FM 1419 - Overlay
1426-01-058 · let Apr 8, 2026 · Cameron, Pharr · Overlay
$7,826,503Low bid: IOC COMPANY LLC+8.1% vs estimate $7,236,974
$498,450Left on the table6.4% gap to the second bid
5BiddersSpread 19% low to high
93Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | IOC COMPANY LLC | $7,826,503 | 8.1% | $498,450 | 0 | 3-$981,589 | |
| 2 | EARTHWORKS ENTERPRISE | $8,324,953 | +6.4% | 15.0% | $142,617 | 1+$157,371 | 1-$60,095 |
| 3 | FOREMOST PAVING, INC. | $8,467,569 | +8.2% | 17.0% | $7,616 | 0 | 0 |
| 4 | POSILLICO CIVIL, INC. | $8,475,185 | +8.3% | 17.1% | $824,422 | 1+$88,091 | 0 |
| 5 | CK NEWBERRY, LLC | $9,299,607 | +18.8% | 28.5% | 2+$231,340 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
IOC COMPANY LLC vs EARTHWORKS ENTERPRISE, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7064 SP MIXES SP-D SAC-A PG76-22 | 45,130 TON | $139.00 | $125.00 | $129.17 | -$631,820 |
| 354-7051 PLANE ASPH CONC PAV(2") | 395,872 SY | $0.8500 | $2.00 | $1.86 | $455,253 |
| 500-7001 MOBILIZATION | 1 LS | $1,000.00 | $380,000.00 | $523,850.32 | $379,000 |
| 3007-7001 BONDING COURSE | 27,712 GAL | $3.00 | $9.00 | $3.32 | $166,272 |
| 505-7003 TMA (MOBILE OPERATION) | 140 DAY | $1.00 | $350.00 | $229.60 | $48,860 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 8,893 SY | $69.00 | $64.00 | $60.19 | -$44,465 |
| 505-7001 TMA (STATIONARY) | 140 DAY | $0.1000 | $300.00 | $217.57 | $41,986 |
| 688-7004 VEH LP DETECT (SAWCUT) | 6,293 LF | $13.50 | $16.00 | $13.72 | $15,733 |
| 506-7044 BIODEG EROSN CONT LOGS (INSTL) (12") | 1,904 LF | $2.50 | $10.00 | $5.23 | $14,280 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 51,774 LF | $0.6300 | $0.7500 | $0.4986 | $6,213 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 39 CY | $770.00 | $621.00 | $616.83 | -$5,811 |
| 506-7046 BIODEG EROSN CONT LOGS (REMOVE) | 1,904 LF | $0.1000 | $3.00 | $1.29 | $5,522 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 8,530 LF | $5.89 | $6.50 | $7.19 | $5,203 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 18,466 LF | $0.7300 | $1.00 | $0.4757 | $4,986 |
| 666-7408 REFL PAV MRK TY I (W)6"(BRK)(100MIL) | 26,185 LF | $0.5900 | $0.7500 | $0.5627 | $4,190 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 1,080 LF | $29.40 | $33.00 | $25.60 | $3,888 |
| 668-7103 PREFAB PM TY C (W)(WORD) | 136 EA | $233.37 | $258.00 | $249.54 | $3,350 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 7 EA | $3,681.00 | $4,141.00 | $3,190.07 | $3,220 |
| 666-7179 RE PM TY II (W) 8" (SLD) | 6,048 LF | $0.2600 | $0.7500 | $0.4127 | $2,964 |
| 666-7172 RE PM TY II (W) 6" (BRK) | 11,776 LF | $0.2700 | $0.5000 | $0.2347 | $2,708 |
Positive: the low bidder was cheaper on that item. These 20 items account for $481,530 of the $498,450 gap.
IOC COMPANY LLC: unbalanced items
Placed 1EARTHWORKS ENTERPRISE: unbalanced items
Placed 2POSILLICO CIVIL, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 3007-7001 BONDING COURSE | 27,712 GAL | $6.50 | $3.32 | 1.96x | $88,091 |