Mill and Inlay (S) FY2027
6501-58-001 · let Oct 6, 2026 · Harrison, Atlanta · Routine Maintenance Project - Sealed
$6,111,500Low bid: EAST TEXAS BRIDGE, INC.-0.3% vs estimate $6,132,750
$68,000Left on the table1.1% gap to the second bid
4BiddersSpread 17% low to high
19Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | EAST TEXAS BRIDGE, INC. | $6,111,500 | -0.3% | $68,000 | 1+$195,193 | 0 | |
| 2 | HIGHWAY 19 CONSTRUCTION LLC | $6,179,500 | +1.1% | 0.8% | $359,785 | 1+$595,193 | 0 |
| 3 | MADDEN CONTRACTING COMPANY, LLC. | $6,539,285 | +7.0% | 6.6% | $627,690 | 1+$527,193 | 1-$69,252 |
| 4 | LONGVIEW BRIDGE AND ROAD, LTD. | $7,166,975 | +17.3% | 16.9% | 2+$495,441 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
EAST TEXAS BRIDGE, INC. vs HIGHWAY 19 CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7030 SP MIXES SP-C SAC-A PG76-22 | 20,000 TON | $196.00 | $175.00 | $138.38 | -$420,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 8 EA | $25,000.00 | $75,000.00 | $600.85 | $400,000 |
| 305-7018 SALV,HAUL & STKPL RCL APH PV (2") | 50,000 SY | $3.00 | $3.95 | $2.36 | $47,500 |
| 305-7016 SALV, HAUL & STKPL RCL APH PV (3") | 50,000 SY | $4.00 | $4.45 | $3.61 | $22,500 |
| 342-7001 PFC-C PG76-22 SAC-A | 5,000 TON | $224.00 | $220.00 | $170.34 | -$20,000 |
| 342-7015 TACK COAT | 5,500 GAL | $5.00 | $8.00 | $3.37 | $16,500 |
| 662-7115 WK ZN PAV MRK SHT TERM RMV (W)(4") | 10,000 LF | $1.85 | $3.50 | $1.83 | $16,500 |
| 662-7116 WK ZN PAV MRK SHT TERM RMV (Y)(4") | 10,000 LF | $1.85 | $3.50 | $1.57 | $16,500 |
| 305-7039 SALV, HAUL & STKPL RCL APH PV (5"-7") | 6,000 SY | $9.00 | $6.50 | $9.00 | -$15,000 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $250.00 | $500.00 | $217.57 | $12,500 |
| 305-7022 SALV, HAUL & STKPL RCL APH PV (4") | 30,000 SY | $5.30 | $5.05 | $4.16 | -$7,500 |
| 505-7002 TMA (MOBILE OPERATION) | 350 HR | $30.00 | $40.00 | $64.00 | $3,500 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 50 DAY | $200.00 | $250.00 | $87.82 | $2,500 |
| 666-7309 ALL-WTHER PM TY I (W)6"(SLD)(100MIL) | 50,000 LF | $0.7000 | $0.6500 | $0.6917 | -$2,500 |
| 666-7315 ALL-WTHER PM TY I (Y)6"(SLD)(100MIL) | 50,000 LF | $0.7000 | $0.6500 | $0.6819 | -$2,500 |
| 668-7089 PREFAB PM TY C (W)(24")(SLD) | 1,000 LF | $15.00 | $13.50 | $13.72 | -$1,500 |
| 666-7310 ALL-WTHER PM TY I (W)6"(BRK)(100MIL) | 10,000 LF | $0.8000 | $0.7500 | $0.8630 | -$500 |
| 666-7316 ALL-WTHER PM TY I (Y)6"(BRK)(100MIL) | 10,000 LF | $0.8000 | $0.7500 | $0.7727 | -$500 |
| 344-7077 TACK COAT | 22,000 GAL | $5.00 | $5.00 | $3.25 | $0 |
Positive: the low bidder was cheaper on that item. These 19 items account for $68,000 of the $68,000 gap.
EAST TEXAS BRIDGE, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 8 EA | $25,000.00 | $600.85 | 41.61x | $195,193 |
HIGHWAY 19 CONSTRUCTION LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 8 EA | $75,000.00 | $600.85 | 124.82x | $595,193 |