METAL BEAM GUARD FENCE REPAIR - FY 27
6504-87-001 · let Oct 6, 2026 · Bell, Waco · Routine Maintenance Project - Sealed
$750,704Low bid: ROSS SA ENTERPRISE LLC-18.0% vs estimate $915,307
$39,935Left on the table5.3% gap to the second bid
3BiddersSpread 15% low to high
32Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ROSS SA ENTERPRISE LLC | $750,704 | -18.0% | $39,935 | 1+$22,959 | 6-$84,177 | |
| 2 | T&L CLEANING SERVICES LLC | $790,639 | +5.3% | -13.6% | $71,149 | 0 | 8-$131,693 |
| 3 | RHINO EQUITY, LLC | $861,788 | +14.8% | -5.8% | 1+$33,891 | 5-$78,977 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
ROSS SA ENTERPRISE LLC vs T&L CLEANING SERVICES LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 770-7037 REPLACE GUARDRAIL END TREATMENT SYSTEM | 97 EA | $3,200.00 | $4,000.00 | $3,116.90 | $77,600 |
| 771-7032 REMOVE CABLE BARRIER SYSTEM | 500 LF | $100.00 | $10.00 | $54.08 | -$45,000 |
| 770-7035 REPLACE W-BEAM RAIL | 7,160 LF | $25.00 | $28.00 | $24.10 | $21,480 |
| 771-7025 REPLACE LINE OR TERMINAL POST (VALTIR) | 500 EA | $300.00 | $275.00 | $215.97 | -$12,500 |
| 429-7009 CONC STR REPAIR (STANDARD) | 250 SF | $50.00 | $20.00 | $146.35 | -$7,500 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 28 DAY | $1.00 | $150.00 | $87.82 | $4,172 |
| 771-7030 CHECK AND RE-TENSION CABLE SYSTEM | 20 EA | $200.00 | $1.00 | $350.67 | -$3,980 |
| 132-7015 EMBANK (VEH)(OC)(TY B) | 75 CY | $1.00 | $50.00 | $25.35 | $3,675 |
| 772-7003 POST AND CABLE FENCE (NEW INSTALLATION) | 200 LF | $25.00 | $10.00 | $22.55 | -$3,000 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 28 DAY | $100.00 | $1.00 | $117.34 | -$2,772 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 50 CY | $350.00 | $300.00 | $616.83 | -$2,500 |
| 770-7039 REPLACE LOW FILL CULVERT RAIL | 100 LF | $25.00 | $50.00 | $13.50 | $2,500 |
| 771-7029 REPLACE CABLE RELEASE POST | 5 EA | $25.00 | $500.00 | $148.81 | $2,375 |
| 770-7036 REPLACE THRIE-BEAM RAIL | 75 LF | $20.00 | $50.00 | $48.04 | $2,250 |
| 771-7033 SPLICE CABLE | 20 EA | $75.00 | $150.00 | $342.77 | $1,500 |
| 771-7031 REPLACE CABLE | 1,000 LF | $2.00 | $3.00 | $3.23 | $1,000 |
| 104-7003 REMOV CONC (MOWSTRIP) | 20 SY | $1.00 | $50.00 | $20.48 | $980 |
| 770-7041 REPLACE GDRL END TREATMENT MRKR | 10 EA | $100.00 | $30.00 | $29.93 | -$700 |
| 658-7056 INSTL OM ASSM (OM-2Y)(WC)GND | 25 EA | $25.00 | $50.00 | $81.96 | $625 |
| 772-7004 POST AND CABLE FENCE (NEW CONC ANCHOR) | 10 EA | $50.00 | $100.00 | $150.87 | $500 |
Positive: the low bidder was cheaper on that item. These 20 items account for $40,705 of the $39,935 gap.
ROSS SA ENTERPRISE LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7032 REMOVE CABLE BARRIER SYSTEM | 500 LF | $100.00 | $54.08 | 1.85x | $22,959 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $1.00 | $217.57 | 0.00x | -$25,989 |
| 429-7009 CONC STR REPAIR (STANDARD) | 250 SF | $50.00 | $146.35 | 0.34x | -$24,087 |
| 500-7002 MOBILIZATION (CALLOUT) | 24 EA | $1.00 | $600.85 | 0.00x | -$14,396 |
| 500-7033 MOBILIZATION (EMERGENCY) | 12 EA | $1.00 | $844.81 | 0.00x | -$10,126 |
| 771-7033 SPLICE CABLE | 20 EA | $75.00 | $342.77 | 0.22x | -$5,355 |
| 770-7040 REMOVE RAIL | 500 LF | $1.00 | $9.45 | 0.11x | -$4,224 |
T&L CLEANING SERVICES LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7009 CONC STR REPAIR (STANDARD) | 250 SF | $20.00 | $146.35 | 0.14x | -$31,587 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $1.00 | $217.57 | 0.00x | -$25,989 |
| 771-7032 REMOVE CABLE BARRIER SYSTEM | 500 LF | $10.00 | $54.08 | 0.18x | -$22,041 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 50 CY | $300.00 | $616.83 | 0.49x | -$15,842 |
| 500-7002 MOBILIZATION (CALLOUT) | 24 EA | $1.00 | $600.85 | 0.00x | -$14,396 |
| 500-7033 MOBILIZATION (EMERGENCY) | 12 EA | $1.00 | $844.81 | 0.00x | -$10,126 |
| 771-7030 CHECK AND RE-TENSION CABLE SYSTEM | 20 EA | $1.00 | $350.67 | 0.00x | -$6,993 |
| 770-7040 REMOVE RAIL | 500 LF | $0.0100 | $9.45 | 0.00x | -$4,719 |
RHINO EQUITY, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 120 DAY | $500.00 | $217.57 | 2.30x | $33,891 |
| 429-7009 CONC STR REPAIR (STANDARD) | 250 SF | $40.00 | $146.35 | 0.27x | -$26,587 |
| 771-7032 REMOVE CABLE BARRIER SYSTEM | 500 LF | $1.00 | $54.08 | 0.02x | -$26,541 |
| 500-7002 MOBILIZATION (CALLOUT) | 24 EA | $100.00 | $600.85 | 0.17x | -$12,020 |
| 771-7030 CHECK AND RE-TENSION CABLE SYSTEM | 20 EA | $1.00 | $350.67 | 0.00x | -$6,993 |
| 771-7033 SPLICE CABLE | 20 EA | $1.00 | $342.77 | 0.00x | -$6,835 |