Tree Trimming and Brush Removal 09 10/26
6501-52-001 · let Oct 14, 2026 · Ellis, Dallas · Routine Maintenance Project - Sealed
$160,931Low bid: GV LANDSCAPE AND CONSTRUCTION LLC-7.0% vs estimate $172,975
-$2,217Left on the table-1.4% gap to the second bid
8BiddersSpread 121% low to high
14Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | GV LANDSCAPE AND CONSTRUCTION LLC | $160,931 | -7.0% | -$2,217 | 1+$4,205 | 2-$534,020 | |
| 2 | VM WEST, LLC | $158,714 | +-1.4% | -8.2% | $5,655 | 0 | 1-$517,722 |
| 3 | WESTERN CERTIFIED ARBORISTS | $164,369 | +2.1% | -5.0% | $3,839 | 1+$19,803 | 2-$539,020 |
| 4 | JACKSON EXCAVATION, LLC | $168,208 | +4.5% | -2.8% | $13,797 | 0 | 3-$553,058 |
| 5 | LOOKS GREAT SERVICES OF MS, INC. | $182,005 | +13.1% | 5.2% | $84,571 | 3+$10,443 | 2-$542,520 |
| 6 | S FOWLER SERVICES LLC | $266,575 | +65.6% | 54.1% | $9,715 | ||
| 7 | MARLANE CONSTRUCTION, LLC | $276,290 | +71.7% | 59.7% | $74,987 | ||
| 8 | ABESCAPE LANDSCAPING, LLC | $351,277 | +118.3% | 103.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
GV LANDSCAPE AND CONSTRUCTION LLC vs VM WEST, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $1,500.00 | $7,419.64 | $11,585.04 | $11,839 |
| 752-7001 TREE TRIMMING / BRUSH REMOVAL | 36.03 MI | $1,700.00 | $1,561.58 | $1,716.86 | -$4,987 |
| 500-7001 MOBILIZATION | 1 LS | $10,000.00 | $6,128.32 | $523,850.32 | -$3,872 |
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 71 EA | $120.00 | $71.98 | $60.77 | -$3,409 |
| 752-7012 TREE REMOVAL (48" - 60" DIA) | 3 EA | $1,000.00 | $515.82 | $450.06 | -$1,453 |
| 752-7013 TREE REMOVAL (60" - 72" DIA) | 1 EA | $1,700.00 | $517.44 | $529.99 | -$1,183 |
| 752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 34 AC | $1,700.00 | $1,726.32 | $1,602.83 | $895 |
| 505-7001 TMA (STATIONARY) | 34 DAY | $150.00 | $174.66 | $217.57 | $838 |
| 752-7011 TREE REMOVAL (42" - 48" DIA) | 2 EA | $800.00 | $475.63 | $436.67 | -$649 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 24 EA | $160.00 | $152.99 | $100.44 | -$168 |
| 752-7010 TREE REMOVAL (36" - 42" DIA) | 2 EA | $500.00 | $425.53 | $334.81 | -$149 |
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 2 EA | $340.00 | $381.91 | $293.05 | $84 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 12 EA | $200.00 | $193.81 | $141.37 | -$74 |
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 4 EA | $260.00 | $277.63 | $208.61 | $71 |
Positive: the low bidder was cheaper on that item. These 14 items account for -$2,217 of the -$2,217 gap.
GV LANDSCAPE AND CONSTRUCTION LLC: unbalanced items
Placed 1VM WEST, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $6,128.32 | $523,850.32 | 0.01x | -$517,722 |
WESTERN CERTIFIED ARBORISTS: unbalanced items
Placed 3JACKSON EXCAVATION, LLC: unbalanced items
Placed 4LOOKS GREAT SERVICES OF MS, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 12 EA | $450.00 | $141.37 | 3.18x | $3,704 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 24 EA | $250.00 | $100.44 | 2.49x | $3,589 |
| 752-7012 TREE REMOVAL (48" - 60" DIA) | 3 EA | $1,500.00 | $450.06 | 3.33x | $3,150 |
| 500-7001 MOBILIZATION | 1 LS | $500.00 | $523,850.32 | 0.00x | -$523,350 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $2,000.00 | $11,585.04 | 0.17x | -$19,170 |