US 83, 0038-01-107 Cable Barrier
0038-01-107 · let Nov 3, 2026 · Webb, Laredo · Safety Improvement Projects
$1,490,944Low bid: HJC FARMS, INC.-6.3% vs estimate $1,590,609
$26,460Left on the table1.8% gap to the second bid
4BiddersSpread 12% low to high
56Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HJC FARMS, INC. | $1,490,944 | -6.3% | $26,460 | 0 | 6-$643,768 | |
| 2 | MASSANA CONSTRUCTION INC. | $1,517,404 | +1.8% | -4.6% | $117,482 | 0 | 2-$76,224 |
| 3 | AUSTIN BARRICADE COMPANY, L.L.C. | $1,634,886 | +9.7% | 2.8% | $40,675 | 2+$116,055 | 4-$492,713 |
| 4 | SCR CIVIL CONSTRUCTION, LLC | $1,675,560 | +12.4% | 5.3% | 0 | 1-$433,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
HJC FARMS, INC. vs MASSANA CONSTRUCTION INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $80,000.00 | $268,781.80 | $523,850.32 | $188,782 |
| 543-7002 CABLE BARRIER SYSTEM (INSTALL)(TL-4) | 34,921 LF | $13.75 | $10.00 | $12.40 | -$130,954 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 1,365 CY | $425.00 | $350.00 | $616.83 | -$102,375 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $2,937.90 | $9,500.00 | $11,585.04 | $45,935 |
| 150-7001 BLADING | 368 STA | $25.00 | $95.00 | $152.64 | $25,760 |
| 543-7018 CABLE BARRIER TERM SEC (INSTL)(TL-4) | 43 EA | $2,100.00 | $2,500.00 | $2,822.11 | $17,200 |
| 772-7001 POST AND CABLE FENCE (REMOVAL) | 1,935 LF | $0.0100 | $4.00 | $4.61 | $7,721 |
| 505-7001 TMA (STATIONARY) | 135 DAY | $1.00 | $55.00 | $217.57 | $7,290 |
| 545-7006 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) | 2 EA | $32,000.00 | $28,500.00 | $26,188.60 | -$7,000 |
| 644-7004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) | 20 EA | $880.57 | $600.00 | $785.93 | -$5,611 |
| 658-7025 INSTL DEL ASSM (D-SY)SZ 1(YFLX)SRF | 47 EA | $200.00 | $95.00 | $131.27 | -$4,935 |
| 545-7004 CRASH CUSH ATTEN (REMOVE) | 1 EA | $5,000.00 | $500.00 | $941.31 | -$4,500 |
| 505-7002 TMA (MOBILE OPERATION) | 16 HR | $300.00 | $60.00 | $64.00 | -$3,840 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 1,443 LF | $7.35 | $5.00 | $3.92 | -$3,391 |
| 644-7001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) | 17 EA | $773.06 | $600.00 | $696.14 | -$2,942 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 805 LF | $5.04 | $2.20 | $0.4757 | -$2,286 |
| 104-7008 REMOV CONC (MEDIANS) | 22 SY | $20.00 | $85.00 | $22.02 | $1,430 |
| 677-7002 ELIM EXT PM & MRKS (6") | 1,596 LF | $1.05 | $0.4000 | $0.2755 | -$1,037 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 791 LF | $3.36 | $2.20 | $0.4986 | -$918 |
| 644-7073 REMOVE SM RD SN SUP&AM | 36 EA | $100.00 | $125.00 | $108.47 | $900 |
Positive: the low bidder was cheaper on that item. These 20 items account for $25,228 of the $26,460 gap.
HJC FARMS, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $80,000.00 | $523,850.32 | 0.15x | -$443,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $2,937.90 | $11,585.04 | 0.25x | -$60,530 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 7 EA | $1,500.00 | $9,253.78 | 0.16x | -$54,276 |
| 150-7001 BLADING | 368 STA | $25.00 | $152.64 | 0.16x | -$46,971 |
| 505-7001 TMA (STATIONARY) | 135 DAY | $1.00 | $217.57 | 0.00x | -$29,237 |
| 772-7001 POST AND CABLE FENCE (REMOVAL) | 1,935 LF | $0.0100 | $4.61 | 0.00x | -$8,903 |
MASSANA CONSTRUCTION INC.: unbalanced items
Placed 2AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 135 DAY | $1,000.00 | $217.57 | 4.60x | $105,628 |
| 772-7001 POST AND CABLE FENCE (REMOVAL) | 1,935 LF | $10.00 | $4.61 | 2.17x | $10,428 |
| 500-7001 MOBILIZATION | 1 LS | $160,000.00 | $523,850.32 | 0.31x | -$363,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $3,500.00 | $11,585.04 | 0.30x | -$56,595 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 7 EA | $3,800.00 | $9,253.78 | 0.41x | -$38,176 |
| 150-7001 BLADING | 368 STA | $60.00 | $152.64 | 0.39x | -$34,091 |
SCR CIVIL CONSTRUCTION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $90,000.00 | $523,850.32 | 0.17x | -$433,850 |