Misc Concrete Repair DW
6497-03-001 · let Apr 8, 2026 · McLennan, Waco · Routine Maintenance Project - Sealed
$755,540Low bid: SHALOM SERVICES CORPORATION-22.0% vs estimate $968,609
$143,101Left on the table18.9% gap to the second bid
8BiddersSpread 109% low to high
28Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SHALOM SERVICES CORPORATION | $755,540 | -22.0% | $143,101 | 1+$5,475 | 3-$24,804 | |
| 2 | CROSS PLUS CONSTRUCTION, LLC | $898,641 | +18.9% | -7.2% | $63,109 | 2+$26,049 | 1-$87,289 |
| 3 | JACKSON EXCAVATION, LLC | $961,750 | +27.3% | -0.7% | $16,080 | 6+$219,370 | 4-$44,621 |
| 4 | GARRET SHIELDS INFRASTRUCTURE | $977,830 | +29.4% | 1.0% | $155,231 | 2+$25,184 | 1-$5,504 |
| 5 | ICOS MANAGEMENT, LLC | $1,133,061 | +50.0% | 17.0% | $58,361 | 9+$219,638 | 0 |
| 6 | ROAD DOCTORS LLC | $1,191,422 | +57.7% | 23.0% | $85,229 | ||
| 7 | STRUCTURAL INTEGRITY GROUP LLC | $1,276,651 | +69.0% | 31.8% | $302,584 | ||
| 8 | ROY JORGENSEN ASSOCIATES, INC. | $1,579,235 | +109.0% | 63.0% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
SHALOM SERVICES CORPORATION vs CROSS PLUS CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 2,075 CY | $170.00 | $223.00 | $184.74 | $109,975 |
| 420-7059 CL C CONC(PILE ENCASEMENT) | 370 LF | $300.00 | $200.00 | $435.92 | -$37,000 |
| 505-7001 TMA (STATIONARY) | 55 DAY | $1.00 | $500.00 | $217.57 | $27,445 |
| 401-7001 FLOWABLE BACKFILL | 236 CY | $300.00 | $400.00 | $298.77 | $23,600 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 379 SF | $185.00 | $155.00 | $150.68 | -$11,370 |
| 735-7060 DRIFTWOOD REMOVAL | 200 CY | $85.00 | $125.00 | $72.46 | $8,000 |
| 429-7001 CONC STR REPAIR(CLEAN & COAT WTH EPOXY) | 103 SF | $125.00 | $200.00 | $120.92 | $7,725 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 420 CY | $30.00 | $42.00 | $16.96 | $5,040 |
| 420-7067 CL C CONC (MISC) | 10 CY | $700.00 | $1,200.00 | $1,569.38 | $5,000 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 100 CY | $190.00 | $225.00 | $190.61 | $3,500 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 100 CY | $190.00 | $221.00 | $179.97 | $3,100 |
| 420-7146 CL C CONC (WINGWALLS) | 5 CY | $2,000.00 | $1,600.00 | $2,100.77 | -$2,000 |
| 467-7348 SET (TY II) (30 IN) (RCP) (6: 1) (P) | 2 EA | $3,500.00 | $2,500.00 | $3,539.26 | -$2,000 |
| 496-7004 REMOV STR (SET) | 2 EA | $850.00 | $123.00 | $514.07 | -$1,454 |
| 420-7011 CL B CONC (MISC) | 25 CY | $750.00 | $800.00 | $760.29 | $1,250 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 12 DAY | $100.00 | $1.00 | $87.82 | -$1,188 |
| 529-7012 CONC CURB (DOWELED) | 50 LF | $35.00 | $52.00 | $18.32 | $850 |
| 104-7046 REMOV CONC (MISC) | 35 SY | $30.00 | $48.00 | $23.49 | $630 |
| 529-7009 CONC CURB & GUTTER (TY II) | 79 LF | $45.00 | $52.00 | $32.57 | $553 |
| 158-7004 SPEC EXCAV WORK (ORIGINAL) | 20 CY | $75.00 | $100.00 | $32.17 | $500 |
Positive: the low bidder was cheaper on that item. These 20 items account for $142,156 of the $143,101 gap.
SHALOM SERVICES CORPORATION: unbalanced items
Placed 1CROSS PLUS CONSTRUCTION, LLC: unbalanced items
Placed 2JACKSON EXCAVATION, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 420-7059 CL C CONC(PILE ENCASEMENT) | 370 LF | $850.00 | $435.92 | 1.95x | $153,211 |
| 500-7002 MOBILIZATION (CALLOUT) | 7 EA | $3,000.00 | $600.85 | 4.99x | $16,794 |
| 467-7003 SET (REPLACE PIPE RUNNER ASSEMBLY) | 6 EA | $3,000.00 | $678.56 | 4.42x | $13,929 |
| 429-7001 CONC STR REPAIR(CLEAN & COAT WTH EPOXY) | 103 SF | $250.00 | $120.92 | 2.07x | $13,295 |
| 500-7033 MOBILIZATION (EMERGENCY) | 3 EA | $5,000.00 | $844.81 | 5.92x | $12,466 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 420 CY | $40.00 | $16.96 | 2.36x | $9,675 |
| 420-7011 CL B CONC (MISC) | 25 CY | $40.00 | $760.29 | 0.05x | -$18,007 |
| 505-7001 TMA (STATIONARY) | 55 DAY | $10.00 | $217.57 | 0.05x | -$11,416 |
| 420-7067 CL C CONC (MISC) | 10 CY | $600.00 | $1,569.38 | 0.38x | -$9,694 |
| 420-7146 CL C CONC (WINGWALLS) | 5 CY | $1,000.00 | $2,100.77 | 0.48x | -$5,504 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 4ICOS MANAGEMENT, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 7 EA | $7,700.00 | $600.85 | 12.82x | $49,694 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 379 SF | $275.00 | $150.68 | 1.83x | $47,117 |
| 500-7033 MOBILIZATION (EMERGENCY) | 3 EA | $13,200.00 | $844.81 | 15.62x | $37,066 |
| 467-7003 SET (REPLACE PIPE RUNNER ASSEMBLY) | 6 EA | $4,400.00 | $678.56 | 6.48x | $22,329 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 420 CY | $66.00 | $16.96 | 3.89x | $20,595 |
| 467-7348 SET (TY II) (30 IN) (RCP) (6: 1) (P) | 2 EA | $11,000.00 | $3,539.26 | 3.11x | $14,921 |
| 735-7060 DRIFTWOOD REMOVAL | 200 CY | $132.00 | $72.46 | 1.82x | $11,908 |
| 429-7009 CONC STR REPAIR (STANDARD) | 70 SF | $264.00 | $146.35 | 1.80x | $8,236 |
| 496-7004 REMOV STR (SET) | 2 EA | $4,400.00 | $514.07 | 8.56x | $7,772 |