6499-80-001 · let Sep 29, 2026 · Aransas, Corpus Christi · Routine Maintenance Project - Sealed
$264,045 Low bid: FYL ENTERPRISES, LLC -4.0% vs estimate $274,988
$12,304 Left on the table 4.7% gap to the second bid
5 Bidders Spread 85% low to high
4 Items compared Against statewide low-bid averages
The bids
# Bidder Total vs low vs estimate Gap to next Loaded items Cut items
1 FYL ENTERPRISES, LLC
$264,045 -4.0%
$12,304
0
3 -$572,432
2 CRACKSEAL OF TEXAS, LLC
$276,349 +4.7% 0.5%
$34,814
0
3 -$576,432
3 D & M CONTRACTORS, LLC
$311,163 +17.8% 13.2%
$21,332
0
3 -$568,344
4 THOMAS 11 DEVELOPMENT LLC
$332,495 +25.9% 20.9%
$156,044
1 +$22,173
2 -$502,605
5 GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
$488,539 +85.0% 77.7%
0
3 -$557,347
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won FYL ENTERPRISES, LLC vs CRACKSEAL OF TEXAS, LLC, biggest item swings
Item Qty Low 2nd Market 2nd minus low
712-7001 JT / CRCK SEAL (RUBBER - ASPHALT)362.3 LMI
$715.00 $760.00 $868.20
$16,304
500-7001 MOBILIZATION1 LS
$5,000.00 $1,000.00 $523,850.32
-$4,000
505-7003 TMA (MOBILE OPERATION)82 DAY
$0.0010 $0.0100 $229.60
$1
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING3 MO
$0.0010 $0.0100 $11,585.04
$0
Positive: the low bidder was cheaper on that item. These 4 items account for $12,304 of the $12,304 gap.
FYL ENTERPRISES, LLC: unbalanced items Placed 1
Item Qty Their price Market x market $ vs market
500-7001 MOBILIZATION1 LS
$5,000.00 $523,850.32 0.01x -$518,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING3 MO
$0.0010 $11,585.04 0.00x -$34,755
505-7003 TMA (MOBILE OPERATION)82 DAY
$0.0010 $229.60 0.00x -$18,827
CRACKSEAL OF TEXAS, LLC: unbalanced items Placed 2
Item Qty Their price Market x market $ vs market
500-7001 MOBILIZATION1 LS
$1,000.00 $523,850.32 0.00x -$522,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING3 MO
$0.0100 $11,585.04 0.00x -$34,755
505-7003 TMA (MOBILE OPERATION)82 DAY
$0.0100 $229.60 0.00x -$18,826
D & M CONTRACTORS, LLC: unbalanced items Placed 3
Item Qty Their price Market x market $ vs market
500-7001 MOBILIZATION1 LS
$9,000.00 $523,850.32 0.02x -$514,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING3 MO
$2.00 $11,585.04 0.00x -$34,749
505-7003 TMA (MOBILE OPERATION)82 DAY
$1.00 $229.60 0.00x -$18,745
THOMAS 11 DEVELOPMENT LLC: unbalanced items Placed 4
Item Qty Their price Market x market $ vs market
505-7003 TMA (MOBILE OPERATION)82 DAY
$500.00 $229.60 2.18x $22,173
500-7001 MOBILIZATION1 LS
$50,000.00 $523,850.32 0.10x -$473,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING3 MO
$2,000.00 $11,585.04 0.17x -$28,755
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY: unbalanced items Placed 5
Item Qty Their price Market x market $ vs market
500-7001 MOBILIZATION1 LS
$20,000.00 $523,850.32 0.04x -$503,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING3 MO
$1.00 $11,585.04 0.00x -$34,752
505-7003 TMA (MOBILE OPERATION)82 DAY
$1.00 $229.60 0.00x -$18,745