FY27 Cable Barrier
6508-49-001 · let Nov 10, 2026 · Wheeler, Childress · Routine Maintenance Project - Sealed
$117,300Low bid: BOEN LANDSCAPING & IRRIGATION, LLC-1.3% vs estimate $118,800
$2,276Left on the table1.9% gap to the second bid
5BiddersSpread 118% low to high
7Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BOEN LANDSCAPING & IRRIGATION, LLC | $117,300 | -1.3% | $2,276 | 2+$18,797 | 1-$4,210 | |
| 2 | AUSTIN BARRICADE COMPANY, L.L.C. | $119,576 | +1.9% | 0.7% | $50,353 | 0 | 5-$34,871 |
| 3 | TI-ZACK CONCRETE, LLC | $169,929 | +44.9% | 43.0% | $13,626 | 3+$64,607 | 0 |
| 4 | HJC FARMS, INC. | $183,554 | +56.5% | 54.5% | $71,802 | 2+$94,233 | 3-$15,250 |
| 5 | MASSANA CONSTRUCTION INC. | $255,356 | +117.7% | 114.9% | 3+$97,454 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
BOEN LANDSCAPING & IRRIGATION, LLC vs AUSTIN BARRICADE COMPANY, L.L.C., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 771-7025 REPLACE LINE OR TERMINAL POST (VALTIR) | 300 EA | $190.00 | $375.00 | $215.97 | $55,500 |
| 771-7029 REPLACE CABLE RELEASE POST | 20 EA | $850.00 | $1.00 | $148.81 | -$16,980 |
| 771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL) | 100 EA | $200.00 | $50.00 | $176.83 | -$15,000 |
| 771-7033 SPLICE CABLE | 20 EA | $375.00 | $1.00 | $342.77 | -$7,480 |
| 771-7031 REPLACE CABLE | 1,000 LF | $8.00 | $2.00 | $3.23 | -$6,000 |
| 505-7001 TMA (STATIONARY) | 24 DAY | $200.00 | $1.00 | $217.57 | -$4,776 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $250.00 | $1.00 | $600.85 | -$2,988 |
Positive: the low bidder was cheaper on that item. These 7 items account for $2,276 of the $2,276 gap.
BOEN LANDSCAPING & IRRIGATION, LLC: unbalanced items
Placed 1AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL) | 100 EA | $50.00 | $176.83 | 0.28x | -$12,683 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $1.00 | $600.85 | 0.00x | -$7,198 |
| 771-7033 SPLICE CABLE | 20 EA | $1.00 | $342.77 | 0.00x | -$6,835 |
| 505-7001 TMA (STATIONARY) | 24 DAY | $1.00 | $217.57 | 0.00x | -$5,198 |
| 771-7029 REPLACE CABLE RELEASE POST | 20 EA | $1.00 | $148.81 | 0.01x | -$2,956 |
TI-ZACK CONCRETE, LLC: unbalanced items
Placed 3HJC FARMS, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7025 REPLACE LINE OR TERMINAL POST (VALTIR) | 300 EA | $500.00 | $215.97 | 2.32x | $85,210 |
| 771-7029 REPLACE CABLE RELEASE POST | 20 EA | $600.00 | $148.81 | 4.03x | $9,024 |
| 771-7033 SPLICE CABLE | 20 EA | $1.00 | $342.77 | 0.00x | -$6,835 |
| 505-7001 TMA (STATIONARY) | 24 DAY | $1.00 | $217.57 | 0.00x | -$5,198 |
| 771-7031 REPLACE CABLE | 1,000 LF | $0.0100 | $3.23 | 0.00x | -$3,217 |