FY26 Lubbock TCP
6500-98-001 · let Apr 28, 2026 · Lubbock, Lubbock · Routine Maintenance Project - Sealed
$359,220Low bid: BARRICADES UNLIMITED-43.0% vs estimate $630,075
$276,290Left on the table76.9% gap to the second bid
3BiddersSpread 115% low to high
22Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BARRICADES UNLIMITED | $359,220 | -43.0% | $276,290 | 3+$15,856 | 2-$16,255 | |
| 2 | AWP SAFETY | $635,510 | +76.9% | 0.9% | $136,565 | 3+$28,391 | 1-$6,198 |
| 3 | APACHE BARRICADE & SIGN | $772,075 | +114.9% | 22.5% | 3+$331,852 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
BARRICADES UNLIMITED vs AWP SAFETY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7002 TMA (MOBILE OPERATION) | 5,000 HR | $50.70 | $100.00 | $64.00 | $246,500 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $300.00 | $600.00 | $217.57 | $15,000 |
| 790-7020 LANE CLOSURE(MAINTENANCE)(TYP 1) | 200 HR | $40.00 | $100.00 | $104.45 | $12,000 |
| 790-7021 LANE CLOSURE(MAINTENANCE)(TYP 2) | 200 HR | $40.00 | $100.00 | $78.09 | $12,000 |
| 790-7024 LANE CLOSURE(MAINTENANCE)(TYP 5) | 200 HR | $50.00 | $100.00 | $78.14 | $10,000 |
| 790-7001 LANE CLOSURE(SETUP & REM)(TYP 1) | 5 EA | $2,000.00 | $185.00 | $353.49 | -$9,075 |
| 790-7007 LANE CLOSURE(SETUP & REM)(TYP 7) | 20 EA | $700.00 | $285.00 | $594.90 | -$8,300 |
| 790-7011 LANE CLOSURE(SETUP & REM)(TYP 11) | 15 EA | $700.00 | $220.00 | $369.14 | -$7,200 |
| 7010-7001 MAINTENANCE SPEED LIMIT SIGNING | 12 EA | $10.00 | $500.00 | $36.55 | $5,880 |
| 790-7018 LANE CLOSURE(SETUP & REM)(TYP 18) | 4 EA | $1,000.00 | $180.00 | $334.85 | -$3,280 |
| 790-7014 LANE CLOSURE(SETUP & REM)(TYP 14) | 4 EA | $1,000.00 | $185.00 | $380.87 | -$3,260 |
| 790-7005 LANE CLOSURE(SETUP & REM)(TYP 5) | 10 EA | $500.00 | $185.00 | $478.42 | -$3,150 |
| 790-7032 LANE CLOSURE(MAINTENANCE)(TYP 13) | 25 HR | $50.00 | $160.00 | $62.93 | $2,750 |
| 790-7026 LANE CLOSURE(MAINTENANCE)(TYP 7) | 50 HR | $100.00 | $150.00 | $75.83 | $2,500 |
| 790-7037 LANE CLOSURE(MAINTENANCE)(TYP 18) | 25 HR | $10.00 | $100.00 | $144.65 | $2,250 |
| 790-7013 LANE CLOSURE(SETUP & REM)(TYP 13) | 4 EA | $1,000.00 | $650.00 | $662.31 | -$1,400 |
| 790-7033 LANE CLOSURE(MAINTENANCE)(TYP 14) | 25 HR | $50.00 | $100.00 | $55.52 | $1,250 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 10 DAY | $10.00 | $100.00 | $87.82 | $900 |
| 790-7002 LANE CLOSURE(SETUP & REM)(TYP 2) | 5 EA | $100.00 | $185.00 | $414.16 | $425 |
| 790-7059 ADDITIONAL LANE CLOSURE ITEM(TYPE 21) | 25 HR | $40.00 | $55.00 | $58.00 | $375 |
Positive: the low bidder was cheaper on that item. These 20 items account for $276,165 of the $276,290 gap.
BARRICADES UNLIMITED: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 790-7001 LANE CLOSURE(SETUP & REM)(TYP 1) | 5 EA | $2,000.00 | $353.49 | 5.66x | $8,233 |
| 790-7011 LANE CLOSURE(SETUP & REM)(TYP 11) | 15 EA | $700.00 | $369.14 | 1.90x | $4,963 |
| 790-7018 LANE CLOSURE(SETUP & REM)(TYP 18) | 4 EA | $1,000.00 | $334.85 | 2.99x | $2,661 |
| 790-7020 LANE CLOSURE(MAINTENANCE)(TYP 1) | 200 HR | $40.00 | $104.45 | 0.38x | -$12,889 |
| 790-7037 LANE CLOSURE(MAINTENANCE)(TYP 18) | 25 HR | $10.00 | $144.65 | 0.07x | -$3,366 |
AWP SAFETY: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 50 DAY | $600.00 | $217.57 | 2.76x | $19,121 |
| 7010-7001 MAINTENANCE SPEED LIMIT SIGNING | 12 EA | $500.00 | $36.55 | 13.68x | $5,561 |
| 790-7026 LANE CLOSURE(MAINTENANCE)(TYP 7) | 50 HR | $150.00 | $75.83 | 1.98x | $3,708 |
| 790-7007 LANE CLOSURE(SETUP & REM)(TYP 7) | 20 EA | $285.00 | $594.90 | 0.48x | -$6,198 |