01 On-Call Reflect Pvment Marks 0426
6495-33-001 · let Apr 15, 2026 · Navarro, Dallas · Routine Maintenance Project - Sealed
$334,438Low bid: TRP INFRASTRUCTURE SERVICES, LLC-19.8% vs estimate $417,029
$58,540Left on the table17.5% gap to the second bid
3BiddersSpread 37% low to high
39Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TRP INFRASTRUCTURE SERVICES, LLC | $334,438 | -19.8% | $58,540 | 1+$34,790 | 3-$35,070 | |
| 2 | D. I. J. CONSTRUCTION, INC. | $392,978 | +17.5% | -5.8% | $64,698 | 4+$68,082 | 3-$32,221 |
| 3 | STRIPE-A-ZONE, LLC | $457,675 | +36.8% | 9.7% | 6+$69,211 | 2-$27,075 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
TRP INFRASTRUCTURE SERVICES, LLC vs D. I. J. CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $3,500.00 | $5,000.00 | $600.85 | $18,000 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 150,000 LF | $0.1900 | $0.3000 | $0.1749 | $16,500 |
| 666-7347 PAVEMENT SLER 6" | 65,000 LF | $0.1000 | $0.2600 | $0.1841 | $10,400 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 65,000 LF | $0.1900 | $0.3000 | $0.1701 | $7,150 |
| 677-7001 ELIM EXT PM & MRKS (4") | 100,000 LF | $0.2700 | $0.2000 | $0.2643 | -$7,000 |
| 666-7171 RE PM TY II (W) 4" (SLD) | 120,000 LF | $0.1500 | $0.2000 | $0.1960 | $6,000 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 26,400 LF | $0.8900 | $0.7000 | $0.6515 | -$5,016 |
| 666-7270 RE PROFILE PM TY I(Y)6"(SLD)(100MIL) | 26,400 LF | $0.8900 | $0.7000 | $0.6629 | -$5,016 |
| 666-7210 RE PM TY II (Y) 4" (SLD) | 85,000 LF | $0.1500 | $0.2000 | $0.1822 | $4,250 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 4,400 LF | $0.2200 | $1.00 | $0.2040 | $3,432 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 4,400 LF | $0.2200 | $1.00 | $0.2394 | $3,432 |
| 666-7346 PAVEMENT SLER 4" | 20,000 LF | $0.1000 | $0.2000 | $0.4948 | $2,000 |
| 666-7405 REFL PAV MRK TY I (W)4"(SLD)(100MIL) | 15,000 LF | $0.4200 | $0.3000 | $0.3245 | -$1,800 |
| 666-7417 REFL PAV MRK TY I (Y)4"(SLD)(100MIL) | 15,000 LF | $0.4200 | $0.3000 | $0.3399 | -$1,800 |
| 666-7274 RE PROFILE PM TY I(Y)6"(BRK)(100MIL) | 6,600 LF | $0.9700 | $0.7000 | $0.6738 | -$1,782 |
| 666-7208 RE PM TY II (Y) 4" (BRK) | 35,000 LF | $0.1500 | $0.2000 | $0.2426 | $1,750 |
| 672-7004 REFL PAV MRKR TY II-A-A | 1,500 EA | $3.50 | $4.60 | $3.97 | $1,650 |
| 666-7348 PAVEMENT SLER 8" | 5,000 LF | $0.2000 | $0.5000 | $0.3318 | $1,500 |
| 666-7168 RE PM TY II (W) 4" (BRK) | 20,000 LF | $0.1500 | $0.2000 | $0.2707 | $1,000 |
| 677-7004 ELIM EXT PM & MRKS (8") | 5,000 LF | $0.7000 | $0.9000 | $0.6468 | $1,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $55,650 of the $58,540 gap.
TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $3,500.00 | $600.85 | 5.83x | $34,790 |
| 505-7003 TMA (MOBILE OPERATION) | 100 DAY | $0.0100 | $229.60 | 0.00x | -$22,959 |
| 666-7346 PAVEMENT SLER 4" | 20,000 LF | $0.1000 | $0.4948 | 0.20x | -$7,896 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 75,000 LF | $0.0100 | $0.0662 | 0.15x | -$4,215 |
D. I. J. CONSTRUCTION, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $5,000.00 | $600.85 | 8.32x | $52,790 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 65,000 LF | $0.3000 | $0.1701 | 1.76x | $8,444 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 4,400 LF | $1.00 | $0.2040 | 4.90x | $3,502 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 4,400 LF | $1.00 | $0.2394 | 4.18x | $3,347 |
| 505-7003 TMA (MOBILE OPERATION) | 100 DAY | $1.00 | $229.60 | 0.00x | -$22,860 |
| 666-7346 PAVEMENT SLER 4" | 20,000 LF | $0.2000 | $0.4948 | 0.40x | -$5,896 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 75,000 LF | $0.0200 | $0.0662 | 0.30x | -$3,465 |
STRIPE-A-ZONE, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 677-7001 ELIM EXT PM & MRKS (4") | 100,000 LF | $0.7000 | $0.2643 | 2.65x | $43,570 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 4,400 LF | $1.85 | $0.2040 | 9.07x | $7,242 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 4,400 LF | $1.85 | $0.2394 | 7.73x | $7,087 |
| 666-7405 REFL PAV MRK TY I (W)4"(SLD)(100MIL) | 15,000 LF | $0.6000 | $0.3245 | 1.85x | $4,133 |
| 666-7417 REFL PAV MRK TY I (Y)4"(SLD)(100MIL) | 15,000 LF | $0.6000 | $0.3399 | 1.77x | $3,902 |
| 677-7002 ELIM EXT PM & MRKS (6") | 6,250 LF | $0.8000 | $0.2755 | 2.90x | $3,278 |
| 505-7003 TMA (MOBILE OPERATION) | 100 DAY | $1.00 | $229.60 | 0.00x | -$22,860 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 75,000 LF | $0.0100 | $0.0662 | 0.15x | -$4,215 |