
| 164-7041 DRILL SEED (PERM_RURAL_SAND) | 72.6 AC | $0.0100 | $0.0100 | $1,030.79 | $0 |
| 168-7001 VEGETATIVE WATERING | 5,663 TGL | $0.0100 | $0.0100 | $8.43 | $0 |
Positive: the low bidder was cheaper on that item. These 14 items account for $191,767 of the $191,767 gap.
ROADWAY SPECIALTIES, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 65 DAY | $297.76 | $87.82 | 3.39x | $13,646 |
| 500-7001 MOBILIZATION | 1 LS | $188,166.37 | $523,850.32 | 0.36x | -$335,684 |
| 164-7041 DRILL SEED (PERM_RURAL_SAND) | 72.6 AC | $0.0100 | $1,030.79 | 0.00x | -$74,834 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $2,771.63 | $11,585.04 | 0.24x | -$61,694 |
| 168-7001 VEGETATIVE WATERING | 5,663 TGL | $0.0100 | $8.43 | 0.00x | -$47,703 |
GRATIOT CONSTRUCTION, LTD.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $195,000.00 | $523,850.32 | 0.37x | -$328,850 |
| 164-7041 DRILL SEED (PERM_RURAL_SAND) | 72.6 AC | $0.0100 | $1,030.79 | 0.00x | -$74,834 |
| 168-7001 VEGETATIVE WATERING | 5,663 TGL | $0.0100 | $8.43 | 0.00x | -$47,703 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $1.00 | $217.57 | 0.00x | -$25,989 |
SCR CIVIL CONSTRUCTION, LLC: unbalanced items
Placed 3SCOUT 5 CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 164-7041 DRILL SEED (PERM_RURAL_SAND) | 72.6 AC | $2,795.00 | $1,030.79 | 2.71x | $128,082 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 1,480 LF | $35.00 | $3.92 | 8.94x | $46,004 |
| 168-7001 VEGETATIVE WATERING | 5,663 TGL | $15.28 | $8.43 | 1.81x | $38,771 |
| 500-7001 MOBILIZATION | 1 LS | $50,011.00 | $523,850.32 | 0.10x | -$473,839 |