Bid Tab X-ray: 6497-92-001

Apr 6, 2026 · Bowie Sign up free
Set your company to personalize scores

Emulsion District Wide FY 26

6497-92-001 · let Apr 6, 2026 · Bowie, Atlanta · Material Maintenance Project

$669,900Low bid: WRIGHT ASPHALT PRODUCTS COMPANY LLC-4.0% vs estimate $697,500
$231,950Left on the table34.6% gap to the second bid
2BiddersSpread 35% low to high
6Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1WRIGHT ASPHALT PRODUCTS COMPANY LLC $669,900-4.0% $231,950 0 0
2ERGON ASPHALT & EMULSIONS, INC. $901,850+34.6%29.3% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

WRIGHT ASPHALT PRODUCTS COMPANY LLC vs ERGON ASPHALT & EMULSIONS, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
8003-7138 CHFRS-2P (DEL)(SITE 1)175,000 GAL $2.70$3.59$2.82 $155,750
8003-7204 CSS-1H (40%)(DEL)(SITE 1)35,000 GAL $1.44$2.09$1.39 $22,750
8003-7086 CSS-1H (PICKUP)25,000 GAL $2.25$3.05$2.52 $20,000
8003-7203 CSS-1H (40%)(PICKUP)30,000 GAL $1.25$1.90$1.20 $19,500
8003-7137 CHFRS-2P (PICKUP)15,000 GAL $2.70$3.40$2.72 $10,500
8003-7087 CSS-1H (DEL)(SITE 1)5,000 GAL $2.55$3.24$2.49 $3,450

Positive: the low bidder was cheaper on that item. These 6 items account for $231,950 of the $231,950 gap.