Bear Creek and Mayde Creek at HW6 Bridge
6495-93-001 · let Apr 14, 2026 · Harris, Houston · Bridge Preventative Maintenance - Sealed
$393,900Low bid: GARRET SHIELDS INFRASTRUCTURE-23.8% vs estimate $517,099
$65,281Left on the table16.6% gap to the second bid
5BiddersSpread 97% low to high
21Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | GARRET SHIELDS INFRASTRUCTURE | $393,900 | -23.8% | $65,281 | 5+$88,794 | 2-$523,605 | |
| 2 | ICOS MANAGEMENT, LLC | $459,181 | +16.6% | -11.2% | $54,445 | 6+$106,494 | 4-$514,569 |
| 3 | ROAD DOCTORS LLC | $513,626 | +30.4% | -0.7% | $4,784 | 6+$131,141 | 4-$518,506 |
| 4 | JACKSON EXCAVATION, LLC | $518,410 | +31.6% | 0.3% | $255,684 | 4+$224,932 | 3-$551,203 |
| 5 | MC2 CIVIL, LLC | $774,094 | +96.5% | 49.7% | 11+$360,127 | 1-$438,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
GARRET SHIELDS INFRASTRUCTURE vs ICOS MANAGEMENT, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $20,000.00 | $107,000.00 | $523,850.32 | $87,000 |
| 7020-7003 GEN DEBRIS REMOVE FROM UNDER BRIDGES | 806 CY | $100.00 | $54.00 | $29.72 | -$37,076 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 1,600 SF | $30.00 | $11.00 | $28.47 | -$30,400 |
| 110-7002 EXCAV (CHANNEL) | 199 CY | $40.00 | $160.00 | $16.69 | $23,880 |
| 104-7006 REMOV CONC (RIPRAP) | 225 SY | $40.00 | $107.00 | $14.32 | $15,075 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $5,000.00 | $1.00 | $11,585.04 | -$14,997 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 199 CY | $200.00 | $268.00 | $184.74 | $13,532 |
| 752-7001 TREE TRIMMING / BRUSH REMOVAL | 4 MI | $1,000.00 | $4,280.00 | $1,716.86 | $13,120 |
| 506-7024 CONSTRUCTION EXITS (REMOVE) | 2,223 SY | $10.00 | $5.00 | $8.93 | -$11,115 |
| 776-7003 REPAIR (STEEL PED. RAIL) | 160 LF | $200.00 | $267.00 | $148.66 | $10,720 |
| 506-7021 CONSTRUCTION EXITS (INSTALL) (TY 2) | 2,223 SY | $15.00 | $11.00 | $26.75 | -$8,892 |
| 752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 0.92 AC | $2,000.00 | $10,700.00 | $1,602.83 | $8,004 |
| 400-7010 CEM STABIL BKFL | 136 CY | $250.00 | $193.00 | $138.14 | -$7,752 |
| 432-7002 RIPRAP (CONC)(5 IN) | 20 CY | $600.00 | $856.00 | $585.15 | $5,120 |
| 104-7047 REMOV CONC (MISC) | 19 CY | $500.00 | $268.00 | $156.71 | -$4,408 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 75 LF | $30.00 | $54.00 | $25.60 | $1,800 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 64 SF | $200.00 | $214.00 | $150.68 | $896 |
| 442-7017 MISC NON-BRIDGE (NBIS) | 10 LB | $20.00 | $107.00 | $47.98 | $870 |
| 505-7001 TMA (STATIONARY) | 24 DAY | $300.00 | $264.00 | $217.57 | -$864 |
| 429-7001 CONC STR REPAIR(CLEAN & COAT WTH EPOXY) | 12 SF | $150.00 | $214.00 | $120.92 | $768 |
Positive: the low bidder was cheaper on that item. These 20 items account for $65,281 of the $65,281 gap.
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 7020-7003 GEN DEBRIS REMOVE FROM UNDER BRIDGES | 806 CY | $100.00 | $29.72 | 3.36x | $56,642 |
| 400-7010 CEM STABIL BKFL | 136 CY | $250.00 | $138.14 | 1.81x | $15,212 |
| 104-7047 REMOV CONC (MISC) | 19 CY | $500.00 | $156.71 | 3.19x | $6,523 |
| 104-7006 REMOV CONC (RIPRAP) | 225 SY | $40.00 | $14.32 | 2.79x | $5,778 |
| 110-7002 EXCAV (CHANNEL) | 199 CY | $40.00 | $16.69 | 2.40x | $4,638 |
| 500-7001 MOBILIZATION | 1 LS | $20,000.00 | $523,850.32 | 0.04x | -$503,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $5,000.00 | $11,585.04 | 0.43x | -$19,755 |
ICOS MANAGEMENT, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7002 EXCAV (CHANNEL) | 199 CY | $160.00 | $16.69 | 9.58x | $28,518 |
| 104-7006 REMOV CONC (RIPRAP) | 225 SY | $107.00 | $14.32 | 7.47x | $20,853 |
| 7020-7003 GEN DEBRIS REMOVE FROM UNDER BRIDGES | 806 CY | $54.00 | $29.72 | 1.82x | $19,566 |
| 776-7003 REPAIR (STEEL PED. RAIL) | 160 LF | $267.00 | $148.66 | 1.80x | $18,935 |
| 752-7001 TREE TRIMMING / BRUSH REMOVAL | 4 MI | $4,280.00 | $1,716.86 | 2.49x | $10,253 |
| 752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 0.92 AC | $10,700.00 | $1,602.83 | 6.68x | $8,369 |
| 500-7001 MOBILIZATION | 1 LS | $107,000.00 | $523,850.32 | 0.20x | -$416,850 |
| 506-7021 CONSTRUCTION EXITS (INSTALL) (TY 2) | 2,223 SY | $11.00 | $26.75 | 0.41x | -$35,014 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $1.00 | $11,585.04 | 0.00x | -$34,752 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 1,600 SF | $11.00 | $28.47 | 0.39x | -$27,953 |
ROAD DOCTORS LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 1,600 SF | $60.00 | $28.47 | 2.11x | $50,447 |
| 752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 0.92 AC | $29,000.00 | $1,602.83 | 18.09x | $25,205 |
| 400-7010 CEM STABIL BKFL | 136 CY | $300.00 | $138.14 | 2.17x | $22,012 |
| 104-7006 REMOV CONC (RIPRAP) | 225 SY | $100.00 | $14.32 | 6.98x | $19,278 |
| 110-7002 EXCAV (CHANNEL) | 199 CY | $60.00 | $16.69 | 3.59x | $8,618 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 75 LF | $100.00 | $25.60 | 3.91x | $5,580 |
| 500-7001 MOBILIZATION | 1 LS | $40,000.00 | $523,850.32 | 0.08x | -$483,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $5,000.00 | $11,585.04 | 0.43x | -$19,755 |
| 432-7002 RIPRAP (CONC)(5 IN) | 20 CY | $100.00 | $585.15 | 0.17x | -$9,703 |
| 505-7001 TMA (STATIONARY) | 24 DAY | $1.00 | $217.57 | 0.00x | -$5,198 |
JACKSON EXCAVATION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 506-7021 CONSTRUCTION EXITS (INSTALL) (TY 2) | 2,223 SY | $90.00 | $26.75 | 3.36x | $140,603 |
| 7020-7003 GEN DEBRIS REMOVE FROM UNDER BRIDGES | 806 CY | $90.00 | $29.72 | 3.03x | $48,582 |
| 506-7024 CONSTRUCTION EXITS (REMOVE) | 2,223 SY | $20.00 | $8.93 | 2.24x | $24,614 |
| 752-7001 TREE TRIMMING / BRUSH REMOVAL | 4 MI | $4,500.00 | $1,716.86 | 2.62x | $11,133 |
| 500-7001 MOBILIZATION | 1 LS | $2,500.00 | $523,850.32 | 0.00x | -$521,350 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $2,500.00 | $11,585.04 | 0.22x | -$27,255 |
| 104-7047 REMOV CONC (MISC) | 19 CY | $20.00 | $156.71 | 0.13x | -$2,597 |
MC2 CIVIL, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 7020-7003 GEN DEBRIS REMOVE FROM UNDER BRIDGES | 806 CY | $130.00 | $29.72 | 4.37x | $80,822 |
| 506-7021 CONSTRUCTION EXITS (INSTALL) (TY 2) | 2,223 SY | $60.00 | $26.75 | 2.24x | $73,913 |
| 104-7006 REMOV CONC (RIPRAP) | 225 SY | $200.00 | $14.32 | 13.97x | $41,778 |
| 110-7002 EXCAV (CHANNEL) | 199 CY | $200.00 | $16.69 | 11.98x | $36,478 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 199 CY | $350.00 | $184.74 | 1.89x | $32,887 |
| 776-7003 REPAIR (STEEL PED. RAIL) | 160 LF | $300.00 | $148.66 | 2.02x | $24,215 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 64 SF | $500.00 | $150.68 | 3.32x | $22,356 |
| 432-7002 RIPRAP (CONC)(5 IN) | 20 CY | $1,600.00 | $585.15 | 2.73x | $20,297 |
| 752-7001 TREE TRIMMING / BRUSH REMOVAL | 4 MI | $5,000.00 | $1,716.86 | 2.91x | $13,133 |
| 752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 0.92 AC | $10,000.00 | $1,602.83 | 6.24x | $7,725 |
| 500-7001 MOBILIZATION | 1 LS | $85,000.00 | $523,850.32 | 0.16x | -$438,850 |