SL375 MILL & INLAY (IH 10 | TOM MAYS PK)
2552-01-062 · let Nov 3, 2026 · El Paso, El Paso · Restoration
$11,850,861Low bid: ALLEN CONCRETE, LLC-18.8% vs estimate $14,597,735
$532,750Left on the table4.5% gap to the second bid
6BiddersSpread 31% low to high
122Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ALLEN CONCRETE, LLC | $11,850,861 | -18.8% | $532,750 | 2+$890,159 | 1-$3,452,790 | |
| 2 | DAN WILLIAMS COMPANY | $12,383,611 | +4.5% | -15.2% | $799,772 | 0 | 0 |
| 3 | JORDAN FOSTER CONSTRUCTION, LLC | $13,183,383 | +11.2% | -9.7% | $622,072 | 2+$787,848 | 0 |
| 4 | ALLIED PAVING CO. | $13,805,455 | +16.5% | -5.4% | $489,857 | 1+$516,150 | 1-$296,535 |
| 5 | INTERNATIONAL EAGLE ENTERPRISES, INC. | $14,295,311 | +20.6% | -2.1% | $1,280,131 | 1+$187,290 | 0 |
| 6 | RAGLE CONSTRUCTION, INC. | $15,575,442 | +31.4% | 6.7% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ALLEN CONCRETE, LLC vs DAN WILLIAMS COMPANY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 346-7001 STONE-MTRX-ASPH SMA-C SAC-A PG76-22 | 27,637 TON | $32.00 | $136.50 | $156.93 | $2,888,067 |
| 341-7046 D-GR HMA TY-D PG64-22 (LEVEL-UP) | 1,299 TON | $760.00 | $145.00 | $152.47 | -$798,885 |
| 351-7004 FLEXIBLE PAVEMENT STRUCTURE REPAIR(5") | 152,427 SY | $35.00 | $32.00 | $35.89 | -$457,281 |
| 500-7001 MOBILIZATION | 1 LS | $689,036.19 | $375,000.00 | $523,850.32 | -$314,036 |
| 354-7052 PLANE ASPH CONC PAV(3") | 167,496 SY | $3.50 | $2.00 | $2.92 | -$251,244 |
| 439-7015 POLYESTER POLYMER CONC OVERLAY (3/4") | 18,379 SY | $98.00 | $87.00 | $106.74 | -$202,169 |
| 3005-7001 MEMBRANE UNDERSEAL | 41,874 GAL | $8.00 | $5.00 | $4.76 | -$125,622 |
| 354-7033 PLANE ASPH CONC PAV(0" TO 3") | 22,728 SY | $7.55 | $2.10 | $3.11 | -$123,868 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 1,234 LF | $12.00 | $55.00 | $15.92 | $53,062 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $14,250.00 | $20,000.00 | $11,585.04 | $46,000 |
| 505-7001 TMA (STATIONARY) | 144 DAY | $540.00 | $250.00 | $217.57 | -$41,760 |
| 134-7009 BACKFILL (TY A OR B)(VEH) | 1,291 CY | $55.00 | $35.00 | $29.93 | -$25,820 |
| 483-7016 SHOT BLASTING | 18,379 SY | $4.50 | $3.70 | $5.25 | -$14,703 |
| 658-7211 REPLC DEL ASSM (D-SY)SZ 6(BRF)CAB3(BI) | 499 EA | $70.00 | $45.00 | $70.00 | -$12,475 |
| 542-7002 REMOVE TERMINAL ANCHOR SECTION | 19 EA | $975.00 | $325.00 | $263.33 | -$12,350 |
| 666-7270 RE PROFILE PM TY I(Y)6"(SLD)(100MIL) | 39,281 LF | $1.45 | $1.20 | $0.6629 | -$9,820 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 38,565 LF | $1.45 | $1.20 | $0.6515 | -$9,641 |
| 658-7177 REPLC DEL ASSM (D-SW)SZ 1(BRF)CTB | 1,186 EA | $38.00 | $32.00 | $37.94 | -$7,116 |
| 354-7024 PLAN & TEXT CONC PAV(0" TO 0.75") | 1,740 SY | $15.00 | $11.00 | $14.11 | -$6,960 |
| 506-7044 BIODEG EROSN CONT LOGS (INSTL) (12") | 1,512 LF | $4.50 | $8.75 | $5.23 | $6,426 |
Positive: the low bidder was cheaper on that item. These 20 items account for $579,804 of the $532,750 gap.
ALLEN CONCRETE, LLC: unbalanced items
Placed 1JORDAN FOSTER CONSTRUCTION, LLC: unbalanced items
Placed 3ALLIED PAVING CO.: unbalanced items
Placed 4INTERNATIONAL EAGLE ENTERPRISES, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 134-7009 BACKFILL (TY A OR B)(VEH) | 1,291 CY | $175.00 | $29.93 | 5.85x | $187,290 |