Reflective Pavement Mrk RMC 6493-67-001
6493-67-001 · let Apr 14, 2026 · Montgomery, Houston · Routine Maintenance Project - Sealed
$693,268Low bid: TRP INFRASTRUCTURE SERVICES, LLC-8.3% vs estimate $755,901
$39,902Left on the table5.8% gap to the second bid
4BiddersSpread 44% low to high
91Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TRP INFRASTRUCTURE SERVICES, LLC | $693,268 | -8.3% | $39,902 | 0 | 6-$93,893 | |
| 2 | STRIPE LINES, INC. | $733,170 | +5.8% | -3.0% | $972 | 5+$91,699 | 9-$123,864 |
| 3 | BATTERSON, LLP | $734,142 | +5.9% | -2.9% | $262,023 | 3+$42,123 | 5-$84,862 |
| 4 | INTERSTATE BARRICADES & MARKINGS, INC. | $996,165 | +43.7% | 31.8% | 13+$226,012 | 3-$45,376 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
TRP INFRASTRUCTURE SERVICES, LLC vs STRIPE LINES, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 666-7347 PAVEMENT SLER 6" | 150,000 LF | $0.1300 | $0.3500 | $0.1841 | $33,000 |
| 500-7033 MOBILIZATION (EMERGENCY) | 6 EA | $500.00 | $5,000.00 | $844.81 | $27,000 |
| 677-7002 ELIM EXT PM & MRKS (6") | 250,000 LF | $0.3500 | $0.2500 | $0.2755 | -$25,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $500.00 | $2,500.00 | $600.85 | $24,000 |
| 672-7004 REFL PAV MRKR TY II-A-A | 10,000 EA | $4.25 | $6.00 | $3.97 | $17,500 |
| 672-7006 REFL PAV MRKR TY II-C-R | 10,000 EA | $4.25 | $6.00 | $4.19 | $17,500 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 7,500 LF | $7.00 | $5.55 | $7.19 | -$10,875 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 25,000 LF | $0.8500 | $1.25 | $0.6515 | $10,000 |
| 677-7008 ELIM EXT PM & MRKS (24") | 4,500 LF | $3.00 | $0.9200 | $2.87 | -$9,360 |
| 677-7006 ELIM EXT PM & MRKS (12") | 16,000 LF | $1.35 | $0.8500 | $1.27 | -$8,000 |
| 666-7114 REFL PAV MRK TY I (Y)8"(SLD)(100MIL) | 15,000 LF | $1.35 | $0.9200 | $0.9877 | -$6,450 |
| 668-7093 PREFAB PM TY C (W)(DBL ARROW) | 250 EA | $300.00 | $275.00 | $314.80 | -$6,250 |
| 666-7072 REFL PAV MRK TY I(W)(EXIT GORE)(100MIL) | 20 EA | $438.00 | $150.00 | $964.21 | -$5,760 |
| 666-7069 REFL PAV MRK TY I(W)(ENTR GORE)(100MIL) | 20 EA | $412.00 | $150.00 | $869.92 | -$5,240 |
| 677-7016 ELIM EXT PM & MRKS (ENTR GORE) | 20 EA | $244.00 | $25.00 | $321.88 | -$4,380 |
| 677-7017 ELIM EXT PM & MRKS (EXIT GORE) | 20 EA | $244.00 | $25.00 | $362.62 | -$4,380 |
| 505-7003 TMA (MOBILE OPERATION) | 150 DAY | $1.00 | $25.00 | $229.60 | $3,600 |
| 666-7352 PAVEMENT SLER 24" | 3,500 LF | $0.5200 | $1.50 | $1.84 | $3,430 |
| 678-7006 PAV SURF PREP FOR MRK (12") | 7,500 LF | $0.5000 | $0.0500 | $0.2487 | -$3,375 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 200,000 LF | $0.0250 | $0.0100 | $0.0662 | -$3,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $43,960 of the $39,902 gap.
TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 150 DAY | $1.00 | $229.60 | 0.00x | -$34,290 |
| 505-7001 TMA (STATIONARY) | 125 DAY | $1.00 | $217.57 | 0.00x | -$27,071 |
| 666-7072 REFL PAV MRK TY I(W)(EXIT GORE)(100MIL) | 20 EA | $438.00 | $964.21 | 0.45x | -$10,524 |
| 666-7069 REFL PAV MRK TY I(W)(ENTR GORE)(100MIL) | 20 EA | $412.00 | $869.92 | 0.47x | -$9,158 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 200,000 LF | $0.0250 | $0.0662 | 0.38x | -$8,240 |
| 666-7352 PAVEMENT SLER 24" | 3,500 LF | $0.5200 | $1.84 | 0.28x | -$4,609 |
STRIPE LINES, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7033 MOBILIZATION (EMERGENCY) | 6 EA | $5,000.00 | $844.81 | 5.92x | $24,931 |
| 666-7347 PAVEMENT SLER 6" | 150,000 LF | $0.3500 | $0.1841 | 1.90x | $24,885 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $2,500.00 | $600.85 | 4.16x | $22,790 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 25,000 LF | $1.25 | $0.6515 | 1.92x | $14,963 |
| 666-7274 RE PROFILE PM TY I(Y)6"(BRK)(100MIL) | 5,000 LF | $1.50 | $0.6738 | 2.23x | $4,131 |
| 505-7003 TMA (MOBILE OPERATION) | 150 DAY | $25.00 | $229.60 | 0.11x | -$30,690 |
| 505-7001 TMA (STATIONARY) | 125 DAY | $15.00 | $217.57 | 0.07x | -$25,321 |
| 666-7072 REFL PAV MRK TY I(W)(EXIT GORE)(100MIL) | 20 EA | $150.00 | $964.21 | 0.16x | -$16,284 |
| 666-7069 REFL PAV MRK TY I(W)(ENTR GORE)(100MIL) | 20 EA | $150.00 | $869.92 | 0.17x | -$14,398 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 200,000 LF | $0.0100 | $0.0662 | 0.15x | -$11,240 |
| 677-7008 ELIM EXT PM & MRKS (24") | 4,500 LF | $0.9200 | $2.87 | 0.32x | -$8,778 |
| 677-7017 ELIM EXT PM & MRKS (EXIT GORE) | 20 EA | $25.00 | $362.62 | 0.07x | -$6,752 |
| 677-7016 ELIM EXT PM & MRKS (ENTR GORE) | 20 EA | $25.00 | $321.88 | 0.08x | -$5,938 |
| 677-7009 ELIM EXT PM & MRKS (ARROW) | 175 EA | $25.00 | $50.50 | 0.50x | -$4,462 |
BATTERSON, LLP: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $2,600.00 | $600.85 | 4.33x | $23,990 |
| 500-7033 MOBILIZATION (EMERGENCY) | 6 EA | $3,000.00 | $844.81 | 3.55x | $12,931 |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 1,000 LF | $8.00 | $2.80 | 2.86x | $5,202 |
| 505-7003 TMA (MOBILE OPERATION) | 150 DAY | $10.00 | $229.60 | 0.04x | -$32,940 |
| 505-7001 TMA (STATIONARY) | 125 DAY | $10.00 | $217.57 | 0.05x | -$25,946 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 200,000 LF | $0.0100 | $0.0662 | 0.15x | -$11,240 |
| 666-7069 REFL PAV MRK TY I(W)(ENTR GORE)(100MIL) | 20 EA | $355.00 | $869.92 | 0.41x | -$10,298 |
| 677-7016 ELIM EXT PM & MRKS (ENTR GORE) | 20 EA | $100.00 | $321.88 | 0.31x | -$4,438 |
INTERSTATE BARRICADES & MARKINGS, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7033 MOBILIZATION (EMERGENCY) | 6 EA | $10,000.00 | $844.81 | 11.84x | $54,931 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $4,500.00 | $600.85 | 7.49x | $46,790 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 25,000 LF | $2.50 | $0.6515 | 3.84x | $46,213 |
| 666-7114 REFL PAV MRK TY I (Y)8"(SLD)(100MIL) | 15,000 LF | $2.00 | $0.9877 | 2.02x | $15,185 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 26,400 LF | $0.8500 | $0.4757 | 1.79x | $9,882 |
| 666-7274 RE PROFILE PM TY I(Y)6"(BRK)(100MIL) | 5,000 LF | $2.50 | $0.6738 | 3.71x | $9,131 |
| 666-7352 PAVEMENT SLER 24" | 3,500 LF | $4.00 | $1.84 | 2.18x | $7,571 |
| 666-7362 PAVEMENT SLER (EXIT GORE) | 20 EA | $500.00 | $158.75 | 3.15x | $6,825 |
| 666-7353 PAVEMENT SLER (ARROW) | 125 EA | $85.00 | $30.62 | 2.78x | $6,797 |
| 666-7350 PAVEMENT SLER 12" | 5,000 LF | $2.00 | $0.6885 | 2.90x | $6,558 |
| 505-7003 TMA (MOBILE OPERATION) | 150 DAY | $100.00 | $229.60 | 0.44x | -$19,440 |
| 505-7001 TMA (STATIONARY) | 125 DAY | $100.00 | $217.57 | 0.46x | -$14,696 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 200,000 LF | $0.0100 | $0.0662 | 0.15x | -$11,240 |