EAO - Miscellaneous Concrete
6507-39-001 · let Oct 14, 2026 · El Paso, El Paso · Routine Maintenance Project
$845,627Low bid: SYNERGY PROJECT CONTRACTORS, INC.+4.4% vs estimate $809,850
$2,248Left on the table0.3% gap to the second bid
6BiddersSpread 49% low to high
24Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SYNERGY PROJECT CONTRACTORS, INC. | $845,627 | 4.4% | $2,248 | 4+$138,611 | 2-$456,553 | |
| 2 | WINDING ROAD CONSTRUCTION, INC. | $847,875 | +0.3% | 4.7% | $55,745 | 8+$180,205 | 2-$487,700 |
| 3 | STRUCTURAL INTEGRITY GROUP LLC | $903,620 | +6.9% | 11.6% | $169,702 | 11+$190,850 | 2-$465,399 |
| 4 | ALLIED PAVING CO. | $1,073,322 | +26.9% | 32.5% | $46,428 | 8+$421,436 | 1-$453,850 |
| 5 | INTERNATIONAL EAGLE ENTERPRISES, INC. | $1,119,750 | +32.4% | 38.3% | $140,700 | 13+$440,154 | 1-$438,850 |
| 6 | CC 915 LLC | $1,260,450 | +49.1% | 55.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
SYNERGY PROJECT CONTRACTORS, INC. vs WINDING ROAD CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7003 MOBILIZATION (CALLOUT 1) | 5 EA | $13,620.00 | $3,000.00 | $599.93 | -$53,100 |
| 420-7002 CL A CONC (MISC) | 70 CY | $482.38 | $1,100.00 | $560.77 | $43,233 |
| 429-7008 CONC STR REPR(RAPID VERT AND OVERHEAD) | 400 SF | $340.50 | $237.00 | $198.67 | -$41,400 |
| 104-7046 REMOV CONC (MISC) | 650 SY | $20.43 | $75.00 | $23.49 | $35,471 |
| 500-7001 MOBILIZATION | 1 LS | $79,450.00 | $50,000.00 | $523,850.32 | -$29,450 |
| 432-7005 RIPRAP (CONC)(CL B) | 300 CY | $675.33 | $590.00 | $556.52 | -$25,599 |
| 420-7146 CL C CONC (WINGWALLS) | 10 CY | $1,078.25 | $3,250.00 | $2,100.77 | $21,718 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $454.00 | $650.00 | $217.57 | $19,600 |
| 429-7009 CONC STR REPAIR (STANDARD) | 150 SF | $351.85 | $228.00 | $146.35 | -$18,578 |
| 420-7157 CL C CONC (HEADWALL) | 10 CY | $1,418.75 | $3,250.00 | $1,847.50 | $18,313 |
| 531-7039 CURB RAMPS (SPECIAL) | 50 SY | $454.00 | $150.00 | $427.00 | -$15,200 |
| 104-7006 REMOV CONC (RIPRAP) | 700 SY | $9.08 | $30.00 | $14.32 | $14,644 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 300 LF | $36.32 | $74.00 | $76.83 | $11,304 |
| 401-7001 FLOWABLE BACKFILL | 20 CY | $312.13 | $575.00 | $298.77 | $5,257 |
| 713-7005 LONGT CRACK CLEANING AND SEALING (CRCP) | 150 LF | $39.73 | $7.50 | $14.53 | -$4,835 |
| 780-7004 CNC CRACK REPAIR (DISCRETE)(SURF SEAL) | 150 LF | $45.40 | $74.00 | $49.91 | $4,290 |
| 529-7007 CONC CURB (MONO) (TY II) | 700 LF | $34.05 | $40.00 | $6.85 | $4,165 |
| 104-7028 REMOV CONC (WINGWALL) | 10 CY | $113.50 | $500.00 | $380.16 | $3,865 |
| 529-7009 CONC CURB & GUTTER (TY II) | 300 LF | $39.73 | $50.00 | $32.57 | $3,081 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 10 DAY | $227.00 | $400.00 | $87.82 | $1,730 |
Positive: the low bidder was cheaper on that item. These 20 items account for -$1,491 of the $2,248 gap.
SYNERGY PROJECT CONTRACTORS, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7003 MOBILIZATION (CALLOUT 1) | 5 EA | $13,620.00 | $599.93 | 22.70x | $65,100 |
| 429-7009 CONC STR REPAIR (STANDARD) | 150 SF | $351.85 | $146.35 | 2.40x | $30,825 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $454.00 | $217.57 | 2.09x | $23,643 |
| 529-7007 CONC CURB (MONO) (TY II) | 700 LF | $34.05 | $6.85 | 4.97x | $19,042 |
| 500-7001 MOBILIZATION | 1 LS | $79,450.00 | $523,850.32 | 0.15x | -$444,400 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 300 LF | $36.32 | $76.83 | 0.47x | -$12,153 |
WINDING ROAD CONSTRUCTION, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 100 DAY | $650.00 | $217.57 | 2.99x | $43,243 |
| 420-7002 CL A CONC (MISC) | 70 CY | $1,100.00 | $560.77 | 1.96x | $37,746 |
| 104-7046 REMOV CONC (MISC) | 650 SY | $75.00 | $23.49 | 3.19x | $33,481 |
| 529-7007 CONC CURB (MONO) (TY II) | 700 LF | $40.00 | $6.85 | 5.84x | $23,207 |
| 420-7157 CL C CONC (HEADWALL) | 10 CY | $3,250.00 | $1,847.50 | 1.76x | $14,025 |
| 500-7003 MOBILIZATION (CALLOUT 1) | 5 EA | $3,000.00 | $599.93 | 5.00x | $12,000 |
| 104-7006 REMOV CONC (RIPRAP) | 700 SY | $30.00 | $14.32 | 2.10x | $10,978 |
| 401-7001 FLOWABLE BACKFILL | 20 CY | $575.00 | $298.77 | 1.92x | $5,525 |
| 500-7001 MOBILIZATION | 1 LS | $50,000.00 | $523,850.32 | 0.10x | -$473,850 |
| 531-7039 CURB RAMPS (SPECIAL) | 50 SY | $150.00 | $427.00 | 0.35x | -$13,850 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7003 MOBILIZATION (CALLOUT 1) | 5 EA | $10,000.00 | $599.93 | 16.67x | $47,000 |
| 420-7002 CL A CONC (MISC) | 70 CY | $1,000.00 | $560.77 | 1.78x | $30,746 |
| 104-7006 REMOV CONC (RIPRAP) | 700 SY | $56.00 | $14.32 | 3.91x | $29,178 |
| 529-7009 CONC CURB & GUTTER (TY II) | 300 LF | $101.00 | $32.57 | 3.10x | $20,530 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 10 DAY | $2,000.00 | $87.82 | 22.77x | $19,122 |
| 529-7007 CONC CURB (MONO) (TY II) | 700 LF | $30.00 | $6.85 | 4.38x | $16,207 |
| 104-7016 REMOV CONC (CURB) | 700 LF | $16.00 | $6.82 | 2.35x | $6,429 |
| 713-7005 LONGT CRACK CLEANING AND SEALING (CRCP) | 150 LF | $56.00 | $14.53 | 3.85x | $6,220 |
| 104-7028 REMOV CONC (WINGWALL) | 10 CY | $935.00 | $380.16 | 2.46x | $5,548 |
| 401-7001 FLOWABLE BACKFILL | 20 CY | $560.00 | $298.77 | 1.87x | $5,225 |
| 500-7001 MOBILIZATION | 1 LS | $71,000.00 | $523,850.32 | 0.14x | -$452,850 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 300 LF | $35.00 | $76.83 | 0.46x | -$12,549 |
ALLIED PAVING CO.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 432-7005 RIPRAP (CONC)(CL B) | 300 CY | $1,051.15 | $556.52 | 1.89x | $148,388 |
| 500-7003 MOBILIZATION (CALLOUT 1) | 5 EA | $26,925.00 | $599.93 | 44.88x | $131,625 |
| 429-7008 CONC STR REPR(RAPID VERT AND OVERHEAD) | 400 SF | $366.18 | $198.67 | 1.84x | $67,003 |
| 420-7002 CL A CONC (MISC) | 70 CY | $1,060.85 | $560.77 | 1.89x | $35,005 |
| 529-7007 CONC CURB (MONO) (TY II) | 700 LF | $31.23 | $6.85 | 4.56x | $17,068 |
| 531-7001 CONC SIDEWALKS (4") | 60 SY | $210.02 | $70.57 | 2.98x | $8,367 |
| 529-7009 CONC CURB & GUTTER (TY II) | 300 LF | $57.08 | $32.57 | 1.75x | $7,354 |
| 401-7001 FLOWABLE BACKFILL | 20 CY | $630.05 | $298.77 | 2.11x | $6,626 |
| 500-7001 MOBILIZATION | 1 LS | $70,000.00 | $523,850.32 | 0.13x | -$453,850 |
INTERNATIONAL EAGLE ENTERPRISES, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7008 CONC STR REPR(RAPID VERT AND OVERHEAD) | 400 SF | $400.00 | $198.67 | 2.01x | $80,531 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 400 SF | $350.00 | $150.68 | 2.32x | $79,728 |
| 500-7003 MOBILIZATION (CALLOUT 1) | 5 EA | $15,000.00 | $599.93 | 25.00x | $72,000 |
| 420-7157 CL C CONC (HEADWALL) | 10 CY | $5,000.00 | $1,847.50 | 2.71x | $31,525 |
| 429-7009 CONC STR REPAIR (STANDARD) | 150 SF | $350.00 | $146.35 | 2.39x | $30,548 |
| 420-7146 CL C CONC (WINGWALLS) | 10 CY | $5,000.00 | $2,100.77 | 2.38x | $28,992 |
| 104-7046 REMOV CONC (MISC) | 650 SY | $60.00 | $23.49 | 2.55x | $23,731 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $450.00 | $217.57 | 2.07x | $23,243 |
| 104-7006 REMOV CONC (RIPRAP) | 700 SY | $45.00 | $14.32 | 3.14x | $21,478 |
| 529-7007 CONC CURB (MONO) (TY II) | 700 LF | $35.00 | $6.85 | 5.11x | $19,707 |
| 500-7001 MOBILIZATION | 1 LS | $85,000.00 | $523,850.32 | 0.16x | -$438,850 |