US 87: 0143-03-049; WNF
0143-03-049 · let Oct 7, 2026 · Wilson, San Antonio · Widen Non-Freeway
$39,881,467Low bid: HUNTER INDUSTRIES, LTD.-20.9% vs estimate $50,415,711
$3,757,182Left on the table9.4% gap to the second bid
8BiddersSpread 33% low to high
231Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HUNTER INDUSTRIES, LTD. | $39,881,467 | -20.9% | $3,757,182 | 2+$2,329,863 | 2-$1,587,588 | |
| 2 | CK NEWBERRY, LLC | $43,638,649 | +9.4% | -13.4% | $740,051 | 1+$3,476,150 | 1-$1,207,355 |
| 3 | WEBBER, LLC | $44,378,700 | +11.3% | -12.0% | $3,147,091 | 3+$4,934,750 | 2-$980,813 |
| 4 | JORDAN FOSTER CONSTRUCTION, LLC | $47,525,791 | +19.2% | -5.7% | $1,197,979 | 2+$4,462,030 | 1-$282,998 |
| 5 | E-Z BEL CONSTRUCTION, LLC | $48,723,770 | +22.2% | -3.4% | $163,534 | 4+$4,774,248 | 0 |
| 6 | POSILLICO CIVIL, INC. | $48,887,304 | +22.6% | -3.0% | $3,010,037 | ||
| 7 | JOE BLAND CONSTRUCTION LLC | $51,897,341 | +30.1% | 2.9% | $965,771 | ||
| 8 | J3 COMPANY, LLC | $52,863,113 | +32.6% | 4.9% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
HUNTER INDUSTRIES, LTD. vs CK NEWBERRY, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,614,517.55 | $4,000,000.00 | $523,850.32 | $1,385,482 |
| 247-7271 FL BS (RDWY DEL)(TY D GR 1-2)(FNAL POS) | 78,033 CY | $55.69 | $65.00 | $56.31 | $726,487 |
| 105-7004 RMV (4"-8") TRT/UNTRT BASE & ASPH PAV | 195,136 SY | $2.84 | $6.00 | $4.38 | $616,630 |
| 508-7001 CONSTRUCTING DETOURS | 38,516 SY | $83.90 | $95.00 | $83.58 | $427,528 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 2,024 CY | $35.00 | $200.00 | $179.97 | $333,960 |
| 400-7001 STRUCT EXCAV | 19,930 CY | $25.82 | $12.00 | $13.82 | -$275,433 |
| 400-7010 CEM STABIL BKFL | 4,550 CY | $229.86 | $170.00 | $138.14 | -$272,363 |
| 110-7001 EXCAV (ROADWAY) | 108,549 CY | $11.84 | $10.00 | $11.68 | -$199,730 |
| 462-7037 CONC BOX CULV (10 FT X 9 FT) | 1,304 LF | $1,550.54 | $1,400.00 | $1,465.93 | -$196,304 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 9,210 LF | $10.50 | $30.00 | $7.54 | $179,595 |
| 341-7001 D-GR HMA TY-B PG64-22 | 27,086 TON | $84.17 | $90.00 | $97.82 | $157,911 |
| 416-7007 DRILL SHAFT (42 IN) | 3,285 LF | $271.47 | $225.00 | $318.92 | -$152,654 |
| 423-7019 RETAINING WALL (DRILL SHAFT) (FASCIA) | 4,266 SF | $80.00 | $115.00 | $103.21 | $149,310 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 35 MO | $6,319.83 | $10,000.00 | $11,585.04 | $128,806 |
| 530-7002 INTERSECTIONS (ACP) | 2,634 SY | $64.20 | $110.00 | $50.74 | $120,637 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 5,340 LF | $25.00 | $45.00 | $52.29 | $106,800 |
| 341-7030 D-GR HMA TY-C PG76-22 | 31,008 TON | $93.40 | $90.00 | $93.60 | -$105,427 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 68,259 CY | $8.60 | $10.00 | $16.96 | $95,563 |
| 432-7048 RIPRAP (STONE PROTECTION)(36 IN) | 550 CY | $55.00 | $225.00 | $174.48 | $93,500 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 5,340 LF | $10.50 | $28.00 | $12.08 | $93,450 |
Positive: the low bidder was cheaper on that item. These 20 items account for $3,413,748 of the $3,757,182 gap.
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,614,517.55 | $523,850.32 | 4.99x | $2,090,667 |
| 400-7001 STRUCT EXCAV | 19,930 CY | $25.82 | $13.82 | 1.87x | $239,196 |
| 100-7002 PREPARING ROW | 238 STA | $635.24 | $6,072.92 | 0.10x | -$1,294,168 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 2,024 CY | $35.00 | $179.97 | 0.19x | -$293,419 |
CK NEWBERRY, LLC: unbalanced items
Placed 2WEBBER, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $4,400,000.00 | $523,850.32 | 8.40x | $3,876,150 |
| 132-7009 EMBANK (FNL)(OC)(TY C2) | 33,992 CY | $25.14 | $8.97 | 2.80x | $549,654 |
| 400-7010 CEM STABIL BKFL | 4,550 CY | $250.00 | $138.14 | 1.81x | $508,946 |
| 110-7001 EXCAV (ROADWAY) | 108,549 CY | $5.00 | $11.68 | 0.43x | -$725,346 |
| 400-7001 STRUCT EXCAV | 19,930 CY | $1.00 | $13.82 | 0.07x | -$255,467 |
JORDAN FOSTER CONSTRUCTION, LLC: unbalanced items
Placed 4E-Z BEL CONSTRUCTION, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,500,000.00 | $523,850.32 | 6.68x | $2,976,150 |
| 105-7004 RMV (4"-8") TRT/UNTRT BASE & ASPH PAV | 195,136 SY | $9.25 | $4.38 | 2.11x | $949,571 |
| 400-7010 CEM STABIL BKFL | 4,550 CY | $250.00 | $138.14 | 1.81x | $508,946 |
| 422-7012 BRIDGE SIDEWALK | 464 SF | $750.00 | $18.14 | 41.33x | $339,581 |