6507-26-001 Brush Removal
6507-26-001 · let Oct 7, 2026 · Midland, Odessa · Routine Maintenance Project
$746,150Low bid: SCR CIVIL CONSTRUCTION, LLC-62.7% vs estimate $1,999,722
$302,450Left on the table40.5% gap to the second bid
11BiddersSpread 212% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SCR CIVIL CONSTRUCTION, LLC | $746,150 | -62.7% | $302,450 | 1+$14,594 | 2-$4,052,918 | |
| 2 | ALLIES LAND CLEARING | $1,048,600 | +40.5% | -47.6% | $77,800 | 0 | 4-$3,762,299 |
| 3 | ORTEGA'S LAWN AND LANDSCAPING, LLC | $1,126,400 | +51.0% | -43.7% | $9,310 | 0 | 3-$3,660,649 |
| 4 | ROAD SOLUTIONS L.L.C. | $1,135,710 | +52.2% | -43.2% | $76,476 | 0 | 1-$3,579,318 |
| 5 | L&L COMPANY | $1,212,186 | +62.5% | -39.4% | $574,790 | 0 | 4-$3,598,713 |
| 6 | WINDING ROAD CONSTRUCTION, INC. | $1,786,976 | +139.5% | -10.6% | $142,109 | ||
| 7 | CROSS PLUS CONSTRUCTION, LLC | $1,929,085 | +158.5% | -3.5% | $52,315 | ||
| 8 | E.V.G. ENTERPRISE | $1,981,400 | +165.5% | -0.9% | $110,651 | ||
| 9 | ABESCAPE LANDSCAPING, LLC | $2,092,051 | +180.4% | 4.6% | $93,129 | ||
| 10 | AUSTIN BARRICADE COMPANY, L.L.C. | $2,185,180 | +192.9% | 9.3% | $141,864 | ||
| 11 | CLAW CONTRACTORS, LLC | $2,327,044 | +211.9% | 16.4% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
SCR CIVIL CONSTRUCTION, LLC vs ALLIES LAND CLEARING, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 100-7001 PREPARING ROW | 1,054 AC | $575.00 | $900.00 | $3,995.94 | $342,550 |
| 505-7001 TMA (STATIONARY) | 80 DAY | $400.00 | $0.0010 | $217.57 | -$32,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $6,300.00 | $0.0010 | $11,585.04 | -$31,500 |
| 500-7001 MOBILIZATION | 1 LS | $76,600.00 | $100,000.00 | $523,850.32 | $23,400 |
Positive: the low bidder was cheaper on that item. These 4 items account for $302,450 of the $302,450 gap.
SCR CIVIL CONSTRUCTION, LLC: unbalanced items
Placed 1ALLIES LAND CLEARING: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7001 PREPARING ROW | 1,054 AC | $900.00 | $3,995.94 | 0.23x | -$3,263,118 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $0.0010 | $11,585.04 | 0.00x | -$57,925 |
| 505-7001 TMA (STATIONARY) | 80 DAY | $0.0010 | $217.57 | 0.00x | -$17,406 |
ORTEGA'S LAWN AND LANDSCAPING, LLC: unbalanced items
Placed 3ROAD SOLUTIONS L.L.C.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7001 PREPARING ROW | 1,054 AC | $600.00 | $3,995.94 | 0.15x | -$3,579,318 |
L&L COMPANY: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7001 PREPARING ROW | 1,054 AC | $1,150.00 | $3,995.94 | 0.29x | -$2,999,618 |
| 500-7001 MOBILIZATION | 1 LS | $1.00 | $523,850.32 | 0.00x | -$523,849 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $1.00 | $11,585.04 | 0.00x | -$57,920 |
| 505-7001 TMA (STATIONARY) | 80 DAY | $1.00 | $217.57 | 0.00x | -$17,326 |