Signal Maint. FY26
6497-30-001 · let Apr 16, 2026 · Lamar, Paris · Routine Maintenance Project - Sealed
$549,355Low bid: NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION-16.7% vs estimate $659,279
$62,694Left on the table11.4% gap to the second bid
3BiddersSpread 50% low to high
50Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION | $549,355 | -16.7% | $62,694 | 3+$68,849 | 11-$191,222 | |
| 2 | TEXAS TRAFFIC CONTROL SYSTEMS, INC. | $612,049 | +11.4% | -7.2% | $211,990 | 3+$73,017 | 9-$197,112 |
| 3 | STRIPING TECHNOLOGY, L.P. | $824,039 | +50.0% | 25.0% | 8+$154,701 | 1-$101,780 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION vs TEXAS TRAFFIC CONTROL SYSTEMS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 6017-7015 VIDEO IMAGING AND RADAR DETECTOR | 4 EA | $5,500.00 | $1,500.00 | $10,622.18 | -$16,000 |
| 690-7074 INS OF TRF SIG PL FND (48" DRIL SHFT) | 40 LF | $400.00 | $785.00 | $501.51 | $15,400 |
| 690-7011 INSTALL OF CABLES | 10,000 LF | $6.50 | $5.00 | $5.39 | -$15,000 |
| 690-7004 INSTALL OF CONDUIT BY BORING | 1,000 LF | $21.00 | $35.00 | $20.66 | $14,000 |
| 690-7020 INSTALL OF ELECTRICAL SERVICE | 3 EA | $1,000.00 | $5,500.00 | $4,991.74 | $13,500 |
| 690-7131 INSTALL BBU SYSTEM | 2 EA | $1,000.00 | $7,700.00 | $5,893.34 | $13,400 |
| 6017-7018 VID IMAGE AND RADAR DET PROCESSOR SYS | 1 EA | $12,000.00 | $1,500.00 | $13,439.26 | -$10,500 |
| 680-7002 INSTALL HWY TRF SIG (ISOLATED) | 4 EA | $12,500.00 | $15,000.00 | $34,944.96 | $10,000 |
| 690-7019 REPLACE OF ELECTRICAL SERVICE | 2 EA | $1,000.00 | $5,500.00 | $4,286.17 | $9,000 |
| 690-7053 INSTALL OF SIGNAL POLE ASSM | 5 EA | $3,500.00 | $1,800.00 | $2,979.22 | -$8,500 |
| 6007-7001 BBU SYSTEM (EXTERNAL BATTERY CABINET) | 2 EA | $7,500.00 | $9,500.00 | $9,205.72 | $4,000 |
| 680-7001 INSTALL HWY TRF SIG (FLASH BEACON) | 2 EA | $6,000.00 | $8,000.00 | $4,405.34 | $4,000 |
| 690-7002 INSTALL OF CONDUIT BY TRENCHING | 2,000 LF | $10.00 | $12.00 | $14.44 | $4,000 |
| 690-7008 INSTALL OF GROUND BOXES | 10 EA | $1,100.00 | $1,500.00 | $1,344.82 | $4,000 |
| 690-7059 INSTALL OF PEDESTRIAN RAMPS | 1 EA | $800.00 | $4,500.00 | $3,200.00 | $3,700 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $3,200.00 | $3,500.00 | $600.85 | $3,600 |
| 690-7052 REPLACE OF SIGNAL POLE ASSM | 2 EA | $3,500.00 | $1,750.00 | $4,135.97 | -$3,500 |
| 690-7009 REMOVAL OF CABLES | 6,000 LF | $2.00 | $1.50 | $0.8964 | -$3,000 |
| 690-7098 INSTALL SPREAD SPECTRUM ANTENNA | 2 EA | $10.00 | $1,500.00 | $118.00 | $2,980 |
| 690-7045 REPLACE OF FLASHER CABINET | 2 EA | $700.00 | $2,000.00 | $1,739.52 | $2,600 |
Positive: the low bidder was cheaper on that item. These 20 items account for $47,680 of the $62,694 gap.
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $3,200.00 | $600.85 | 5.33x | $31,190 |
| 690-7025 REPLACE OF SIGNAL HEAD ASSM | 50 EA | $1,250.00 | $629.25 | 1.99x | $31,038 |
| 690-7009 REMOVAL OF CABLES | 6,000 LF | $2.00 | $0.8964 | 2.23x | $6,622 |
| 680-7002 INSTALL HWY TRF SIG (ISOLATED) | 4 EA | $12,500.00 | $34,944.96 | 0.36x | -$89,780 |
| 690-7138 VIVDS CAMERA (INSTALL) | 10 EA | $1,000.00 | $3,440.96 | 0.29x | -$24,410 |
| 690-7020 INSTALL OF ELECTRICAL SERVICE | 3 EA | $1,000.00 | $4,991.74 | 0.20x | -$11,975 |
| 6006-7002 VIVDS CAM ASSY FXD LNS | 4 EA | $1,500.00 | $4,074.68 | 0.37x | -$10,299 |
| 690-7131 INSTALL BBU SYSTEM | 2 EA | $1,000.00 | $5,893.34 | 0.17x | -$9,787 |
| 690-7100 REMOVE TRAFFIC SIGNAL | 2 EA | $2,000.00 | $6,615.18 | 0.30x | -$9,230 |
| 690-7084 INSTL VID IMAGE VEH DET SYS (VIVDS) | 5 EA | $1,000.00 | $2,773.96 | 0.36x | -$8,870 |
| 6006-7001 VIVDS PROSR SYS | 1 EA | $3,000.00 | $11,799.49 | 0.25x | -$8,799 |
| 690-7039 REPLACE OF CONTROL CABINET(GRND MNT) | 2 EA | $2,000.00 | $6,196.97 | 0.32x | -$8,394 |
| 690-7019 REPLACE OF ELECTRICAL SERVICE | 2 EA | $1,000.00 | $4,286.17 | 0.23x | -$6,572 |
TEXAS TRAFFIC CONTROL SYSTEMS, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $3,500.00 | $600.85 | 5.83x | $34,790 |
| 690-7025 REPLACE OF SIGNAL HEAD ASSM | 50 EA | $1,250.00 | $629.25 | 1.99x | $31,038 |
| 680-7001 INSTALL HWY TRF SIG (FLASH BEACON) | 2 EA | $8,000.00 | $4,405.34 | 1.82x | $7,189 |
| 680-7002 INSTALL HWY TRF SIG (ISOLATED) | 4 EA | $15,000.00 | $34,944.96 | 0.43x | -$79,780 |
| 6017-7015 VIDEO IMAGING AND RADAR DETECTOR | 4 EA | $1,500.00 | $10,622.18 | 0.14x | -$36,489 |
| 690-7138 VIVDS CAMERA (INSTALL) | 10 EA | $750.00 | $3,440.96 | 0.22x | -$26,910 |
| 6017-7018 VID IMAGE AND RADAR DET PROCESSOR SYS | 1 EA | $1,500.00 | $13,439.26 | 0.11x | -$11,939 |
| 6006-7001 VIVDS PROSR SYS | 1 EA | $1,500.00 | $11,799.49 | 0.13x | -$10,299 |
| 6006-7002 VIVDS CAM ASSY FXD LNS | 4 EA | $1,500.00 | $4,074.68 | 0.37x | -$10,299 |
| 690-7039 REPLACE OF CONTROL CABINET(GRND MNT) | 2 EA | $2,000.00 | $6,196.97 | 0.32x | -$8,394 |
| 690-7100 REMOVE TRAFFIC SIGNAL | 2 EA | $2,500.00 | $6,615.18 | 0.38x | -$8,230 |
| 690-7052 REPLACE OF SIGNAL POLE ASSM | 2 EA | $1,750.00 | $4,135.97 | 0.42x | -$4,772 |
STRIPING TECHNOLOGY, L.P.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 690-7074 INS OF TRF SIG PL FND (48" DRIL SHFT) | 40 LF | $1,500.00 | $501.51 | 2.99x | $39,940 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $3,500.00 | $600.85 | 5.83x | $34,790 |
| 6017-7018 VID IMAGE AND RADAR DET PROCESSOR SYS | 1 EA | $35,675.00 | $13,439.26 | 2.65x | $22,236 |
| 690-7009 REMOVAL OF CABLES | 6,000 LF | $3.25 | $0.8964 | 3.63x | $14,122 |
| 690-7020 INSTALL OF ELECTRICAL SERVICE | 3 EA | $9,250.00 | $4,991.74 | 1.85x | $12,775 |
| 690-7019 REPLACE OF ELECTRICAL SERVICE | 2 EA | $10,500.00 | $4,286.17 | 2.45x | $12,428 |
| 690-7131 INSTALL BBU SYSTEM | 2 EA | $10,525.00 | $5,893.34 | 1.79x | $9,263 |
| 690-7051 REMOVAL OF SIGNAL POLE ASSM | 2 EA | $6,250.00 | $1,675.77 | 3.73x | $9,148 |
| 680-7002 INSTALL HWY TRF SIG (ISOLATED) | 4 EA | $9,500.00 | $34,944.96 | 0.27x | -$101,780 |