Pavement Markings Metro
6498-23-001 · let Apr 14, 2026 · Harris, Houston · Routine Maintenance Project - Sealed
$687,170Low bid: BATTERSON, LLP-21.9% vs estimate $879,642
$73,541Left on the table10.7% gap to the second bid
3BiddersSpread 41% low to high
41Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BATTERSON, LLP | $687,170 | -21.9% | $73,541 | 3+$55,198 | 4-$564,376 | |
| 2 | STRIPE LINES, INC. | $760,711 | +10.7% | -13.5% | $207,630 | 3+$158,987 | 6-$575,014 |
| 3 | TRP INFRASTRUCTURE SERVICES, LLC | $968,341 | +40.9% | 10.1% | 3+$120,711 | 2-$486,282 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
BATTERSON, LLP vs STRIPE LINES, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 MO | $1,500.00 | $85,000.00 | $11,585.04 | $83,500 |
| 666-7242 RE PM TY III (W)(12")(SLD) | 9,000 LF | $2.00 | $7.75 | $2.62 | $51,750 |
| 668-7135 PREFAB PM TY C (MULTI)(SHIELD) | 89 EA | $2,500.00 | $1,984.69 | $2,331.55 | -$45,863 |
| 677-7022 ELIM EXT PM & MRKS (SHIELD) | 89 EA | $120.00 | $619.00 | $175.80 | $44,411 |
| 668-7093 PREFAB PM TY C (W)(DBL ARROW) | 45 EA | $775.00 | $278.13 | $314.80 | -$22,359 |
| 668-7091 PREFAB PM TY C (W)(ARROW) | 67 EA | $458.00 | $176.70 | $201.69 | -$18,847 |
| 668-7103 PREFAB PM TY C (W)(WORD) | 67 EA | $508.00 | $231.37 | $249.54 | -$18,534 |
| 666-7262 RE PM TY III (BLK)(6")(SHADOW) | 85,500 LF | $0.8500 | $0.7100 | $0.7183 | -$11,970 |
| 6065-7001 MLTPLY PV MK W/WTY (W) (6") (SLD) | 56,250 LF | $0.6300 | $0.7800 | $0.6352 | $8,438 |
| 6065-7004 MLTPLY PV MK W/WTY (Y) (6") (SLD) | 56,250 LF | $0.6300 | $0.7800 | $0.6356 | $8,438 |
| 666-7072 REFL PAV MRK TY I(W)(EXIT GORE)(100MIL) | 18 EA | $575.00 | $190.21 | $964.21 | -$6,926 |
| 668-7001 PRFB RUMBLE STRIP (BLK)(4')(TRANSVERSE) | 1,800 LF | $6.00 | $9.28 | $10.44 | $5,904 |
| 677-7006 ELIM EXT PM & MRKS (12") | 9,000 LF | $1.50 | $0.8500 | $1.27 | -$5,850 |
| 6065-7002 MLTPLY PV MK W/WTY (W) (6") (BRK) | 85,500 LF | $0.7200 | $0.7800 | $0.7024 | $5,130 |
| 500-7001 MOBILIZATION | 1 LS | $5,000.00 | $10,000.00 | $523,850.32 | $5,000 |
| 672-7006 REFL PAV MRKR TY II-C-R | 6,425 EA | $5.50 | $4.75 | $4.19 | -$4,819 |
| 677-7017 ELIM EXT PM & MRKS (EXIT GORE) | 18 EA | $300.00 | $100.00 | $362.62 | -$3,600 |
| 668-7100 PREFAB PM TY C (W)(LN REDUCT ARROW) | 6 EA | $885.00 | $300.00 | $467.68 | -$3,510 |
| 666-7069 REFL PAV MRK TY I(W)(ENTR GORE)(100MIL) | 18 EA | $365.00 | $181.10 | $869.92 | -$3,310 |
| 668-7102 PREFAB PM TY C (W)(NUMBER) | 18 EA | $245.00 | $78.63 | $129.07 | -$2,995 |
Positive: the low bidder was cheaper on that item. These 20 items account for $63,987 of the $73,541 gap.
BATTERSON, LLP: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 668-7093 PREFAB PM TY C (W)(DBL ARROW) | 45 EA | $775.00 | $314.80 | 2.46x | $20,709 |
| 668-7103 PREFAB PM TY C (W)(WORD) | 67 EA | $508.00 | $249.54 | 2.04x | $17,317 |
| 668-7091 PREFAB PM TY C (W)(ARROW) | 67 EA | $458.00 | $201.69 | 2.27x | $17,173 |
| 500-7001 MOBILIZATION | 1 LS | $5,000.00 | $523,850.32 | 0.01x | -$518,850 |
| 505-7003 TMA (MOBILE OPERATION) | 120 DAY | $10.00 | $229.60 | 0.04x | -$26,352 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 MO | $1,500.00 | $11,585.04 | 0.13x | -$10,085 |
| 666-7069 REFL PAV MRK TY I(W)(ENTR GORE)(100MIL) | 18 EA | $365.00 | $869.92 | 0.42x | -$9,089 |
STRIPE LINES, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 MO | $85,000.00 | $11,585.04 | 7.34x | $73,415 |
| 666-7242 RE PM TY III (W)(12")(SLD) | 9,000 LF | $7.75 | $2.62 | 2.95x | $46,127 |
| 677-7022 ELIM EXT PM & MRKS (SHIELD) | 89 EA | $619.00 | $175.80 | 3.52x | $39,445 |
| 500-7001 MOBILIZATION | 1 LS | $10,000.00 | $523,850.32 | 0.02x | -$513,850 |
| 505-7003 TMA (MOBILE OPERATION) | 120 DAY | $12.00 | $229.60 | 0.05x | -$26,112 |
| 666-7072 REFL PAV MRK TY I(W)(EXIT GORE)(100MIL) | 18 EA | $190.21 | $964.21 | 0.20x | -$13,932 |
| 666-7069 REFL PAV MRK TY I(W)(ENTR GORE)(100MIL) | 18 EA | $181.10 | $869.92 | 0.21x | -$12,399 |
| 677-7017 ELIM EXT PM & MRKS (EXIT GORE) | 18 EA | $100.00 | $362.62 | 0.28x | -$4,727 |
| 677-7016 ELIM EXT PM & MRKS (ENTR GORE) | 18 EA | $100.00 | $321.88 | 0.31x | -$3,994 |
TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 MO | $85,000.00 | $11,585.04 | 7.34x | $73,415 |
| 672-7006 REFL PAV MRKR TY II-C-R | 6,425 EA | $10.00 | $4.19 | 2.38x | $37,306 |
| 666-7363 PAVEMENT SLER (SYMBOL) | 89 EA | $145.00 | $32.75 | 4.43x | $9,990 |
| 500-7001 MOBILIZATION | 1 LS | $65,000.00 | $523,850.32 | 0.12x | -$458,850 |
| 505-7003 TMA (MOBILE OPERATION) | 120 DAY | $1.00 | $229.60 | 0.00x | -$27,432 |