FY 27 Ditch Cleaning and Reshaping
6506-33-001 · let Oct 7, 2026 · Jasper, Beaumont · Routine Maintenance Project
$2,396,085Low bid: TEXAS DRAINAGE INC.-11.6% vs estimate $2,711,299
$1,090,515Left on the table45.5% gap to the second bid
2BiddersSpread 46% low to high
10Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TEXAS DRAINAGE INC. | $2,396,085 | -11.6% | $1,090,515 | 1+$264,558 | 2-$394,305 | |
| 2 | GROD CONSTRUCTION LLC | $3,486,600 | +45.5% | 28.6% | 3+$299,120 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
TEXAS DRAINAGE INC. vs GROD CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 760-7001 DITCH CLEANING AND RESHAPING (FOOT) | 1,000,000 LF | $1.98 | $2.60 | $1.96 | $620,000 |
| 480-7001 CLEAN EXIST CULVERTS | 200 EA | $250.00 | $2,000.00 | $1,712.97 | $350,000 |
| 505-7001 TMA (STATIONARY) | 490 DAY | $10.00 | $450.00 | $217.57 | $215,600 |
| 500-7002 MOBILIZATION (CALLOUT) | 49 EA | $6,000.00 | $4,000.00 | $600.85 | -$98,000 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 88 DAY | $100.00 | $300.00 | $87.82 | $17,600 |
| 472-7004 REMOV & RE - LAY PIPE (18 IN) | 140 LF | $99.99 | $60.00 | $59.22 | -$5,599 |
| 472-7006 REMOV & RE - LAY PIPE (24 IN) | 140 LF | $109.99 | $75.00 | $90.86 | -$4,899 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 6 EA | $1,999.00 | $1,300.00 | $1,176.76 | -$4,194 |
| 467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) | 6 EA | $1,999.00 | $2,000.00 | $1,883.43 | $6 |
| 496-7004 REMOV STR (SET) | 10 EA | $500.00 | $500.00 | $514.07 | $0 |
Positive: the low bidder was cheaper on that item. These 10 items account for $1,090,515 of the $1,090,515 gap.