Mill and Inlay (N) FY2027
6501-57-001 · let Oct 6, 2026 · Bowie, Atlanta · Routine Maintenance Project - Sealed
$5,500,500Low bid: EAST TEXAS BRIDGE, INC.-10.3% vs estimate $6,132,750
$752,245Left on the table13.7% gap to the second bid
5BiddersSpread 34% low to high
19Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | EAST TEXAS BRIDGE, INC. | $5,500,500 | -10.3% | $752,245 | 1+$195,193 | 0 | |
| 2 | RK HALL, LLC | $6,252,745 | +13.7% | 2.0% | $25,105 | 4+$886,705 | 0 |
| 3 | DRAKE COMPANIES LLC | $6,277,850 | +14.1% | 2.4% | $221,650 | 2+$298,441 | 0 |
| 4 | LONGVIEW BRIDGE AND ROAD, LTD. | $6,499,500 | +18.2% | 6.0% | $862,500 | 3+$1,163,751 | 0 |
| 5 | HIGHWAY 19 CONSTRUCTION LLC | $7,362,000 | +33.8% | 20.0% | 1+$795,193 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
EAST TEXAS BRIDGE, INC. vs RK HALL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 8 EA | $25,000.00 | $75,000.00 | $600.85 | $400,000 |
| 342-7001 PFC-C PG76-22 SAC-A | 5,000 TON | $253.00 | $230.00 | $170.34 | -$115,000 |
| 305-7016 SALV, HAUL & STKPL RCL APH PV (3") | 50,000 SY | $4.00 | $5.90 | $3.61 | $95,000 |
| 305-7018 SALV,HAUL & STKPL RCL APH PV (2") | 50,000 SY | $3.00 | $4.59 | $2.36 | $79,500 |
| 305-7022 SALV, HAUL & STKPL RCL APH PV (4") | 30,000 SY | $5.30 | $7.64 | $4.16 | $70,200 |
| 344-7030 SP MIXES SP-C SAC-A PG76-22 | 20,000 TON | $158.00 | $161.51 | $138.38 | $70,200 |
| 344-7077 TACK COAT | 22,000 GAL | $5.00 | $6.69 | $3.25 | $37,180 |
| 505-7002 TMA (MOBILE OPERATION) | 350 HR | $30.00 | $135.00 | $64.00 | $36,750 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $250.00 | $650.00 | $217.57 | $20,000 |
| 305-7039 SALV, HAUL & STKPL RCL APH PV (5"-7") | 6,000 SY | $9.00 | $12.01 | $9.00 | $18,060 |
| 662-7115 WK ZN PAV MRK SHT TERM RMV (W)(4") | 10,000 LF | $1.85 | $3.35 | $1.83 | $15,000 |
| 662-7116 WK ZN PAV MRK SHT TERM RMV (Y)(4") | 10,000 LF | $1.85 | $3.35 | $1.57 | $15,000 |
| 342-7015 TACK COAT | 5,500 GAL | $5.00 | $7.25 | $3.37 | $12,375 |
| 668-7089 PREFAB PM TY C (W)(24")(SLD) | 1,000 LF | $15.00 | $14.18 | $13.72 | -$820 |
| 666-7309 ALL-WTHER PM TY I (W)6"(SLD)(100MIL) | 50,000 LF | $0.7500 | $0.7400 | $0.6917 | -$500 |
| 666-7315 ALL-WTHER PM TY I (Y)6"(SLD)(100MIL) | 50,000 LF | $0.7500 | $0.7400 | $0.6819 | -$500 |
| 666-7310 ALL-WTHER PM TY I (W)6"(BRK)(100MIL) | 10,000 LF | $0.7500 | $0.7400 | $0.8630 | -$100 |
| 666-7316 ALL-WTHER PM TY I (Y)6"(BRK)(100MIL) | 10,000 LF | $0.7500 | $0.7400 | $0.7727 | -$100 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 50 DAY | $200.00 | $200.00 | $87.82 | $0 |
Positive: the low bidder was cheaper on that item. These 19 items account for $752,245 of the $752,245 gap.
EAST TEXAS BRIDGE, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 8 EA | $25,000.00 | $600.85 | 41.61x | $195,193 |
RK HALL, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 8 EA | $75,000.00 | $600.85 | 124.82x | $595,193 |
| 305-7018 SALV,HAUL & STKPL RCL APH PV (2") | 50,000 SY | $4.59 | $2.36 | 1.94x | $111,335 |
| 305-7022 SALV, HAUL & STKPL RCL APH PV (4") | 30,000 SY | $7.64 | $4.16 | 1.84x | $104,448 |
| 344-7077 TACK COAT | 22,000 GAL | $6.69 | $3.25 | 2.06x | $75,728 |
DRAKE COMPANIES LLC: unbalanced items
Placed 3LONGVIEW BRIDGE AND ROAD, LTD.: unbalanced items
Placed 4HIGHWAY 19 CONSTRUCTION LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 8 EA | $100,000.00 | $600.85 | 166.43x | $795,193 |