FM 835 and Brazos River Bridge Replaceme
0933-01-044 · let Apr 7, 2026 · Lubbock, Lubbock · Bridge Replacement
$5,991,100Low bid: WEBBER, LLC+34.3% vs estimate $4,462,426
$2,405,837Left on the table40.2% gap to the second bid
2BiddersSpread 40% low to high
86Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | WEBBER, LLC | $5,991,100 | 34.3% | $2,405,837 | 7+$1,405,062 | 0 | |
| 2 | FNF CONSTRUCTION, INC. | $8,396,937 | +40.2% | 88.2% | 16+$3,913,781 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
WEBBER, LLC vs FNF CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 4067-7001 STR STEEL (PRESS BRAKE) | 187,386 LB | $3.00 | $9.50 | $3.00 | $1,218,009 |
| 100-7002 PREPARING ROW | 7 STA | $82,800.00 | $4,000.00 | $6,072.92 | -$551,600 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 625 SF | $46.00 | $579.00 | $28.47 | $333,125 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $650,000.00 | $325,000.00 | $136,676.66 | -$325,000 |
| 422-7023 REINF CONC SLAB (PRECAST SUPER ASSEM) | 6,790 SF | $95.50 | $140.00 | $63.92 | $302,155 |
| 500-7001 MOBILIZATION | 1 LS | $590,000.00 | $833,000.00 | $523,850.32 | $243,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $7,000.00 | $30,000.00 | $11,585.04 | $207,000 |
| 432-7002 RIPRAP (CONC)(5 IN) | 232 CY | $750.00 | $1,400.00 | $585.15 | $150,800 |
| 416-7006 DRILL SHAFT (36 IN) | 548 LF | $240.00 | $500.00 | $280.58 | $142,480 |
| 341-7083 D-GR HMA TY-B SAC-B PG70-28 | 1,313 TON | $200.00 | $275.00 | $146.43 | $98,475 |
| 420-7022 CL C CONC (CAP) | 19.2 CY | $2,400.00 | $7,000.00 | $1,543.38 | $88,320 |
| 450-7008 RAIL (TY T223) | 390 LF | $140.00 | $350.00 | $141.07 | $81,900 |
| 420-7013 CL C CONC (ABUT)(HPC) | 56.8 CY | $3,600.00 | $5,000.00 | $1,329.26 | $79,520 |
| 3002-7002 ASPH FOR REINF FAB (PG76-28) | 205 GAL | $325.00 | $8.50 | $5.17 | -$64,883 |
| 341-7053 D-GR HMA TY-D SAC-A PG70-28 | 237 TON | $255.00 | $500.00 | $133.62 | $58,065 |
| 439-7014 MULTI-LAYER POLYMER OVERLAY | 1,078 SY | $40.00 | $90.00 | $40.32 | $53,900 |
| 422-7014 APPROACH SLAB (HPC) | 107 CY | $1,500.00 | $1,000.00 | $731.91 | -$53,500 |
| 416-7004 DRILL SHAFT (24 IN) | 120 LF | $195.00 | $600.00 | $234.98 | $48,600 |
| 4006-7001 TEMP CONSTRUCTION ACCESS | 1 LS | $755,000.00 | $800,000.00 | $447,206.31 | $45,000 |
| 420-7023 CL C CONC (CAP)(HPC) | 27.6 CY | $2,900.00 | $4,000.00 | $1,420.15 | $30,360 |
Positive: the low bidder was cheaper on that item. These 20 items account for $2,185,727 of the $2,405,837 gap.
WEBBER, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 7 STA | $82,800.00 | $6,072.92 | 13.63x | $537,090 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $650,000.00 | $136,676.66 | 4.76x | $513,323 |
| 420-7013 CL C CONC (ABUT)(HPC) | 56.8 CY | $3,600.00 | $1,329.26 | 2.71x | $128,978 |
| 422-7014 APPROACH SLAB (HPC) | 107 CY | $1,500.00 | $731.91 | 2.05x | $82,185 |
| 3002-7002 ASPH FOR REINF FAB (PG76-28) | 205 GAL | $325.00 | $5.17 | 62.85x | $65,565 |
| 420-7023 CL C CONC (CAP)(HPC) | 27.6 CY | $2,900.00 | $1,420.15 | 2.04x | $40,844 |
| 105-7032 RMV (12") TRT/UNTRT BASE & ASPH PAV | 2,818 SY | $20.70 | $7.54 | 2.74x | $37,077 |
FNF CONSTRUCTION, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 4067-7001 STR STEEL (PRESS BRAKE) | 187,386 LB | $9.50 | $3.00 | 3.17x | $1,218,009 |
| 422-7023 REINF CONC SLAB (PRECAST SUPER ASSEM) | 6,790 SF | $140.00 | $63.92 | 2.19x | $516,600 |
| 4006-7001 TEMP CONSTRUCTION ACCESS | 1 LS | $800,000.00 | $447,206.31 | 1.79x | $352,794 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 625 SF | $579.00 | $28.47 | 20.34x | $344,081 |
| 420-7013 CL C CONC (ABUT)(HPC) | 56.8 CY | $5,000.00 | $1,329.26 | 3.76x | $208,498 |
| 432-7002 RIPRAP (CONC)(5 IN) | 232 CY | $1,400.00 | $585.15 | 2.39x | $189,045 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $325,000.00 | $136,676.66 | 2.38x | $188,323 |
| 341-7083 D-GR HMA TY-B SAC-B PG70-28 | 1,313 TON | $275.00 | $146.43 | 1.88x | $168,809 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $30,000.00 | $11,585.04 | 2.59x | $165,735 |
| 416-7006 DRILL SHAFT (36 IN) | 548 LF | $500.00 | $280.58 | 1.78x | $120,242 |