THERMOPLASTIC STRIPING AND PAV
6496-56-001 · let Oct 6, 2026 · Brown, Brownwood · Routine Maintenance Project
$3,276,697Low bid: DOUBLE A CONTRACTING, L.P.-25.8% vs estimate $4,414,901
$320,110Left on the table9.8% gap to the second bid
7BiddersSpread 92% low to high
38Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DOUBLE A CONTRACTING, L.P. | $3,276,697 | -25.8% | $320,110 | 0 | 1-$51,663 | |
| 2 | STRIPE LINES, INC. | $3,596,807 | +9.8% | -18.5% | $231,078 | 0 | 1-$49,629 |
| 3 | CENTERLINE TECHNOLOGIES, LLC | $3,827,885 | +16.8% | -13.3% | $53,329 | 0 | 1-$51,663 |
| 4 | TRP INFRASTRUCTURE SERVICES, LLC | $3,881,214 | +18.4% | -12.1% | $165,740 | 0 | 1-$51,663 |
| 5 | FLAT LINE, INC. | $4,046,954 | +23.5% | -8.3% | $897,856 | 1+$43,197 | 1-$29,289 |
| 6 | STRIPE-A-ZONE, LLC | $4,944,811 | +50.9% | 12.0% | $1,350,390 | ||
| 7 | L&L COMPANY | $6,295,201 | +92.1% | 42.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
DOUBLE A CONTRACTING, L.P. vs STRIPE LINES, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 666-7409 REFL PAV MRK TY I (W)6"(SLD)(060MIL) | 4,569,903 LF | $0.2800 | $0.3200 | $0.3171 | $182,796 |
| 666-7421 REFL PAV MRK TY I (Y)6"(SLD)(060MIL) | 4,542,906 LF | $0.3000 | $0.3200 | $0.3278 | $90,858 |
| 668-7089 PREFAB PM TY C (W)(24")(SLD) | 10,642 LF | $11.50 | $13.41 | $13.72 | $20,326 |
| 668-7111 PREFAB PM TY C (W)(36")(YLD TRI) | 234 EA | $16.00 | $79.33 | $38.96 | $14,819 |
| 666-7418 REFL PAV MRK TY I (Y)6"(BRK)(060MIL) | 482,483 LF | $0.3000 | $0.3200 | $0.3503 | $9,650 |
| 500-7002 MOBILIZATION (CALLOUT) | 3 EA | $5,500.00 | $3,500.00 | $600.85 | -$6,000 |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 5,500 LF | $4.50 | $3.50 | $2.80 | -$5,500 |
| 666-7022 REFL PAV MRK TY I (W)8"(SLD)(060MIL) | 30,416 LF | $0.4800 | $0.6500 | $0.6127 | $5,171 |
| 668-7127 PREFAB PM TY C (Y)(24")(SLD) | 1,353 LF | $10.00 | $13.53 | $11.82 | $4,776 |
| 668-7091 PREFAB PM TY C (W)(ARROW) | 148 EA | $180.00 | $208.85 | $201.69 | $4,270 |
| 668-7100 PREFAB PM TY C (W)(LN REDUCT ARROW) | 37 EA | $550.00 | $435.00 | $467.68 | -$4,255 |
| 505-7003 TMA (MOBILE OPERATION) | 226 DAY | $1.00 | $10.00 | $229.60 | $2,034 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 50,000 LF | $0.7500 | $0.7900 | $0.6515 | $2,000 |
| 666-7270 RE PROFILE PM TY I(Y)6"(SLD)(100MIL) | 50,000 LF | $0.7500 | $0.7900 | $0.6629 | $2,000 |
| 666-7274 RE PROFILE PM TY I(Y)6"(BRK)(100MIL) | 50,000 LF | $0.7500 | $0.7900 | $0.6738 | $2,000 |
| 668-7093 PREFAB PM TY C (W)(DBL ARROW) | 7 EA | $550.00 | $294.97 | $314.80 | -$1,785 |
| 666-7007 REFL PAV MRK TY I (W)6"(DOT)(060MIL) | 8,085 LF | $0.3800 | $0.5300 | $0.7227 | $1,213 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 9,299 LF | $0.6500 | $0.5200 | $0.4986 | -$1,209 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 4,158 LF | $0.7500 | $0.5200 | $0.4757 | -$956 |
| 668-7108 PREFAB PM TY C (W)(RR XING) | 28 EA | $550.00 | $517.08 | $602.94 | -$922 |
Positive: the low bidder was cheaper on that item. These 20 items account for $321,286 of the $320,110 gap.
DOUBLE A CONTRACTING, L.P.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 226 DAY | $1.00 | $229.60 | 0.00x | -$51,663 |
STRIPE LINES, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 226 DAY | $10.00 | $229.60 | 0.04x | -$49,629 |
CENTERLINE TECHNOLOGIES, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 226 DAY | $1.00 | $229.60 | 0.00x | -$51,663 |
TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 226 DAY | $1.00 | $229.60 | 0.00x | -$51,663 |