US0087-1-1/1
0068-05-039 · let Sep 3, 2026 · Dawson, Lubbock · Safety Improvement Projects
$3,985,831Low bid: GRATIOT CONSTRUCTION, LTD.-9.8% vs estimate $4,420,417
$211,972Left on the table5.3% gap to the second bid
5BiddersSpread 39% low to high
24Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | GRATIOT CONSTRUCTION, LTD. | $3,985,831 | -9.8% | $211,972 | 1+$38,126 | 4-$192,325 | |
| 2 | ALTUS CONSTRUCTION LLC | $4,197,803 | +5.3% | -5.0% | $357,204 | 2+$434,801 | 1-$101,754 |
| 3 | HJC FARMS, INC. | $4,555,008 | +14.3% | 3.0% | $424,624 | 0 | 2-$149,506 |
| 4 | SCR CIVIL CONSTRUCTION, LLC | $4,979,632 | +24.9% | 12.7% | $554,725 | 2+$512,654 | 1-$42,210 |
| 5 | MASSANA CONSTRUCTION INC. | $5,534,357 | +38.9% | 25.2% | 1+$1,205,589 | 2-$68,637 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
GRATIOT CONSTRUCTION, LTD. vs ALTUS CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 314-7011 EMULS ASPH (EROSN CONT)(CSS-1H) | 49,635.53 GAL | $3.00 | $9.92 | $3.76 | $343,478 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $6,000.00 | $29,986.18 | $11,585.04 | $167,903 |
| 110-7001 EXCAV (ROADWAY) | 51,702.52 CY | $10.00 | $7.61 | $11.68 | -$123,569 |
| 500-7001 MOBILIZATION | 1 LS | $520,000.00 | $417,707.49 | $523,850.32 | -$102,293 |
| 505-7001 TMA (STATIONARY) | 304 DAY | $1.00 | $202.49 | $217.57 | $61,253 |
| 543-7002 CABLE BARRIER SYSTEM (INSTALL)(TL-4) | 63,140 LF | $14.75 | $13.84 | $12.40 | -$57,457 |
| 543-7018 CABLE BARRIER TERM SEC (INSTL)(TL-4) | 42 EA | $3,500.00 | $2,267.77 | $2,822.11 | -$51,754 |
| 432-7014 RIPRAP (MOW STRIP)(5 IN) | 2,980.51 CY | $475.00 | $457.69 | $480.77 | -$51,593 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 410 DAY | $1.00 | $89.96 | $87.82 | $36,474 |
| 506-7045 BIODEG EROSN CONT LOGS (INSTL) (18") | 5,700 LF | $15.00 | $8.64 | $8.31 | -$36,252 |
| 134-7002 BACKFILL (TY B) | 642.95 STA | $100.00 | $48.68 | $206.94 | -$32,996 |
| 6016-7001 TEMP SPEED MONITOR SYS | 2 EA | $3,500.00 | $16,149.44 | $14,567.06 | $25,299 |
| 543-7036 CABLE BARRIER TERM SEC (RELOC)(TL-4) | 5 EA | $1,744.19 | $6,127.29 | $3,795.73 | $21,916 |
| 106-7001 OBLITERATING ABANDONED ROAD | 9.28 STA | $3,000.00 | $5,204.12 | $4,237.42 | $20,454 |
| 677-7004 ELIM EXT PM & MRKS (8") | 1,052 LF | $11.00 | $0.7300 | $0.6468 | -$10,804 |
| 505-7003 TMA (MOBILE OPERATION) | 20 DAY | $1.00 | $215.58 | $229.60 | $4,292 |
| 644-7065 RELOCATE SM RD SN SUP&AM TY 10BWG | 20 EA | $930.00 | $1,139.96 | $643.01 | $4,199 |
| 506-7046 BIODEG EROSN CONT LOGS (REMOVE) | 3,800 LF | $2.10 | $1.27 | $1.29 | -$3,154 |
| 730-7019 FULL - WIDTH MOWING | 2 CYC | $5,800.00 | $5,011.09 | $4,717.56 | -$1,578 |
| 543-7020 CABLE BARRIER SYSTEM (RELOCATE)(TL-4) | 500 LF | $17.44 | $15.33 | $13.57 | -$1,055 |
Positive: the low bidder was cheaper on that item. These 20 items account for $212,763 of the $211,972 gap.
GRATIOT CONSTRUCTION, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 506-7045 BIODEG EROSN CONT LOGS (INSTL) (18") | 5,700 LF | $15.00 | $8.31 | 1.80x | $38,126 |
| 134-7002 BACKFILL (TY B) | 642.95 STA | $100.00 | $206.94 | 0.48x | -$68,758 |
| 505-7001 TMA (STATIONARY) | 304 DAY | $1.00 | $217.57 | 0.00x | -$65,838 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 410 DAY | $1.00 | $87.82 | 0.01x | -$35,595 |
| 6016-7001 TEMP SPEED MONITOR SYS | 2 EA | $3,500.00 | $14,567.06 | 0.24x | -$22,134 |