FY 26 Pavement Repair (SB)
6470-82-001 · let Apr 7, 2026 · Cameron, Pharr · Routine Maintenance Project - Sealed
$4,198,453Low bid: FOREMOST PAVING, INC.+12.4% vs estimate $3,735,225
$181,685Left on the table4.3% gap to the second bid
4BiddersSpread 82% low to high
23Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FOREMOST PAVING, INC. | $4,198,453 | 12.4% | $181,685 | 2+$76,481 | 2-$458,465 | |
| 2 | IOC COMPANY LLC | $4,380,137 | +4.3% | 17.3% | $1,582,157 | 1+$75,542 | 1-$473,850 |
| 3 | POSILLICO CIVIL, INC. | $5,962,294 | +42.0% | 59.6% | $1,691,644 | 3+$145,680 | 0 |
| 4 | CK NEWBERRY, LLC | $7,653,938 | +82.3% | 104.9% | 3+$3,111,737 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
FOREMOST PAVING, INC. vs IOC COMPANY LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7064 SP MIXES SP-D SAC-A PG76-22 | 10,960 TON | $139.53 | $166.50 | $129.17 | $295,591 |
| 354-7018 PLANE & TEXT ASPH CONC PAV(1.5") | 243,676 SY | $3.04 | $2.00 | $1.85 | -$253,423 |
| 346-7009 STONE-MTRX-ASPH SMA-D SAC-A PG76-22 | 9,875 TON | $155.96 | $170.00 | $152.44 | $138,645 |
| 3007-7001 BONDING COURSE | 17,057 GAL | $2.93 | $7.75 | $3.32 | $82,215 |
| 500-7001 MOBILIZATION | 1 LS | $87,500.00 | $50,000.00 | $523,850.32 | -$37,500 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 91,260 LF | $0.9600 | $0.5900 | $0.4757 | -$33,766 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 69,970 LF | $0.9600 | $0.6300 | $0.4986 | -$23,090 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $57.93 | $150.00 | $217.57 | $11,048 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $4,213.55 | $7,000.00 | $11,585.04 | $8,359 |
| 666-7408 REFL PAV MRK TY I (W)6"(BRK)(100MIL) | 25,800 LF | $0.9600 | $0.6600 | $0.5627 | -$7,740 |
| 666-7030 REFL PAV MRK TY I (W)12"(SLD)(100MIL) | 3,920 LF | $2.53 | $3.27 | $2.94 | $2,901 |
| 666-7196 RE PM TY II (W) (EXIT GORE) | 3 EA | $1,186.75 | $306.68 | $370.61 | -$2,640 |
| 666-7195 RE PM TY II (W) (ENTR GORE) | 2 EA | $1,186.75 | $306.68 | $337.62 | -$1,760 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 12,500 EA | $1.15 | $1.29 | $1.03 | $1,750 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 3,499 EA | $1.15 | $1.62 | $0.5715 | $1,645 |
| 666-7024 REFL PAV MRK TY I (W)8"(SLD)(100MIL) | 900 LF | $1.27 | $2.86 | $0.9489 | $1,431 |
| 672-7006 REFL PAV MRKR TY II-C-R | 1,380 EA | $6.57 | $5.93 | $4.19 | -$883 |
| 672-7002 REFL PAV MRKR TY I-C | 285 EA | $6.57 | $4.91 | $4.04 | -$473 |
| 668-7103 PREFAB PM TY C (W)(WORD) | 4 EA | $404.00 | $286.24 | $249.54 | -$471 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 190 LF | $12.12 | $11.65 | $7.19 | -$89 |
Positive: the low bidder was cheaper on that item. These 20 items account for $181,749 of the $181,685 gap.
FOREMOST PAVING, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 91,260 LF | $0.9600 | $0.4757 | 2.02x | $44,197 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 69,970 LF | $0.9600 | $0.4986 | 1.93x | $32,284 |
| 500-7001 MOBILIZATION | 1 LS | $87,500.00 | $523,850.32 | 0.17x | -$436,350 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $4,213.55 | $11,585.04 | 0.36x | -$22,114 |