Linden Hot Mix FY 27
6509-85-001 · let Oct 22, 2026 · Cass, Atlanta · Material Maintenance Project
$311,000Low bid: C-RAE MATERIALS LLC-23.5% vs estimate $406,700
$14,600Left on the table4.7% gap to the second bid
2BiddersSpread 5% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | C-RAE MATERIALS LLC | $311,000 | -23.5% | $14,600 | 0 | 0 | |
| 2 | RK HALL, LLC | $325,600 | +4.7% | -19.9% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
C-RAE MATERIALS LLC vs RK HALL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8011-7056 D-GR HMA TY D PG 64-22 (DEL) SITE 1 | 500 TON | $105.00 | $113.00 | $99.54 | $4,000 |
| 8011-7146 D-GR HMA TY D PG 70-22 (DEL) SITE 1 | 500 TON | $110.00 | $118.00 | $117.96 | $4,000 |
| 8011-7055 D-GR HMA TY D PG 64-22 (PICKUP) | 1,100 TON | $90.00 | $93.00 | $89.12 | $3,300 |
| 8011-7145 D-GR HMA TY D PG 70-22 (PICKUP) | 1,100 TON | $95.00 | $98.00 | $111.44 | $3,300 |
Positive: the low bidder was cheaper on that item. These 4 items account for $14,600 of the $14,600 gap.