FY 2027 Culvert Cleaning - Districtwide
6506-36-001 · let Oct 15, 2026 · McLennan, Waco · Routine Maintenance Project
$472,690Low bid: KriMatt Services LLC-15.9% vs estimate $561,816
$78,853Left on the table16.7% gap to the second bid
2BiddersSpread 17% low to high
22Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | KriMatt Services LLC | $472,690 | -15.9% | $78,853 | 3+$40,654 | 2-$9,502 | |
| 2 | SKYLINE CONSTRUCTION PAVING & STRIPING | $551,544 | +16.7% | -1.8% | 4+$126,972 | 4-$66,732 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
KriMatt Services LLC vs SKYLINE CONSTRUCTION PAVING & STRIPING, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 38 AC | $1,800.00 | $300.00 | $1,602.83 | -$57,000 |
| 760-7001 DITCH CLEANING AND RESHAPING (FOOT) | 9,125 LF | $2.75 | $7.59 | $1.96 | $44,165 |
| 735-7060 DRIFTWOOD REMOVAL | 2,255 CY | $65.00 | $79.10 | $72.46 | $31,796 |
| 764-7018 STORM SEWER CLEAN (BOX CULV)(24-<48 SF) | 2,291 LF | $16.00 | $26.13 | $17.30 | $23,208 |
| 110-7002 EXCAV (CHANNEL) | 1,235 CY | $25.00 | $39.97 | $16.69 | $18,488 |
| 764-7017 STORM SEWER CLEAN (BOX CULV)(12-<24 SF) | 1,630 LF | $11.00 | $20.81 | $9.24 | $15,990 |
| 764-7019 STORM SEWER CLEAN (BOX CULV)(48-<96 SF) | 1,720 LF | $27.00 | $33.33 | $24.47 | $10,888 |
| 467-7003 SET (REPLACE PIPE RUNNER ASSEMBLY) | 20 EA | $500.00 | $999.99 | $678.56 | $10,000 |
| 164-7039 BROADCAST SEED (TEMP_WARM_COOL) | 5 AC | $1,500.00 | $0.1000 | $752.58 | -$7,500 |
| 764-7020 STORM SEWER CLEAN (BOX CULV) (>96 SF) | 900 LF | $65.00 | $59.01 | $27.93 | -$5,391 |
| 169-7029 SOIL RET BLKT(CHAN_TEMP_2 PSF) | 500 SY | $10.00 | $0.1100 | $2.88 | -$4,945 |
| 505-7001 TMA (STATIONARY) | 40 DAY | $100.00 | $1.00 | $217.57 | -$3,960 |
| 764-7008 STORM SEWER CLEANING (PIPE)(19"-24"DIA) | 585 LF | $4.50 | $6.49 | $3.96 | $1,164 |
| 764-7021 SLOTTED DRAIN CLEANING | 150 LF | $5.50 | $12.92 | $6.57 | $1,113 |
| 764-7016 STORM SEWER CLEAN (BOX CULV) (6-<12 SF) | 680 LF | $12.50 | $13.81 | $11.56 | $891 |
| 764-7010 STORM SEWER CLEANING (PIPE)(31"-36"DIA) | 230 LF | $6.00 | $8.49 | $6.94 | $573 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 5 DAY | $110.00 | $1.00 | $117.34 | -$545 |
| 764-7007 STORM SEWER CLEANING (PIPE)(12"-18"DIA) | 130 LF | $2.50 | $6.00 | $3.42 | $455 |
| 506-7001 ROCK FILTER DAMS (INSTALL) (TY 1) | 15 LF | $30.00 | $1.00 | $37.24 | -$435 |
| 764-7001 DRAIN INLET CLEANING | 5 EA | $150.00 | $99.99 | $124.25 | -$250 |
Positive: the low bidder was cheaper on that item. These 20 items account for $78,704 of the $78,853 gap.
KriMatt Services LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 764-7020 STORM SEWER CLEAN (BOX CULV) (>96 SF) | 900 LF | $65.00 | $27.93 | 2.33x | $33,359 |
| 164-7039 BROADCAST SEED (TEMP_WARM_COOL) | 5 AC | $1,500.00 | $752.58 | 1.99x | $3,737 |
| 169-7029 SOIL RET BLKT(CHAN_TEMP_2 PSF) | 500 SY | $10.00 | $2.88 | 3.47x | $3,558 |
| 500-7002 MOBILIZATION (CALLOUT) | 8 EA | $1.00 | $600.85 | 0.00x | -$4,799 |
| 505-7001 TMA (STATIONARY) | 40 DAY | $100.00 | $217.57 | 0.46x | -$4,703 |
SKYLINE CONSTRUCTION PAVING & STRIPING: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 760-7001 DITCH CLEANING AND RESHAPING (FOOT) | 9,125 LF | $7.59 | $1.96 | 3.88x | $51,407 |
| 110-7002 EXCAV (CHANNEL) | 1,235 CY | $39.97 | $16.69 | 2.39x | $28,746 |
| 764-7020 STORM SEWER CLEAN (BOX CULV) (>96 SF) | 900 LF | $59.01 | $27.93 | 2.11x | $27,968 |
| 764-7017 STORM SEWER CLEAN (BOX CULV)(12-<24 SF) | 1,630 LF | $20.81 | $9.24 | 2.25x | $18,852 |
| 752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 38 AC | $300.00 | $1,602.83 | 0.19x | -$49,508 |
| 505-7001 TMA (STATIONARY) | 40 DAY | $1.00 | $217.57 | 0.00x | -$8,663 |
| 500-7002 MOBILIZATION (CALLOUT) | 8 EA | $1.00 | $600.85 | 0.00x | -$4,799 |
| 164-7039 BROADCAST SEED (TEMP_WARM_COOL) | 5 AC | $0.1000 | $752.58 | 0.00x | -$3,762 |