IH 69C Overlay FY 2026
0255-07-153 · let Apr 7, 2026 · Hidalgo, Pharr · Overlay
$8,784,922Low bid: FOREMOST PAVING, INC.+8.0% vs estimate $8,135,339
$2,140,902Left on the table24.4% gap to the second bid
3BiddersSpread 27% low to high
87Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FOREMOST PAVING, INC. | $8,784,922 | 8.0% | $2,140,902 | 0 | 1-$388,850 | |
| 2 | POSILLICO CIVIL, INC. | $10,925,824 | +24.4% | 34.3% | $204,381 | 2+$563,105 | 0 |
| 3 | CK NEWBERRY, LLC | $11,130,206 | +26.7% | 36.8% | 3+$924,670 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
FOREMOST PAVING, INC. vs POSILLICO CIVIL, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $135,000.00 | $993,256.75 | $523,850.32 | $858,257 |
| 346-7009 STONE-MTRX-ASPH SMA-D SAC-A PG76-22 | 25,799 TON | $135.87 | $160.00 | $152.44 | $622,530 |
| 344-7064 SP MIXES SP-D SAC-A PG76-22 | 15,679 TON | $117.67 | $145.00 | $129.17 | $428,507 |
| 3007-7001 BONDING COURSE | 25,470 GAL | $2.86 | $7.00 | $3.32 | $105,446 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 34,059 SY | $66.04 | $68.00 | $60.19 | $66,756 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $8,843.64 | $15,000.00 | $11,585.04 | $36,938 |
| 505-7003 TMA (MOBILE OPERATION) | 120 DAY | $0.0100 | $300.00 | $229.60 | $35,999 |
| 688-7004 VEH LP DETECT (SAWCUT) | 3,350 LF | $14.45 | $10.00 | $13.72 | -$14,908 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 3 EA | $39.90 | $4,000.00 | $3,190.07 | $11,880 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 72,990 LF | $0.2300 | $0.3000 | $0.1701 | $5,109 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 285 LF | $47.22 | $31.00 | $25.60 | -$4,623 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $169.50 | $140.00 | $217.57 | -$3,540 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 94,576 LF | $0.1700 | $0.1500 | $0.2040 | -$1,892 |
| 542-7001 REMOVE METAL BEAM GUARD FENCE | 305 LF | $10.00 | $5.00 | $2.84 | -$1,525 |
| 104-7005 REMOV CONC (MOWSTRIP) | 21 LF | $34.71 | $100.00 | $9.49 | $1,371 |
| 666-7024 REFL PAV MRK TY I (W)8"(SLD)(100MIL) | 9,041 LF | $0.8900 | $1.00 | $0.9489 | $995 |
| 544-7003 GUARDRAIL END TREATMENT (REMOVE) | 2 EA | $756.49 | $275.00 | $284.94 | -$963 |
| 658-7012 INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB | 125 EA | $21.97 | $15.00 | $9.89 | -$871 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 73,343 LF | $0.6100 | $0.6000 | $0.4986 | -$733 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 72,990 LF | $0.6100 | $0.6000 | $0.4757 | -$730 |
Positive: the low bidder was cheaper on that item. These 20 items account for $2,144,003 of the $2,140,902 gap.
FOREMOST PAVING, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $135,000.00 | $523,850.32 | 0.26x | -$388,850 |