Culvert Repair Franklin Co.
6498-80-001 · let Apr 16, 2026 · Franklin, Paris · Routine Maintenance Project - Sealed
$121,450Low bid: RB CONTRACTING, LLC-52.1% vs estimate $253,524
$11,400Left on the table9.4% gap to the second bid
8BiddersSpread 74% low to high
16Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RB CONTRACTING, LLC | $121,450 | -52.1% | $11,400 | 5+$28,238 | 2-$522,020 | |
| 2 | GARRET SHIELDS INFRASTRUCTURE | $132,850 | +9.4% | -47.6% | $12,594 | 3+$15,918 | 1-$503,850 |
| 3 | ICOS MANAGEMENT, LLC | $145,444 | +19.8% | -42.6% | $22,796 | 4+$24,666 | 2-$503,018 |
| 4 | JACKSON EXCAVATION, LLC | $168,240 | +38.5% | -33.6% | $5,335 | 5+$66,817 | 2-$512,020 |
| 5 | CATOCON, INC. | $173,575 | +42.9% | -31.5% | $8,925 | 9+$76,744 | 2-$522,020 |
| 6 | SHALOM SERVICES CORPORATION | $182,500 | +50.3% | -28.0% | $9,570 | ||
| 7 | GHB EQUIPMENT COMPANY, L.L.C. | $192,070 | +58.1% | -24.2% | $19,054 | ||
| 8 | ROAD DOCTORS LLC | $211,124 | +73.8% | -16.7% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
RB CONTRACTING, LLC vs GARRET SHIELDS INFRASTRUCTURE, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $5,000.00 | $10,000.00 | $11,585.04 | $10,000 |
| 466-7189 WINGWALL (PW - 2) (HW=5 FT) | 1 EA | $13,000.00 | $20,000.00 | $18,305.05 | $7,000 |
| 500-7001 MOBILIZATION | 1 LS | $15,000.00 | $20,000.00 | $523,850.32 | $5,000 |
| 400-7008 CUT & RESTORE ASPH PAVING | 30 SY | $300.00 | $150.00 | $140.13 | -$4,500 |
| 462-7060 CONC BOX CULV (4 FT X 4 FT)(EXTEND) | 4 LF | $2,000.00 | $1,000.00 | $742.91 | -$4,000 |
| 496-7006 REMOV STR (HEADWALL) | 1 EA | $1,000.00 | $5,000.00 | $1,533.90 | $4,000 |
| 432-7001 RIPRAP (CONC)(4 IN) | 11 CY | $900.00 | $600.00 | $573.24 | -$3,300 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 285 LF | $60.00 | $50.00 | $15.92 | -$2,850 |
| 496-7018 REMOVE STR (GABION) | 40 LF | $50.00 | $100.00 | $57.12 | $2,000 |
| 505-7001 TMA (STATIONARY) | 24 DAY | $350.00 | $300.00 | $217.57 | -$1,200 |
| 529-7009 CONC CURB & GUTTER (TY II) | 24 LF | $150.00 | $100.00 | $32.57 | -$1,200 |
| 132-7001 EMBANK (FNL)(OC)(TY A) | 100 CY | $40.00 | $50.00 | $22.62 | $1,000 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 40 CY | $275.00 | $300.00 | $184.74 | $1,000 |
| 401-7001 FLOWABLE BACKFILL | 10 CY | $385.00 | $300.00 | $298.77 | -$850 |
| 110-7002 EXCAV (CHANNEL) | 70 CY | $60.00 | $50.00 | $16.69 | -$700 |
| 104-7007 REMOV CONC (RIPRAP) | 7 CY | $200.00 | $200.00 | $26.91 | $0 |
Positive: the low bidder was cheaper on that item. These 16 items account for $11,400 of the $11,400 gap.
RB CONTRACTING, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 285 LF | $60.00 | $15.92 | 3.77x | $12,564 |
| 462-7060 CONC BOX CULV (4 FT X 4 FT)(EXTEND) | 4 LF | $2,000.00 | $742.91 | 2.69x | $5,028 |
| 400-7008 CUT & RESTORE ASPH PAVING | 30 SY | $300.00 | $140.13 | 2.14x | $4,796 |
| 110-7002 EXCAV (CHANNEL) | 70 CY | $60.00 | $16.69 | 3.59x | $3,031 |
| 529-7009 CONC CURB & GUTTER (TY II) | 24 LF | $150.00 | $32.57 | 4.61x | $2,818 |
| 500-7001 MOBILIZATION | 1 LS | $15,000.00 | $523,850.32 | 0.03x | -$508,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $5,000.00 | $11,585.04 | 0.43x | -$13,170 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 285 LF | $50.00 | $15.92 | 3.14x | $9,714 |
| 496-7006 REMOV STR (HEADWALL) | 1 EA | $5,000.00 | $1,533.90 | 3.26x | $3,466 |
| 132-7001 EMBANK (FNL)(OC)(TY A) | 100 CY | $50.00 | $22.62 | 2.21x | $2,738 |
| 500-7001 MOBILIZATION | 1 LS | $20,000.00 | $523,850.32 | 0.04x | -$503,850 |
ICOS MANAGEMENT, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 285 LF | $66.00 | $15.92 | 4.15x | $14,274 |
| 132-7001 EMBANK (FNL)(OC)(TY A) | 100 CY | $66.00 | $22.62 | 2.92x | $4,338 |
| 462-7060 CONC BOX CULV (4 FT X 4 FT)(EXTEND) | 4 LF | $1,540.00 | $742.91 | 2.07x | $3,188 |
| 496-7006 REMOV STR (HEADWALL) | 1 EA | $4,400.00 | $1,533.90 | 2.87x | $2,866 |
| 500-7001 MOBILIZATION | 1 LS | $44,000.00 | $523,850.32 | 0.08x | -$479,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $1.00 | $11,585.04 | 0.00x | -$23,168 |
JACKSON EXCAVATION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 466-7189 WINGWALL (PW - 2) (HW=5 FT) | 1 EA | $50,000.00 | $18,305.05 | 2.73x | $31,695 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 285 LF | $90.00 | $15.92 | 5.65x | $21,114 |
| 505-7001 TMA (STATIONARY) | 24 DAY | $520.00 | $217.57 | 2.39x | $7,258 |
| 132-7001 EMBANK (FNL)(OC)(TY A) | 100 CY | $60.00 | $22.62 | 2.65x | $3,738 |
| 401-7001 FLOWABLE BACKFILL | 10 CY | $600.00 | $298.77 | 2.01x | $3,012 |
| 500-7001 MOBILIZATION | 1 LS | $30,000.00 | $523,850.32 | 0.06x | -$493,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $2,500.00 | $11,585.04 | 0.22x | -$18,170 |
CATOCON, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 462-7060 CONC BOX CULV (4 FT X 4 FT)(EXTEND) | 4 LF | $5,000.00 | $742.91 | 6.73x | $17,028 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 285 LF | $75.00 | $15.92 | 4.71x | $16,839 |
| 110-7002 EXCAV (CHANNEL) | 70 CY | $150.00 | $16.69 | 8.99x | $9,331 |
| 496-7006 REMOV STR (HEADWALL) | 1 EA | $10,000.00 | $1,533.90 | 6.52x | $8,466 |
| 400-7008 CUT & RESTORE ASPH PAVING | 30 SY | $400.00 | $140.13 | 2.85x | $7,796 |
| 104-7007 REMOV CONC (RIPRAP) | 7 CY | $1,000.00 | $26.91 | 37.16x | $6,812 |
| 529-7009 CONC CURB & GUTTER (TY II) | 24 LF | $200.00 | $32.57 | 6.14x | $4,018 |
| 496-7018 REMOVE STR (GABION) | 40 LF | $150.00 | $57.12 | 2.63x | $3,715 |
| 132-7001 EMBANK (FNL)(OC)(TY A) | 100 CY | $50.00 | $22.62 | 2.21x | $2,738 |
| 500-7001 MOBILIZATION | 1 LS | $15,000.00 | $523,850.32 | 0.03x | -$508,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $5,000.00 | $11,585.04 | 0.43x | -$13,170 |