Bid Tab X-ray: 6508-49-001

Nov 10, 2026 · Wheeler Sign up free
Set your company to personalize scores

FY27 Cable Barrier

6508-49-001 · let Nov 10, 2026 · Wheeler, Childress · Routine Maintenance Project - Sealed

$117,300Low bid: BOEN LANDSCAPING & IRRIGATION, LLC-1.3% vs estimate $118,800
$2,276Left on the table1.9% gap to the second bid
5BiddersSpread 118% low to high
7Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1BOEN LANDSCAPING & IRRIGATION, LLC $117,300-1.3% $2,276 2+$18,797 1-$4,210
2AUSTIN BARRICADE COMPANY, L.L.C. $119,576+1.9%0.7% $50,353 0 5-$34,871
3TI-ZACK CONCRETE, LLC $169,929+44.9%43.0% $13,626 3+$64,607 0
4HJC FARMS, INC. $183,554+56.5%54.5% $71,802 2+$94,233 3-$15,250
5MASSANA CONSTRUCTION INC. $255,356+117.7%114.9% 3+$97,454 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

BOEN LANDSCAPING & IRRIGATION, LLC vs AUSTIN BARRICADE COMPANY, L.L.C., biggest item swings
ItemQtyLow2ndMarket2nd minus low
771-7025 REPLACE LINE OR TERMINAL POST (VALTIR)300 EA $190.00$375.00$215.97 $55,500
771-7029 REPLACE CABLE RELEASE POST20 EA $850.00$1.00$148.81 -$16,980
771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL)100 EA $200.00$50.00$176.83 -$15,000
771-7033 SPLICE CABLE20 EA $375.00$1.00$342.77 -$7,480
771-7031 REPLACE CABLE1,000 LF $8.00$2.00$3.23 -$6,000
505-7001 TMA (STATIONARY)24 DAY $200.00$1.00$217.57 -$4,776
500-7002 MOBILIZATION (CALLOUT)12 EA $250.00$1.00$600.85 -$2,988

Positive: the low bidder was cheaper on that item. These 7 items account for $2,276 of the $2,276 gap.

BOEN LANDSCAPING & IRRIGATION, LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
771-7029 REPLACE CABLE RELEASE POST20 EA $850.00$148.815.71x$14,024
771-7031 REPLACE CABLE1,000 LF $8.00$3.232.48x$4,773
500-7002 MOBILIZATION (CALLOUT)12 EA $250.00$600.850.42x-$4,210

AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL)100 EA $50.00$176.830.28x-$12,683
500-7002 MOBILIZATION (CALLOUT)12 EA $1.00$600.850.00x-$7,198
771-7033 SPLICE CABLE20 EA $1.00$342.770.00x-$6,835
505-7001 TMA (STATIONARY)24 DAY $1.00$217.570.00x-$5,198
771-7029 REPLACE CABLE RELEASE POST20 EA $1.00$148.810.01x-$2,956

TI-ZACK CONCRETE, LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
771-7031 REPLACE CABLE1,000 LF $41.13$3.2312.75x$37,898
771-7029 REPLACE CABLE RELEASE POST20 EA $998.75$148.816.71x$16,999
500-7002 MOBILIZATION (CALLOUT)12 EA $1,410.00$600.852.35x$9,710

HJC FARMS, INC.: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
771-7025 REPLACE LINE OR TERMINAL POST (VALTIR)300 EA $500.00$215.972.32x$85,210
771-7029 REPLACE CABLE RELEASE POST20 EA $600.00$148.814.03x$9,024
771-7033 SPLICE CABLE20 EA $1.00$342.770.00x-$6,835
505-7001 TMA (STATIONARY)24 DAY $1.00$217.570.00x-$5,198
771-7031 REPLACE CABLE1,000 LF $0.0100$3.230.00x-$3,217

MASSANA CONSTRUCTION INC.: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)12 EA $5,958.00$600.859.92x$64,286
771-7029 REPLACE CABLE RELEASE POST20 EA $1,200.00$148.818.06x$21,024
771-7033 SPLICE CABLE20 EA $950.00$342.772.77x$12,145