SH 132:0017-13-013; SC
0017-13-013 · let Oct 7, 2026 · Atascosa, San Antonio · Seal Coat
$10,890,777Low bid: RONALD R. WAGNER & CO., LP+0.3% vs estimate $10,853,914
$542,107Left on the table5.0% gap to the second bid
3BiddersSpread 6% low to high
414Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RONALD R. WAGNER & CO., LP | $10,890,777 | 0.3% | $542,107 | 1+$1,350,636 | 1-$69,510 | |
| 2 | CLARK CONSTRUCTION OF TEXAS, INC. | $11,432,884 | +5.0% | 5.3% | $102,115 | 1+$1,234,755 | 0 |
| 3 | STX CIVIL | $11,534,999 | +5.9% | 6.3% | 1+$182,488 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
RONALD R. WAGNER & CO., LP vs CLARK CONSTRUCTION OF TEXAS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 316-7224 AGGR (TY-PD, GR-4)(SAC-B) | 22,366 CY | $91.81 | $104.83 | $86.92 | $291,205 |
| 316-7084 ASPH (AC-20-5TR OR AC-20XP) | 4,019 TON | $578.63 | $644.00 | $650.02 | $262,722 |
| 500-7001 MOBILIZATION | 1 LS | $1,874,486.43 | $1,758,605.00 | $523,850.32 | -$115,881 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $0.0100 | $15,000.00 | $11,585.04 | $90,000 |
| 316-7222 AGGR (TY-PD, GR-3)(SAC-B) | 9,622 CY | $120.00 | $121.20 | $103.76 | $11,546 |
| 316-7214 AGGR (TY-PB, GR-5)(SAC-B) | 240 CY | $53.48 | $63.00 | $121.24 | $2,285 |
| 505-7003 TMA (MOBILE OPERATION) | 232 DAY | $0.0100 | $1.00 | $229.60 | $230 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 4,101 EA | $0.0100 | $0.0100 | $1.03 | $0 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 47,222 EA | $0.0100 | $0.0100 | $0.5715 | $0 |
| 668-7091 PREFAB PM TY C (W)(ARROW) | 139 EA | $200.00 | $200.00 | $201.69 | $0 |
| 668-7093 PREFAB PM TY C (W)(DBL ARROW) | 1 EA | $225.00 | $225.00 | $314.80 | $0 |
| 668-7100 PREFAB PM TY C (W)(LN REDUCT ARROW) | 22 EA | $350.00 | $350.00 | $467.68 | $0 |
| 668-7102 PREFAB PM TY C (W)(NUMBER) | 2 EA | $150.00 | $150.00 | $129.07 | $0 |
| 668-7103 PREFAB PM TY C (W)(WORD) | 142 EA | $225.00 | $225.00 | $249.54 | $0 |
| 668-7108 PREFAB PM TY C (W)(RR XING) | 5 EA | $750.00 | $750.00 | $602.94 | $0 |
| 668-7111 PREFAB PM TY C (W)(36")(YLD TRI) | 125 EA | $50.00 | $50.00 | $38.96 | $0 |
| 668-7129 PREFAB PM TY C (Y)(MED NOSE) | 51 EA | $350.00 | $350.00 | $318.45 | $0 |
| 672-7002 REFL PAV MRKR TY I-C | 1,363 EA | $4.00 | $4.00 | $4.04 | $0 |
| 672-7004 REFL PAV MRKR TY II-A-A | 26,899 EA | $4.00 | $4.00 | $3.97 | $0 |
| 316-7001 ASPH (A-R TYPE II) | 690,971 GAL | $3.30 | $3.30 | $3.86 | $0 |
Positive: the low bidder was cheaper on that item. These 20 items account for $542,107 of the $542,107 gap.
RONALD R. WAGNER & CO., LP: unbalanced items
Placed 1CLARK CONSTRUCTION OF TEXAS, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,758,605.00 | $523,850.32 | 3.36x | $1,234,755 |
STX CIVIL: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7537 RE PM TY II (Y)6"(SLD)(020 MIL) | 1,313,808 LF | $0.3100 | $0.1711 | 1.81x | $182,488 |