FY27 Plainview Call Out MBGF Repair
6510-77-001 · let Nov 5, 2026 · Hale, Lubbock · Routine Maintenance Project - Sealed
$158,004Low bid: AUSTIN BARRICADE COMPANY, L.L.C.-55.3% vs estimate $353,850
$95,130Left on the table60.2% gap to the second bid
4BiddersSpread 127% low to high
10Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | AUSTIN BARRICADE COMPANY, L.L.C. | $158,004 | -55.3% | $95,130 | 0 | 6-$111,793 | |
| 2 | T&L CLEANING SERVICES LLC | $253,134 | +60.2% | -28.5% | $85,066 | 3+$73,938 | 3-$100,811 |
| 3 | BOEN LANDSCAPING & IRRIGATION, LLC | $338,200 | +114.0% | -4.4% | $20,140 | 3+$34,658 | 0 |
| 4 | TI-ZACK CONCRETE, LLC | $358,340 | +126.8% | 1.3% | 6+$98,432 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
AUSTIN BARRICADE COMPANY, L.L.C. vs T&L CLEANING SERVICES LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 770-7037 REPLACE GUARDRAIL END TREATMENT SYSTEM | 20 EA | $4,000.00 | $5,500.00 | $3,116.90 | $30,000 |
| 770-7035 REPLACE W-BEAM RAIL | 2,500 LF | $30.00 | $40.00 | $24.10 | $25,000 |
| 770-7039 REPLACE LOW FILL CULVERT RAIL | 250 LF | $1.00 | $100.00 | $13.50 | $24,750 |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL | 10 EA | $1.00 | $1,000.00 | $534.87 | $9,990 |
| 770-7038 REPLACE CURVED RAIL | 100 LF | $1.00 | $50.00 | $26.19 | $4,900 |
| 770-7041 REPLACE GDRL END TREATMENT MRKR | 10 EA | $1.00 | $50.00 | $29.93 | $490 |
| 500-7002 MOBILIZATION (CALLOUT) | 24 EA | $1.00 | $1.00 | $600.85 | $0 |
| 505-7001 TMA (STATIONARY) | 360 DAY | $1.00 | $1.00 | $217.57 | $0 |
| 770-7036 REPLACE THRIE-BEAM RAIL | 25 LF | $50.00 | $50.00 | $48.04 | $0 |
| 770-7040 REMOVE RAIL | 1,000 LF | $1.00 | $1.00 | $9.45 | $0 |
Positive: the low bidder was cheaper on that item. These 10 items account for $95,130 of the $95,130 gap.
AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 360 DAY | $1.00 | $217.57 | 0.00x | -$77,966 |
| 500-7002 MOBILIZATION (CALLOUT) | 24 EA | $1.00 | $600.85 | 0.00x | -$14,396 |
| 770-7040 REMOVE RAIL | 1,000 LF | $1.00 | $9.45 | 0.11x | -$8,449 |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL | 10 EA | $1.00 | $534.87 | 0.00x | -$5,339 |
| 770-7039 REPLACE LOW FILL CULVERT RAIL | 250 LF | $1.00 | $13.50 | 0.07x | -$3,125 |
| 770-7038 REPLACE CURVED RAIL | 100 LF | $1.00 | $26.19 | 0.04x | -$2,519 |
T&L CLEANING SERVICES LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 770-7037 REPLACE GUARDRAIL END TREATMENT SYSTEM | 20 EA | $5,500.00 | $3,116.90 | 1.76x | $47,662 |
| 770-7039 REPLACE LOW FILL CULVERT RAIL | 250 LF | $100.00 | $13.50 | 7.41x | $21,625 |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL | 10 EA | $1,000.00 | $534.87 | 1.87x | $4,651 |
| 505-7001 TMA (STATIONARY) | 360 DAY | $1.00 | $217.57 | 0.00x | -$77,966 |
| 500-7002 MOBILIZATION (CALLOUT) | 24 EA | $1.00 | $600.85 | 0.00x | -$14,396 |
| 770-7040 REMOVE RAIL | 1,000 LF | $1.00 | $9.45 | 0.11x | -$8,449 |
BOEN LANDSCAPING & IRRIGATION, LLC: unbalanced items
Placed 3TI-ZACK CONCRETE, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL | 10 EA | $4,025.00 | $534.87 | 7.53x | $34,901 |
| 770-7039 REPLACE LOW FILL CULVERT RAIL | 250 LF | $143.75 | $13.50 | 10.65x | $32,563 |
| 500-7002 MOBILIZATION (CALLOUT) | 24 EA | $1,380.00 | $600.85 | 2.30x | $18,700 |
| 770-7036 REPLACE THRIE-BEAM RAIL | 25 LF | $287.50 | $48.04 | 5.98x | $5,987 |
| 770-7038 REPLACE CURVED RAIL | 100 LF | $63.25 | $26.19 | 2.42x | $3,706 |
| 770-7041 REPLACE GDRL END TREATMENT MRKR | 10 EA | $287.50 | $29.93 | 9.61x | $2,576 |