SH 35 BRIDGE REPLACEMENT 2712
0179-09-041 · let Apr 8, 2026 · Jackson, Yoakum · Bridge Replacement
$25,784,015Low bid: RAGLE CONSTRUCTION, INC.+19.9% vs estimate $21,500,022
$578,985Left on the table2.2% gap to the second bid
4BiddersSpread 46% low to high
76Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RAGLE CONSTRUCTION, INC. | $25,784,015 | 19.9% | $578,985 | 8+$9,363,723 | 0 | |
| 2 | ORION CONSTRUCTION, LLC | $26,363,000 | +2.2% | 22.6% | $5,786,043 | 3+$4,532,264 | 1-$186,428 |
| 3 | HUNTER INDUSTRIES, LTD. | $32,149,043 | +24.7% | 49.5% | $5,468,642 | 8+$12,490,700 | 0 |
| 4 | ZACHRY CONSTRUCTION CORPORATION | $37,617,685 | +45.9% | 75.0% | 12+$16,966,931 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
RAGLE CONSTRUCTION, INC. vs ORION CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 22 MO | $125,000.00 | $20,000.00 | $11,585.04 | -$2,310,000 |
| 425-7002 PRESTR CONC GIRDER (TX34) | 15,264 LF | $220.00 | $319.00 | $210.34 | $1,511,136 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 17,402 CY | $85.00 | $8.00 | $18.71 | -$1,339,954 |
| 409-7004 PRESTR CONC PIL (24 IN SQ) | 14,492 LF | $214.60 | $290.00 | $224.35 | $1,092,697 |
| 422-7001 REINF CONC SLAB | 117,760 SF | $24.00 | $33.00 | $24.45 | $1,059,840 |
| 496-7012 REMOV STR (BRIDGE 1000 FT OR GREATER) | 1 EA | $1,100,000.00 | $2,000,000.00 | $1,524,722.04 | $900,000 |
| 100-7002 PREPARING ROW | 66.4 STA | $50,000.00 | $39,608.43 | $6,072.92 | -$690,000 |
| 420-7022 CL C CONC (CAP) | 644.8 CY | $1,400.00 | $2,250.00 | $1,543.38 | $548,080 |
| 403-7001 TEMPORARY SPL SHORING | 3,378 SF | $60.00 | $0.2500 | $25.56 | -$201,836 |
| 110-7001 EXCAV (ROADWAY) | 21,426 CY | $18.00 | $11.00 | $11.68 | -$149,982 |
| 500-7001 MOBILIZATION | 1 LS | $2,500,000.00 | $2,630,000.00 | $523,850.32 | $130,000 |
| 450-7024 RAIL (TY SSTR) | 5,172 LF | $63.00 | $80.00 | $69.92 | $87,924 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $75,000.00 | $35,000.00 | $9,253.78 | -$80,000 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 1,260 LF | $175.00 | $115.00 | $52.29 | -$75,600 |
| 400-7010 CEM STABIL BKFL | 252 CY | $175.00 | $400.00 | $138.14 | $56,700 |
| 106-7002 OBLITERATING ABANDONED ROAD | 11,045 SY | $6.80 | $1.80 | $7.04 | -$55,225 |
| 454-7004 SEALED EXPANSION JOINT (4 IN) (SEJ - M) | 516 LF | $205.00 | $305.78 | $221.89 | $52,002 |
| 420-7012 CL C CONC (ABUT) | 56.8 CY | $1,400.00 | $2,250.00 | $1,307.98 | $48,280 |
| 341-7058 D-GR HMA TY-D SAC-B PG76-22 | 2,865 TON | $225.00 | $210.00 | $120.18 | -$42,975 |
| 341-7001 D-GR HMA TY-B PG64-22 | 2,426 TON | $195.00 | $180.00 | $97.82 | -$36,390 |
Positive: the low bidder was cheaper on that item. These 20 items account for $504,698 of the $578,985 gap.
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 66.4 STA | $50,000.00 | $6,072.92 | 8.23x | $2,916,758 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 22 MO | $125,000.00 | $11,585.04 | 10.79x | $2,495,129 |
| 500-7001 MOBILIZATION | 1 LS | $2,500,000.00 | $523,850.32 | 4.77x | $1,976,150 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 17,402 CY | $85.00 | $18.71 | 4.54x | $1,153,526 |
| 341-7058 D-GR HMA TY-D SAC-B PG76-22 | 2,865 TON | $225.00 | $120.18 | 1.87x | $300,304 |
| 341-7001 D-GR HMA TY-B PG64-22 | 2,426 TON | $195.00 | $97.82 | 1.99x | $235,747 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 1,260 LF | $175.00 | $52.29 | 3.35x | $154,616 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $75,000.00 | $9,253.78 | 8.10x | $131,492 |
ORION CONSTRUCTION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 66.4 STA | $39,608.43 | $6,072.92 | 6.52x | $2,226,758 |
| 500-7001 MOBILIZATION | 1 LS | $2,630,000.00 | $523,850.32 | 5.02x | $2,106,150 |
| 341-7001 D-GR HMA TY-B PG64-22 | 2,426 TON | $180.00 | $97.82 | 1.84x | $199,357 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 17,402 CY | $8.00 | $18.71 | 0.43x | -$186,428 |
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 409-7004 PRESTR CONC PIL (24 IN SQ) | 14,492 LF | $560.00 | $224.35 | 2.50x | $4,864,288 |
| 100-7002 PREPARING ROW | 66.4 STA | $48,382.03 | $6,072.92 | 7.97x | $2,809,325 |
| 500-7001 MOBILIZATION | 1 LS | $3,214,183.11 | $523,850.32 | 6.14x | $2,690,333 |
| 420-7022 CL C CONC (CAP) | 644.8 CY | $2,750.00 | $1,543.38 | 1.78x | $778,029 |
| 110-7001 EXCAV (ROADWAY) | 21,426 CY | $30.00 | $11.68 | 2.57x | $392,477 |
| 403-7001 TEMPORARY SPL SHORING | 3,378 SF | $125.00 | $25.56 | 4.89x | $335,906 |
| 450-7024 RAIL (TY SSTR) | 5,172 LF | $131.70 | $69.92 | 1.88x | $319,514 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 17,402 CY | $36.00 | $18.71 | 1.92x | $300,828 |
ZACHRY CONSTRUCTION CORPORATION: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 409-7004 PRESTR CONC PIL (24 IN SQ) | 14,492 LF | $605.00 | $224.35 | 2.70x | $5,516,428 |
| 100-7002 PREPARING ROW | 66.4 STA | $57,000.00 | $6,072.92 | 9.39x | $3,381,558 |
| 500-7001 MOBILIZATION | 1 LS | $3,750,000.00 | $523,850.32 | 7.16x | $3,226,150 |
| 420-7022 CL C CONC (CAP) | 644.8 CY | $3,350.00 | $1,543.38 | 2.17x | $1,164,909 |
| 450-7024 RAIL (TY SSTR) | 5,172 LF | $255.00 | $69.92 | 3.65x | $957,222 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 22 MO | $40,000.00 | $11,585.04 | 3.45x | $625,129 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 17,402 CY | $45.00 | $18.71 | 2.40x | $457,446 |
| 341-7058 D-GR HMA TY-D SAC-B PG76-22 | 2,865 TON | $270.00 | $120.18 | 2.25x | $429,229 |
| 247-7193 FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS) | 3,404 CY | $200.00 | $91.27 | 2.19x | $370,106 |
| 341-7001 D-GR HMA TY-B PG64-22 | 2,426 TON | $230.00 | $97.82 | 2.35x | $320,657 |