CR 33: 0915-11-037: BR
0915-11-037 · let Sep 2, 2026 · Kendall, San Antonio · Bridge Replacement
$659,000Low bid: DELGADO'S CONTRACTORS, LLC+25.8% vs estimate $523,737
$11,257Left on the table1.7% gap to the second bid
8BiddersSpread 30% low to high
55Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DELGADO'S CONTRACTORS, LLC | $659,000 | 25.8% | $11,257 | 3+$41,072 | 3-$559,581 | |
| 2 | PRESIDIO CONTRACTING, LLC | $670,257 | +1.7% | 28.0% | $92,677 | 6+$62,363 | 4-$546,406 |
| 3 | TAYLOR BRIDGE LLC | $762,934 | +15.8% | 45.7% | $2,490 | 7+$111,928 | 4-$529,972 |
| 4 | E-Z BEL CONSTRUCTION, LLC | $765,423 | +16.1% | 46.1% | $54,948 | 6+$94,734 | 3-$529,897 |
| 5 | J3 COMPANY, LLC | $820,372 | +24.5% | 56.6% | $3,206 | 7+$91,708 | 3-$534,176 |
| 6 | STX CIVIL | $823,577 | +25.0% | 57.3% | $16,783 | ||
| 7 | DEAN WORD COMPANY, LTD. | $840,360 | +27.5% | 60.5% | $13,864 | ||
| 8 | YOKO EXCAVATING, LLC | $854,224 | +29.6% | 63.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
DELGADO'S CONTRACTORS, LLC vs PRESIDIO CONTRACTING, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $42,500.00 | $67,000.00 | $523,850.32 | $24,500 |
| 420-7012 CL C CONC (ABUT) | 43.6 CY | $1,200.00 | $940.00 | $1,307.98 | -$11,336 |
| 422-7013 APPROACH SLAB | 51.4 CY | $800.00 | $595.00 | $738.51 | -$10,537 |
| 104-7030 REMOV CONC (APPR SLAB) | 292 SY | $50.00 | $15.50 | $64.93 | -$10,074 |
| 450-7008 RAIL (TY T223) | 178 LF | $150.00 | $100.00 | $141.07 | -$8,900 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $8,500.00 | $6,710.00 | $9,253.78 | -$7,160 |
| 416-7006 DRILL SHAFT (36 IN) | 120 LF | $395.00 | $453.40 | $280.58 | $7,008 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 128 CY | $250.00 | $200.00 | $184.74 | -$6,400 |
| 422-7001 REINF CONC SLAB | 2,210 SF | $29.00 | $26.35 | $24.45 | -$5,857 |
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 379 CY | $45.00 | $57.25 | $17.39 | $4,643 |
| 425-7001 PRESTR CONC GIRDER (TX28) | 258 LF | $225.00 | $242.65 | $217.69 | $4,554 |
| 110-7001 EXCAV (ROADWAY) | 135 CY | $20.00 | $53.25 | $11.68 | $4,489 |
| 341-7032 D-GR HMA TY-C SAC-B PG76-22 | 96 TON | $175.00 | $212.80 | $175.00 | $3,629 |
| 400-7010 CEM STABIL BKFL | 102 CY | $165.00 | $200.40 | $138.14 | $3,611 |
| 100-7002 PREPARING ROW | 4.4 STA | $750.00 | $1,525.00 | $6,072.92 | $3,410 |
| 505-7003 TMA (MOBILE OPERATION) | 10 DAY | $200.00 | $465.00 | $229.60 | $2,650 |
| 164-7002 BROADCAST SEED (PERM_RURAL_CLAY) | 552 SY | $3.00 | $7.45 | $0.3117 | $2,456 |
| 341-7001 D-GR HMA TY-B PG64-22 | 339 TON | $175.00 | $181.85 | $97.82 | $2,322 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $15,762.00 | $17,900.00 | $28,021.15 | $2,138 |
| 540-7005 MTL BEAM GD FEN TRANS (THRIE-BEAM) | 4 EA | $2,100.00 | $2,615.00 | $2,218.70 | $2,060 |
Positive: the low bidder was cheaper on that item. These 20 items account for $7,206 of the $11,257 gap.
DELGADO'S CONTRACTORS, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7001 D-GR HMA TY-B PG64-22 | 339 TON | $175.00 | $97.82 | 1.79x | $26,162 |
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 379 CY | $45.00 | $17.39 | 2.59x | $10,464 |
| 161-7002 COMPOST MANUF TOPSOIL (4") | 552 SY | $10.00 | $1.95 | 5.14x | $4,445 |
| 500-7001 MOBILIZATION | 1 LS | $42,500.00 | $523,850.32 | 0.08x | -$481,350 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,450.00 | $11,585.04 | 0.21x | -$54,810 |
| 100-7002 PREPARING ROW | 4.4 STA | $750.00 | $6,072.92 | 0.12x | -$23,421 |
PRESIDIO CONTRACTING, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7001 D-GR HMA TY-B PG64-22 | 339 TON | $181.85 | $97.82 | 1.86x | $28,485 |
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 379 CY | $57.25 | $17.39 | 3.29x | $15,107 |
| 161-7002 COMPOST MANUF TOPSOIL (4") | 552 SY | $12.55 | $1.95 | 6.45x | $5,853 |
| 110-7001 EXCAV (ROADWAY) | 135 CY | $53.25 | $11.68 | 4.56x | $5,612 |
| 164-7002 BROADCAST SEED (PERM_RURAL_CLAY) | 552 SY | $7.45 | $0.3117 | 23.90x | $3,940 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 716 LF | $5.20 | $0.4986 | 10.43x | $3,366 |
| 500-7001 MOBILIZATION | 1 LS | $67,000.00 | $523,850.32 | 0.13x | -$456,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,400.00 | $11,585.04 | 0.21x | -$55,110 |
| 100-7002 PREPARING ROW | 4.4 STA | $1,525.00 | $6,072.92 | 0.25x | -$20,011 |
| 104-7030 REMOV CONC (APPR SLAB) | 292 SY | $15.50 | $64.93 | 0.24x | -$14,434 |
TAYLOR BRIDGE LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7001 D-GR HMA TY-B PG64-22 | 339 TON | $200.00 | $97.82 | 2.04x | $34,637 |
| 416-7006 DRILL SHAFT (36 IN) | 120 LF | $500.00 | $280.58 | 1.78x | $26,330 |
| 341-7032 D-GR HMA TY-C SAC-B PG76-22 | 96 TON | $350.00 | $175.00 | 2.00x | $16,800 |
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 379 CY | $50.00 | $17.39 | 2.88x | $12,359 |
| 400-7010 CEM STABIL BKFL | 102 CY | $250.00 | $138.14 | 1.81x | $11,409 |
| 505-7001 TMA (STATIONARY) | 2 DAY | $3,500.00 | $217.57 | 16.09x | $6,565 |
| 104-7006 REMOV CONC (RIPRAP) | 244 SY | $30.00 | $14.32 | 2.10x | $3,826 |
| 500-7001 MOBILIZATION | 1 LS | $75,000.00 | $523,850.32 | 0.14x | -$448,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $3,000.00 | $11,585.04 | 0.26x | -$51,510 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $3,000.00 | $9,253.78 | 0.32x | -$25,015 |
| 506-7020 CONSTRUCTION EXITS (INSTALL) (TY 1) | 156 SY | $1.00 | $30.47 | 0.03x | -$4,597 |
E-Z BEL CONSTRUCTION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 416-7006 DRILL SHAFT (36 IN) | 120 LF | $520.00 | $280.58 | 1.85x | $28,730 |
| 341-7001 D-GR HMA TY-B PG64-22 | 339 TON | $176.00 | $97.82 | 1.80x | $26,501 |
| 400-7010 CEM STABIL BKFL | 102 CY | $315.00 | $138.14 | 2.28x | $18,039 |
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 379 CY | $40.00 | $17.39 | 2.30x | $8,569 |
| 110-7001 EXCAV (ROADWAY) | 135 CY | $75.00 | $11.68 | 6.42x | $8,548 |
| 161-7002 COMPOST MANUF TOPSOIL (4") | 552 SY | $9.82 | $1.95 | 5.04x | $4,346 |
| 500-7001 MOBILIZATION | 1 LS | $70,000.00 | $523,850.32 | 0.13x | -$453,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1,000.00 | $11,585.04 | 0.09x | -$63,510 |
| 104-7030 REMOV CONC (APPR SLAB) | 292 SY | $22.00 | $64.93 | 0.34x | -$12,536 |
J3 COMPANY, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7001 D-GR HMA TY-B PG64-22 | 339 TON | $176.00 | $97.82 | 1.80x | $26,501 |
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 379 CY | $80.00 | $17.39 | 4.60x | $23,729 |
| 110-7001 EXCAV (ROADWAY) | 135 CY | $120.00 | $11.68 | 10.27x | $14,623 |
| 552-7003 WIRE FENCE (TY C) | 100 LF | $85.00 | $12.12 | 7.01x | $7,288 |
| 161-7002 COMPOST MANUF TOPSOIL (4") | 552 SY | $15.00 | $1.95 | 7.70x | $7,205 |
| 104-7006 REMOV CONC (RIPRAP) | 244 SY | $40.00 | $14.32 | 2.79x | $6,266 |
| 505-7003 TMA (MOBILE OPERATION) | 10 DAY | $839.00 | $229.60 | 3.65x | $6,094 |
| 500-7001 MOBILIZATION | 1 LS | $55,000.00 | $523,850.32 | 0.10x | -$468,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $5,000.00 | $11,585.04 | 0.43x | -$39,510 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $2,800.00 | $9,253.78 | 0.30x | -$25,815 |