SH 5 N OF OUTER LOOP TO N OF HACKBERRY
0047-04-032 · let Nov 4, 2026 · Collin, Dallas · Widen Non-Freeway
$35,766,135Low bid: MARIO SINACOLA & SONS EXCAVATING, INC.-10.4% vs estimate $39,930,214
$890,797Left on the table2.5% gap to the second bid
4BiddersSpread 13% low to high
215Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | MARIO SINACOLA & SONS EXCAVATING, INC. | $35,766,135 | -10.4% | $890,797 | 3+$4,146,735 | 3-$654,022 | |
| 2 | ED BELL CONSTRUCTION COMPANY | $36,656,931 | +2.5% | -8.2% | $1,513,024 | 5+$4,455,647 | 0 |
| 3 | TISEO PAVING COMPANY, LLC | $38,169,956 | +6.7% | -4.4% | $2,271,547 | 2+$1,586,405 | 1-$204,641 |
| 4 | HARPER BROTHERS CONSTRUCTION LLC | $40,441,503 | +13.1% | 1.3% | 3+$3,058,644 | 1-$257,840 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
MARIO SINACOLA & SONS EXCAVATING, INC. vs ED BELL CONSTRUCTION COMPANY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 360-7005 CONC PVMT (CRCP) (11") | 96,787 SY | $80.00 | $90.00 | $94.72 | $967,870 |
| 100-7002 PREPARING ROW | 138 STA | $10,865.00 | $4,000.00 | $6,072.92 | -$947,370 |
| 464-7005 RC PIPE (CL III)(24 IN) | 15,190 LF | $102.00 | $70.00 | $108.34 | -$486,080 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 32 MO | $27,500.00 | $42,000.00 | $11,585.04 | $464,000 |
| 110-7001 EXCAV (ROADWAY) | 42,020 CY | $20.00 | $10.00 | $11.68 | -$420,200 |
| 360-7050 CONC PVMT (CRCP)(HES) (11") | 10,485 SY | $86.00 | $125.00 | $102.34 | $408,915 |
| 260-7001 LIME (COM OR QK)(SLURRY) OR QK(DRY) | 2,986 TON | $320.00 | $450.00 | $345.77 | $388,180 |
| 105-7052 RMV (0"-12") TRT/UNTRT BASE & ASPH PAV | 43,710 SY | $6.00 | $13.50 | $7.43 | $327,825 |
| 508-7001 CONSTRUCTING DETOURS | 25,823 SY | $60.00 | $71.00 | $83.58 | $284,053 |
| 462-7001 CONC BOX CULV (3 FT X 2 FT) | 2,638 LF | $290.00 | $190.00 | $328.79 | -$263,800 |
| 260-7007 LIME TRT (EXIST MATL)(8") | 113,095 SY | $6.00 | $3.75 | $4.35 | -$254,464 |
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 49,819 CY | $20.00 | $15.00 | $17.39 | -$249,095 |
| 105-7028 RMV (8") TRT/UNTRT BASE & ASPH PAV | 35,107 SY | $5.00 | $11.00 | $5.21 | $210,642 |
| 6006-7006 VIVDS TEMPORARY | 5 EA | $43,000.00 | $7,987.50 | $31,364.57 | -$175,063 |
| 344-7001 SP MIXES SP-B PG64-22 | 24,066 TON | $108.20 | $115.25 | $124.45 | $169,665 |
| 500-7001 MOBILIZATION | 1 LS | $3,500,000.00 | $3,350,000.00 | $523,850.32 | -$150,000 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 5,150 LF | $40.00 | $14.00 | $43.56 | -$133,900 |
| 529-7007 CONC CURB (MONO) (TY II) | 53,199 LF | $1.50 | $4.00 | $6.85 | $132,998 |
| 464-7007 RC PIPE (CL III)(30 IN) | 2,557 LF | $147.00 | $95.00 | $140.03 | -$132,964 |
| 462-7003 CONC BOX CULV (4 FT X 2 FT) | 1,249 LF | $325.00 | $225.00 | $419.86 | -$124,900 |
Positive: the low bidder was cheaper on that item. These 20 items account for $16,313 of the $890,797 gap.
MARIO SINACOLA & SONS EXCAVATING, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,500,000.00 | $523,850.32 | 6.68x | $2,976,150 |
| 100-7002 PREPARING ROW | 138 STA | $10,865.00 | $6,072.92 | 1.79x | $661,307 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 32 MO | $27,500.00 | $11,585.04 | 2.37x | $509,279 |
| 529-7007 CONC CURB (MONO) (TY II) | 53,199 LF | $1.50 | $6.85 | 0.22x | -$284,439 |
| 168-7001 VEGETATIVE WATERING | 22,847 TGL | $0.1000 | $8.43 | 0.01x | -$190,400 |
| 505-7001 TMA (STATIONARY) | 1,109 DAY | $56.00 | $217.57 | 0.26x | -$179,183 |
ED BELL CONSTRUCTION COMPANY: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,350,000.00 | $523,850.32 | 6.39x | $2,826,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 32 MO | $42,000.00 | $11,585.04 | 3.63x | $973,279 |
| 105-7052 RMV (0"-12") TRT/UNTRT BASE & ASPH PAV | 43,710 SY | $13.50 | $7.43 | 1.82x | $265,525 |
| 105-7028 RMV (8") TRT/UNTRT BASE & ASPH PAV | 35,107 SY | $11.00 | $5.21 | 2.11x | $203,319 |
| 680-7002 INSTALL HWY TRF SIG (ISOLATED) | 5 EA | $72,420.00 | $34,944.96 | 2.07x | $187,375 |
TISEO PAVING COMPANY, LLC: unbalanced items
Placed 3HARPER BROTHERS CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,500,000.00 | $523,850.32 | 4.77x | $1,976,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 32 MO | $32,500.00 | $11,585.04 | 2.81x | $669,279 |
| 260-7007 LIME TRT (EXIST MATL)(8") | 113,095 SY | $8.00 | $4.35 | 1.84x | $413,215 |
| 529-7007 CONC CURB (MONO) (TY II) | 53,199 LF | $2.00 | $6.85 | 0.29x | -$257,840 |