BPM FM 1378 Erosion Control 07 08.26
6498-35-001 · let Sep 9, 2026 · Collin, Dallas · Bridge Preventative Maintenance - Sealed
$79,718Low bid: TEXAS ROAD CONSTRUCTION, LLC+10.9% vs estimate $71,867
$2,696Left on the table3.4% gap to the second bid
3BiddersSpread 18% low to high
8Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TEXAS ROAD CONSTRUCTION, LLC | $79,718 | 10.9% | $2,696 | 2+$6,285 | 4-$547,336 | |
| 2 | GARRET SHIELDS INFRASTRUCTURE | $82,414 | +3.4% | 14.7% | $11,436 | 0 | 4-$542,030 |
| 3 | TEXWAY WASTEWATER SERVICES, LLC | $93,850 | +17.7% | 30.6% | 1+$3,244 | 3-$538,718 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
TEXAS ROAD CONSTRUCTION, LLC vs GARRET SHIELDS INFRASTRUCTURE, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $1,000.00 | $5,000.00 | $11,585.04 | $8,000 |
| 500-7001 MOBILIZATION | 1 LS | $8,000.00 | $5,000.00 | $523,850.32 | -$3,000 |
| 104-7006 REMOV CONC (RIPRAP) | 40 SY | $100.00 | $40.00 | $14.32 | -$2,400 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 60 CY | $70.00 | $40.00 | $22.38 | -$1,800 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 318 CY | $175.00 | $180.00 | $179.97 | $1,590 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 34 DAY | $1.00 | $10.00 | $87.82 | $306 |
| 400-7010 CEM STABIL BKFL | 29 CY | $200.00 | $200.00 | $138.14 | $0 |
| 505-7001 TMA (STATIONARY) | 34 DAY | $1.00 | $1.00 | $217.57 | $0 |
Positive: the low bidder was cheaper on that item. These 8 items account for $2,696 of the $2,696 gap.
TEXAS ROAD CONSTRUCTION, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 104-7006 REMOV CONC (RIPRAP) | 40 SY | $100.00 | $14.32 | 6.98x | $3,427 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 60 CY | $70.00 | $22.38 | 3.13x | $2,857 |
| 500-7001 MOBILIZATION | 1 LS | $8,000.00 | $523,850.32 | 0.02x | -$515,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $1,000.00 | $11,585.04 | 0.09x | -$21,170 |
| 505-7001 TMA (STATIONARY) | 34 DAY | $1.00 | $217.57 | 0.00x | -$7,363 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 34 DAY | $1.00 | $87.82 | 0.01x | -$2,952 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $5,000.00 | $523,850.32 | 0.01x | -$518,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $5,000.00 | $11,585.04 | 0.43x | -$13,170 |
| 505-7001 TMA (STATIONARY) | 34 DAY | $1.00 | $217.57 | 0.00x | -$7,363 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 34 DAY | $10.00 | $87.82 | 0.11x | -$2,646 |
TEXWAY WASTEWATER SERVICES, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 29 CY | $250.00 | $138.14 | 1.81x | $3,244 |
| 500-7001 MOBILIZATION | 1 LS | $10,000.00 | $523,850.32 | 0.02x | -$513,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $2,000.00 | $11,585.04 | 0.17x | -$19,170 |
| 505-7001 TMA (STATIONARY) | 34 DAY | $50.00 | $217.57 | 0.23x | -$5,697 |