TRAFFIC CONTROL SERVICES FY 2027(EAST)
6509-56-001 · let Nov 4, 2026 · Hill, Waco · Routine Maintenance Project
$2,308,875Low bid: AWP SAFETY+6.8% vs estimate $2,162,139
$253,596Left on the table11.0% gap to the second bid
3BiddersSpread 27% low to high
33Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | AWP SAFETY | $2,308,875 | 6.8% | $253,596 | 1+$307,428 | 1-$25,342 | |
| 2 | ROAD SOLUTIONS L.L.C. | $2,562,471 | +11.0% | 18.5% | $369,230 | 2+$501,218 | 1-$25,342 |
| 3 | BARRICADES UNLIMITED | $2,931,700 | +27.0% | 35.6% | 1+$482,428 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
AWP SAFETY vs ROAD SOLUTIONS L.L.C., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $1,000.00 | $10,500.00 | $600.85 | $114,000 |
| 505-7001 TMA (STATIONARY) | 1,000 DAY | $525.00 | $600.00 | $217.57 | $75,000 |
| 790-7001 LANE CLOSURE(SETUP & REM)(TYP 1) | 500 EA | $225.00 | $300.00 | $353.49 | $37,500 |
| 505-7002 TMA (MOBILE OPERATION) | 6,000 HR | $80.00 | $84.56 | $64.00 | $27,360 |
| 790-7059 ADDITIONAL LANE CLOSURE ITEM(TYPE 21) | 5,000 HR | $60.00 | $55.00 | $58.00 | -$25,000 |
| 790-7002 LANE CLOSURE(SETUP & REM)(TYP 2) | 200 EA | $225.00 | $300.00 | $414.16 | $15,000 |
| 790-7020 LANE CLOSURE(MAINTENANCE)(TYP 1) | 3,000 HR | $115.00 | $120.00 | $104.45 | $15,000 |
| 790-7058 ADDITIONAL LANE CLOSURE ITEM(TYPE 20) | 2,500 HR | $45.00 | $40.00 | $48.40 | -$12,500 |
| 790-7021 LANE CLOSURE(MAINTENANCE)(TYP 2) | 1,500 HR | $115.00 | $120.00 | $78.09 | $7,500 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 150 DAY | $150.00 | $103.44 | $117.34 | -$6,984 |
| 500-7033 MOBILIZATION (EMERGENCY) | 6 EA | $1,000.00 | $2,000.00 | $844.81 | $6,000 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 75 DAY | $100.00 | $136.39 | $87.82 | $2,729 |
| 790-7028 LANE CLOSURE(MAINTENANCE)(TYP 9) | 20 HR | $230.00 | $175.00 | $118.00 | -$1,100 |
| 545-7004 CRASH CUSH ATTEN (REMOVE) | 1 EA | $2,500.00 | $1,415.25 | $941.31 | -$1,085 |
| 545-7001 CRASH CUSH ATTEN (DES SOURCE) | 1 EA | $2,500.00 | $2,000.00 | $1,747.21 | -$500 |
| 790-7007 LANE CLOSURE(SETUP & REM)(TYP 7) | 2 EA | $350.00 | $500.00 | $594.90 | $300 |
| 790-7008 LANE CLOSURE(SETUP & REM)(TYP 8) | 2 EA | $350.00 | $500.00 | $233.89 | $300 |
| 790-7025 LANE CLOSURE(MAINTENANCE)(TYP 6) | 50 HR | $120.00 | $115.00 | $62.12 | -$250 |
| 790-7026 LANE CLOSURE(MAINTENANCE)(TYP 7) | 20 HR | $170.00 | $175.00 | $75.83 | $100 |
| 790-7027 LANE CLOSURE(MAINTENANCE)(TYP 8) | 20 HR | $170.00 | $175.00 | $81.37 | $100 |
Positive: the low bidder was cheaper on that item. These 20 items account for $253,471 of the $253,596 gap.
AWP SAFETY: unbalanced items
Placed 1ROAD SOLUTIONS L.L.C.: unbalanced items
Placed 2BARRICADES UNLIMITED: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 1,000 DAY | $700.00 | $217.57 | 3.22x | $482,428 |