6499-60-001 BPM
6499-60-001 · let Apr 21, 2026 · Ector, Odessa · Bridge Preventative Maintenance - Sealed
$521,997Low bid: ICOS MANAGEMENT, LLC-21.0% vs estimate $660,927
$69,645Left on the table13.3% gap to the second bid
7BiddersSpread 50% low to high
22Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ICOS MANAGEMENT, LLC | $521,997 | -21.0% | $69,645 | 6+$40,146 | 2-$537,686 | |
| 2 | ROAD DOCTORS LLC | $591,641 | +13.3% | -10.5% | $25,712 | 7+$144,510 | 4-$715,738 |
| 3 | TI-ZACK CONCRETE, LLC | $617,353 | +18.3% | -6.6% | $134,257 | 8+$141,213 | 2-$512,623 |
| 4 | THE TRUESDELL CORPORATION | $751,610 | +44.0% | 13.7% | $25,257 | 4+$119,854 | 3-$442,916 |
| 5 | SCR CIVIL CONSTRUCTION, LLC | $776,867 | +48.8% | 17.5% | $4,707 | 9+$176,763 | 2-$470,190 |
| 6 | PREMIER CONTRACTORS LLC | $781,574 | +49.7% | 18.3% | $2,226 | ||
| 7 | GARRET SHIELDS INFRASTRUCTURE | $783,800 | +50.2% | 18.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ICOS MANAGEMENT, LLC vs ROAD DOCTORS LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 2,382 SF | $107.00 | $60.00 | $150.68 | -$111,954 |
| 780-7003 CONC CRCK REPR(DISCRETE)(ROUT AND SEAL) | 551 LF | $43.00 | $150.00 | $46.07 | $58,957 |
| 423-7013 RETAINING WALL (CONC BLOCK) | 301 SF | $54.00 | $175.00 | $52.00 | $36,421 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 450 SF | $193.00 | $250.00 | $192.68 | $25,650 |
| 500-7001 MOBILIZATION | 1 LS | $32,500.00 | $55,000.00 | $523,850.32 | $22,500 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $1.00 | $5,000.00 | $11,585.04 | $19,996 |
| 410-7001 SOIL NAIL ANCHORS | 226 LF | $28.00 | $100.00 | $30.07 | $16,272 |
| 480-7001 CLEAN EXIST CULVERTS | 2 EA | $8,560.00 | $2,500.00 | $1,712.97 | -$12,120 |
| 110-7003 EXCAV (SPECIAL) | 34 CY | $86.00 | $400.00 | $18.78 | $10,676 |
| 423-7023 RETAINING WALL (SOIL NAIL) (FASCIA) | 301 SF | $45.00 | $75.00 | $66.42 | $9,030 |
| 432-7001 RIPRAP (CONC)(4 IN) | 14 CY | $856.00 | $1,400.00 | $573.24 | $7,616 |
| 505-7001 TMA (STATIONARY) | 21 DAY | $267.00 | $1.00 | $217.57 | -$5,586 |
| 540-7007 MTL BEAM GD FEN TRANS (T101) | 2 EA | $4,280.00 | $1,500.00 | $901.86 | -$5,560 |
| 776-7003 REPAIR (STEEL PED. RAIL) | 54 LF | $267.00 | $200.00 | $148.66 | -$3,618 |
| 540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION | 2 EA | $3,210.00 | $1,500.00 | $1,297.32 | -$3,420 |
| 104-7007 REMOV CONC (RIPRAP) | 13 CY | $321.00 | $550.00 | $26.91 | $2,977 |
| 776-7006 REPAIR (T101) | 28 LF | $267.00 | $175.00 | $64.98 | -$2,576 |
| 403-7001 TEMPORARY SPL SHORING | 54 SF | $22.00 | $50.00 | $25.56 | $1,512 |
| 540-7002 MTL W-BEAM GD FEN (STEEL POST) | 25 LF | $53.50 | $100.00 | $30.74 | $1,163 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 2 CY | $1,070.00 | $1,500.00 | $616.83 | $860 |
Positive: the low bidder was cheaper on that item. These 20 items account for $68,796 of the $69,645 gap.
ICOS MANAGEMENT, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 480-7001 CLEAN EXIST CULVERTS | 2 EA | $8,560.00 | $1,712.97 | 5.00x | $13,694 |
| 540-7007 MTL BEAM GD FEN TRANS (T101) | 2 EA | $4,280.00 | $901.86 | 4.75x | $6,756 |
| 776-7003 REPAIR (STEEL PED. RAIL) | 54 LF | $267.00 | $148.66 | 1.80x | $6,390 |
| 776-7006 REPAIR (T101) | 28 LF | $267.00 | $64.98 | 4.11x | $5,656 |
| 540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION | 2 EA | $3,210.00 | $1,297.32 | 2.47x | $3,825 |
| 104-7007 REMOV CONC (RIPRAP) | 13 CY | $321.00 | $26.91 | 11.93x | $3,823 |
| 500-7001 MOBILIZATION | 1 LS | $32,500.00 | $523,850.32 | 0.06x | -$491,350 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $1.00 | $11,585.04 | 0.00x | -$46,336 |
ROAD DOCTORS LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 780-7003 CONC CRCK REPR(DISCRETE)(ROUT AND SEAL) | 551 LF | $150.00 | $46.07 | 3.26x | $57,266 |
| 423-7013 RETAINING WALL (CONC BLOCK) | 301 SF | $175.00 | $52.00 | 3.37x | $37,022 |
| 410-7001 SOIL NAIL ANCHORS | 226 LF | $100.00 | $30.07 | 3.33x | $15,805 |
| 110-7003 EXCAV (SPECIAL) | 34 CY | $400.00 | $18.78 | 21.30x | $12,962 |
| 432-7001 RIPRAP (CONC)(4 IN) | 14 CY | $1,400.00 | $573.24 | 2.44x | $11,575 |
| 104-7007 REMOV CONC (RIPRAP) | 13 CY | $550.00 | $26.91 | 20.44x | $6,800 |
| 776-7006 REPAIR (T101) | 28 LF | $175.00 | $64.98 | 2.69x | $3,080 |
| 500-7001 MOBILIZATION | 1 LS | $55,000.00 | $523,850.32 | 0.10x | -$468,850 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 2,382 SF | $60.00 | $150.68 | 0.40x | -$216,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $5,000.00 | $11,585.04 | 0.43x | -$26,340 |
| 505-7001 TMA (STATIONARY) | 21 DAY | $1.00 | $217.57 | 0.00x | -$4,548 |
TI-ZACK CONCRETE, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 423-7023 RETAINING WALL (SOIL NAIL) (FASCIA) | 301 SF | $222.00 | $66.42 | 3.34x | $46,830 |
| 423-7013 RETAINING WALL (CONC BLOCK) | 301 SF | $135.60 | $52.00 | 2.61x | $25,163 |
| 410-7001 SOIL NAIL ANCHORS | 226 LF | $138.00 | $30.07 | 4.59x | $24,393 |
| 480-7001 CLEAN EXIST CULVERTS | 2 EA | $9,600.00 | $1,712.97 | 5.60x | $15,774 |
| 540-7007 MTL BEAM GD FEN TRANS (T101) | 2 EA | $6,600.00 | $901.86 | 7.32x | $11,396 |
| 540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION | 2 EA | $4,800.00 | $1,297.32 | 3.70x | $7,005 |
| 403-7001 TEMPORARY SPL SHORING | 54 SF | $150.00 | $25.56 | 5.87x | $6,720 |
| 110-7003 EXCAV (SPECIAL) | 34 CY | $134.40 | $18.78 | 7.16x | $3,931 |
| 500-7001 MOBILIZATION | 1 LS | $30,000.00 | $523,850.32 | 0.06x | -$493,850 |
| 780-7003 CONC CRCK REPR(DISCRETE)(ROUT AND SEAL) | 551 LF | $12.00 | $46.07 | 0.26x | -$18,772 |
THE TRUESDELL CORPORATION: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 423-7023 RETAINING WALL (SOIL NAIL) (FASCIA) | 301 SF | $297.12 | $66.42 | 4.47x | $69,441 |
| 410-7001 SOIL NAIL ANCHORS | 226 LF | $130.25 | $30.07 | 4.33x | $22,642 |
| 480-7001 CLEAN EXIST CULVERTS | 2 EA | $9,000.00 | $1,712.97 | 5.25x | $14,574 |
| 540-7007 MTL BEAM GD FEN TRANS (T101) | 2 EA | $7,500.00 | $901.86 | 8.32x | $13,196 |
| 500-7001 MOBILIZATION | 1 LS | $90,000.00 | $523,850.32 | 0.17x | -$433,850 |
| 505-7001 TMA (STATIONARY) | 21 DAY | $1.00 | $217.57 | 0.00x | -$4,548 |
| 776-7003 REPAIR (STEEL PED. RAIL) | 54 LF | $65.00 | $148.66 | 0.44x | -$4,518 |
SCR CIVIL CONSTRUCTION, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 410-7001 SOIL NAIL ANCHORS | 226 LF | $270.00 | $30.07 | 8.98x | $54,225 |
| 423-7023 RETAINING WALL (SOIL NAIL) (FASCIA) | 301 SF | $185.00 | $66.42 | 2.79x | $35,693 |
| 480-7001 CLEAN EXIST CULVERTS | 2 EA | $15,520.00 | $1,712.97 | 9.06x | $27,614 |
| 423-7013 RETAINING WALL (CONC BLOCK) | 301 SF | $103.00 | $52.00 | 1.98x | $15,350 |
| 432-7001 RIPRAP (CONC)(4 IN) | 14 CY | $1,470.00 | $573.24 | 2.56x | $12,555 |
| 403-7001 TEMPORARY SPL SHORING | 54 SF | $230.00 | $25.56 | 9.00x | $11,040 |
| 104-7007 REMOV CONC (RIPRAP) | 13 CY | $726.00 | $26.91 | 26.98x | $9,088 |
| 540-7007 MTL BEAM GD FEN TRANS (T101) | 2 EA | $4,015.00 | $901.86 | 4.45x | $6,226 |
| 110-7003 EXCAV (SPECIAL) | 34 CY | $165.00 | $18.78 | 8.79x | $4,972 |
| 500-7001 MOBILIZATION | 1 LS | $77,600.00 | $523,850.32 | 0.15x | -$446,250 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $5,600.00 | $11,585.04 | 0.48x | -$23,940 |