IH 20 WESTBROOK TO COLORADO CITY
0005-08-109 · let Apr 8, 2026 · Mitchell, Abilene · Overlay
$12,796,839Low bid: CK NEWBERRY, LLC+2.2% vs estimate $12,515,643
$55,144Left on the table0.4% gap to the second bid
5BiddersSpread 61% low to high
45Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CK NEWBERRY, LLC | $12,796,839 | 2.2% | $55,144 | 1+$476,150 | 0 | |
| 2 | RK HALL, LLC | $12,851,983 | +0.4% | 2.7% | $2,339,653 | 0 | 0 |
| 3 | REECE ALBERT, INC. | $15,191,636 | +18.7% | 21.4% | $2,998,318 | 1+$85,578 | 0 |
| 4 | OVERLAND CORPORATION | $18,189,954 | +42.1% | 45.3% | $2,357,244 | 3+$4,817,230 | 0 |
| 5 | GILVIN-TERRILL, LTD. | $20,547,197 | +60.6% | 64.2% | 3+$6,681,483 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
CK NEWBERRY, LLC vs RK HALL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,000,000.00 | $399,945.56 | $523,850.32 | -$600,054 |
| 354-7074 PLANE ASPH CONC PAV (1.5") | 519,621 SY | $0.8500 | $1.77 | $1.35 | $478,051 |
| 346-7009 STONE-MTRX-ASPH SMA-D SAC-A PG76-22 | 30,191 TON | $160.00 | $152.15 | $152.44 | -$236,999 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 1,677 CY | $655.00 | $737.23 | $616.83 | $137,900 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 23,240 SY | $36.00 | $40.73 | $35.01 | $109,925 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 28,825 LF | $24.75 | $27.79 | $25.60 | $87,628 |
| 134-7002 BACKFILL (TY B) | 1,136 STA | $225.00 | $167.45 | $206.94 | -$65,377 |
| 341-7050 D-GR HMA TY-D SAC-B PG70-22 | 12,682 TON | $125.00 | $119.89 | $116.75 | -$64,805 |
| 454-7009 HEADER TYPE EXPANSION JOINT | 490 CF | $295.00 | $413.40 | $434.15 | $58,016 |
| 451-7052 RETROFIT RAIL (ADD HSS) | 3,238 LF | $130.00 | $141.78 | $125.03 | $38,144 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 15,830 EA | $1.00 | $3.35 | $1.03 | $37,201 |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 984 LF | $30.00 | $65.72 | $38.57 | $35,148 |
| 542-7001 REMOVE METAL BEAM GUARD FENCE | 33,200 LF | $2.00 | $1.13 | $2.84 | -$28,884 |
| 505-7003 TMA (MOBILE OPERATION) | 150 DAY | $25.00 | $200.00 | $229.60 | $26,250 |
| 666-7030 REFL PAV MRK TY I (W)12"(SLD)(100MIL) | 5,085 LF | $2.00 | $6.36 | $2.94 | $22,171 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 47 EA | $3,200.00 | $3,601.09 | $3,190.07 | $18,851 |
| 505-7001 TMA (STATIONARY) | 70 DAY | $500.00 | $237.54 | $217.57 | -$18,372 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $15,000.00 | $16,500.00 | $11,585.04 | $18,000 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $10,000.00 | $18,000.00 | $9,253.78 | $16,000 |
| 666-7309 ALL-WTHER PM TY I (W)6"(SLD)(100MIL) | 118,590 LF | $0.6500 | $0.5200 | $0.6917 | -$15,417 |
Positive: the low bidder was cheaper on that item. These 20 items account for $53,376 of the $55,144 gap.
CK NEWBERRY, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,000,000.00 | $523,850.32 | 1.91x | $476,150 |
REECE ALBERT, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 150 DAY | $800.12 | $229.60 | 3.48x | $85,578 |