Callout Cable Barrier East FY26
6505-54-001 · let Oct 29, 2026 · Taylor, Abilene · Routine Maintenance Project - Sealed
$696,554Low bid: ROSS SA ENTERPRISE LLC+11.3% vs estimate $625,967
$68,329Left on the table9.8% gap to the second bid
3BiddersSpread 15% low to high
8Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ROSS SA ENTERPRISE LLC | $696,554 | 11.3% | $68,329 | 0 | 4-$144,348 | |
| 2 | T&L CLEANING SERVICES LLC | $764,883 | +9.8% | 22.2% | $32,836 | 0 | 5-$149,793 |
| 3 | AUSTIN BARRICADE COMPANY, L.L.C. | $797,719 | +14.5% | 27.4% | 2+$14,362 | 3-$133,941 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
ROSS SA ENTERPRISE LLC vs T&L CLEANING SERVICES LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 771-7025 REPLACE LINE OR TERMINAL POST (VALTIR) | 2,124 EA | $275.00 | $300.00 | $215.97 | $53,100 |
| 771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL) | 604 EA | $175.00 | $200.00 | $176.83 | $15,100 |
| 771-7029 REPLACE CABLE RELEASE POST | 57 EA | $100.00 | $1.00 | $148.81 | -$5,643 |
| 771-7033 SPLICE CABLE | 20 EA | $1.00 | $150.00 | $342.77 | $2,980 |
| 771-7031 REPLACE CABLE | 698 LF | $1.00 | $5.00 | $3.23 | $2,792 |
| 500-7002 MOBILIZATION (CALLOUT) | 20 EA | $1.00 | $1.00 | $600.85 | $0 |
| 500-7033 MOBILIZATION (EMERGENCY) | 91 EA | $1.00 | $1.00 | $844.81 | $0 |
| 505-7001 TMA (STATIONARY) | 225 DAY | $1.00 | $1.00 | $217.57 | $0 |
Positive: the low bidder was cheaper on that item. These 8 items account for $68,329 of the $68,329 gap.
ROSS SA ENTERPRISE LLC: unbalanced items
Placed 1T&L CLEANING SERVICES LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7033 MOBILIZATION (EMERGENCY) | 91 EA | $1.00 | $844.81 | 0.00x | -$76,787 |
| 505-7001 TMA (STATIONARY) | 225 DAY | $1.00 | $217.57 | 0.00x | -$48,729 |
| 500-7002 MOBILIZATION (CALLOUT) | 20 EA | $1.00 | $600.85 | 0.00x | -$11,997 |
| 771-7029 REPLACE CABLE RELEASE POST | 57 EA | $1.00 | $148.81 | 0.01x | -$8,425 |
| 771-7033 SPLICE CABLE | 20 EA | $150.00 | $342.77 | 0.44x | -$3,855 |
AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7031 REPLACE CABLE | 698 LF | $15.00 | $3.23 | 4.65x | $8,218 |
| 771-7033 SPLICE CABLE | 20 EA | $650.00 | $342.77 | 1.90x | $6,145 |
| 500-7033 MOBILIZATION (EMERGENCY) | 91 EA | $1.00 | $844.81 | 0.00x | -$76,787 |
| 505-7001 TMA (STATIONARY) | 225 DAY | $1.00 | $217.57 | 0.00x | -$48,729 |
| 771-7029 REPLACE CABLE RELEASE POST | 57 EA | $1.00 | $148.81 | 0.01x | -$8,425 |