Off-Syst Charlie Brown Rd @ Draw
0922-20-030 · let Oct 7, 2026 · La Salle, Laredo · Bridge Replacement
$485,016Low bid: PRESIDIO CONTRACTING, LLC-27.5% vs estimate $668,834
$109,673Left on the table22.6% gap to the second bid
6BiddersSpread 35% low to high
40Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | PRESIDIO CONTRACTING, LLC | $485,016 | -27.5% | $109,673 | 5+$19,237 | 4-$595,412 | |
| 2 | LUCANIA CONTRACTORS LLC | $594,689 | +22.6% | -11.1% | $13,615 | 7+$96,838 | 3-$539,809 |
| 3 | STX CIVIL | $608,304 | +25.4% | -9.1% | $8,435 | 6+$71,586 | 3-$518,004 |
| 4 | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. | $616,739 | +27.2% | -7.8% | $22,606 | 3+$28,390 | 3-$452,407 |
| 5 | J. CARROLL WEAVER, INC. | $639,345 | +31.8% | -4.4% | $14,007 | 5+$33,876 | 4-$430,932 |
| 6 | E-Z BEL CONSTRUCTION, LLC | $653,352 | +34.7% | -2.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
PRESIDIO CONTRACTING, LLC vs LUCANIA CONTRACTORS LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 508-7003 CONSTRUCTING DETOURS (TY1) | 945 SY | $29.55 | $70.00 | $101.74 | $38,225 |
| 416-7004 DRILL SHAFT (24 IN) | 240 LF | $227.50 | $370.00 | $234.98 | $34,200 |
| 425-7017 PRESTR CONC SLAB BEAM (5SB12) | 197.5 LF | $312.10 | $450.00 | $242.93 | $27,235 |
| 422-7007 REINF CONC SLAB (SLAB BEAM) | 1,040 SF | $36.30 | $50.00 | $23.90 | $14,248 |
| 420-7012 CL C CONC (ABUT) | 17.6 CY | $1,190.00 | $1,900.00 | $1,307.98 | $12,496 |
| 500-7001 MOBILIZATION | 1 LS | $48,320.00 | $37,000.00 | $523,850.32 | -$11,320 |
| 330-7010 LRA PAV TY-II GR-CS | 96 TON | $286.15 | $200.00 | $286.15 | -$8,270 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 160 LF | $40.00 | $90.00 | $43.56 | $8,000 |
| 164-7042 DRILL SEED (PERM_RURAL_CLAY) | 0.25 AC | $6,825.00 | $27,000.00 | $678.02 | $5,044 |
| 512-7010 PORT CTB (FUR & INST)(LOW PROF)(TY 2) | 80 LF | $44.00 | $100.00 | $55.61 | $4,480 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 30 CY | $588.00 | $450.00 | $616.83 | -$4,140 |
| 164-7045 DRILL SEED (TEMP_WARM) | 0.25 AC | $6,825.00 | $22,200.00 | $550.09 | $3,844 |
| 450-7020 RAIL (TY T631) | 104 LF | $120.00 | $150.00 | $108.10 | $3,120 |
| 310-7004 PRIME COAT (MC-30) | 200 GAL | $25.00 | $10.00 | $5.35 | -$3,000 |
| 400-7010 CEM STABIL BKFL | 28 CY | $263.00 | $160.00 | $138.14 | -$2,884 |
| 110-7001 EXCAV (ROADWAY) | 55 CY | $76.00 | $25.00 | $11.68 | -$2,805 |
| 100-7002 PREPARING ROW | 3 STA | $2,100.00 | $1,200.00 | $6,072.92 | -$2,700 |
| 506-7030 BACKHOE WORK (EROSION & SEDMT CONT) | 20 HR | $135.00 | $1.00 | $78.98 | -$2,680 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 48 CY | $250.00 | $300.00 | $179.97 | $2,400 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 4 EA | $4,400.00 | $3,800.00 | $3,190.07 | -$2,400 |
Positive: the low bidder was cheaper on that item. These 20 items account for $113,093 of the $109,673 gap.
PRESIDIO CONTRACTING, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7002 EMBANK (FNL)(DC)(TY A) | 241 CY | $35.00 | $15.82 | 2.21x | $4,622 |
| 310-7004 PRIME COAT (MC-30) | 200 GAL | $25.00 | $5.35 | 4.68x | $3,931 |
| 512-7057 PORT CTB (REMOVE)(LOW PROF)(TY 1) | 160 LF | $34.00 | $11.18 | 3.04x | $3,650 |
| 110-7001 EXCAV (ROADWAY) | 55 CY | $76.00 | $11.68 | 6.51x | $3,537 |
| 400-7010 CEM STABIL BKFL | 28 CY | $263.00 | $138.14 | 1.90x | $3,496 |
| 500-7001 MOBILIZATION | 1 LS | $48,320.00 | $523,850.32 | 0.09x | -$475,530 |
| 508-7003 CONSTRUCTING DETOURS (TY1) | 945 SY | $29.55 | $101.74 | 0.29x | -$68,223 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $1,650.00 | $11,585.04 | 0.14x | -$39,740 |
| 100-7002 PREPARING ROW | 3 STA | $2,100.00 | $6,072.92 | 0.35x | -$11,919 |
LUCANIA CONTRACTORS LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 425-7017 PRESTR CONC SLAB BEAM (5SB12) | 197.5 LF | $450.00 | $242.93 | 1.85x | $40,896 |
| 422-7007 REINF CONC SLAB (SLAB BEAM) | 1,040 SF | $50.00 | $23.90 | 2.09x | $27,140 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 160 LF | $90.00 | $43.56 | 2.07x | $7,430 |
| 164-7042 DRILL SEED (PERM_RURAL_CLAY) | 0.25 AC | $27,000.00 | $678.02 | 39.82x | $6,580 |
| 132-7002 EMBANK (FNL)(DC)(TY A) | 241 CY | $40.00 | $15.82 | 2.53x | $5,827 |
| 164-7045 DRILL SEED (TEMP_WARM) | 0.25 AC | $22,200.00 | $550.09 | 40.36x | $5,412 |
| 512-7010 PORT CTB (FUR & INST)(LOW PROF)(TY 2) | 80 LF | $100.00 | $55.61 | 1.80x | $3,551 |
| 500-7001 MOBILIZATION | 1 LS | $37,000.00 | $523,850.32 | 0.07x | -$486,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $2,000.00 | $11,585.04 | 0.17x | -$38,340 |
| 100-7002 PREPARING ROW | 3 STA | $1,200.00 | $6,072.92 | 0.20x | -$14,619 |
STX CIVIL: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 420-7012 CL C CONC (ABUT) | 17.6 CY | $2,830.00 | $1,307.98 | 2.16x | $26,788 |
| 422-7007 REINF CONC SLAB (SLAB BEAM) | 1,040 SF | $42.50 | $23.90 | 1.78x | $19,340 |
| 132-7002 EMBANK (FNL)(DC)(TY A) | 241 CY | $60.00 | $15.82 | 3.79x | $10,647 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 48 CY | $330.00 | $179.97 | 1.83x | $7,201 |
| 110-7001 EXCAV (ROADWAY) | 55 CY | $88.00 | $11.68 | 7.53x | $4,197 |
| 400-7010 CEM STABIL BKFL | 28 CY | $260.00 | $138.14 | 1.88x | $3,412 |
| 500-7001 MOBILIZATION | 1 LS | $53,175.00 | $523,850.32 | 0.10x | -$470,675 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $3,040.00 | $11,585.04 | 0.26x | -$34,180 |
| 100-7002 PREPARING ROW | 3 STA | $1,690.00 | $6,072.92 | 0.28x | -$13,149 |
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7002 EMBANK (FNL)(DC)(TY A) | 241 CY | $68.44 | $15.82 | 4.33x | $12,681 |
| 247-7001 FL BS (CMP IN PLC)(TY A GR 1-2) | 205 TON | $121.41 | $64.23 | 1.89x | $11,721 |
| 512-7057 PORT CTB (REMOVE)(LOW PROF)(TY 1) | 160 LF | $36.11 | $11.18 | 3.23x | $3,988 |
| 500-7001 MOBILIZATION | 1 LS | $109,253.54 | $523,850.32 | 0.21x | -$414,597 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $5,485.88 | $11,585.04 | 0.47x | -$24,397 |
| 100-7002 PREPARING ROW | 3 STA | $1,601.64 | $6,072.92 | 0.26x | -$13,414 |
J. CARROLL WEAVER, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7001 FL BS (CMP IN PLC)(TY A GR 1-2) | 205 TON | $133.77 | $64.23 | 2.08x | $14,255 |
| 164-7042 DRILL SEED (PERM_RURAL_CLAY) | 0.25 AC | $25,200.00 | $678.02 | 37.17x | $6,130 |
| 164-7045 DRILL SEED (TEMP_WARM) | 0.25 AC | $20,720.00 | $550.09 | 37.67x | $5,042 |
| 110-7001 EXCAV (ROADWAY) | 55 CY | $102.68 | $11.68 | 8.79x | $5,005 |
| 132-7002 EMBANK (FNL)(DC)(TY A) | 241 CY | $30.11 | $15.82 | 1.90x | $3,444 |
| 500-7001 MOBILIZATION | 1 LS | $154,248.32 | $523,850.32 | 0.29x | -$369,602 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $2,800.00 | $11,585.04 | 0.24x | -$35,140 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $2,022.23 | $9,253.78 | 0.22x | -$14,463 |
| 100-7002 PREPARING ROW | 3 STA | $2,164.10 | $6,072.92 | 0.36x | -$11,726 |