FY 27 Districtwide Seal Coat Aggregate
6496-55-001 · let Nov 3, 2026 · Bastrop, Austin · Material Maintenance Project
$2,525,950Low bid: TOUCHSTONE RESOURCES, LLC-5.5% vs estimate $2,672,500
$11,200Left on the table0.4% gap to the second bid
4BiddersSpread 37% low to high
9Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TOUCHSTONE RESOURCES, LLC | $2,525,950 | -5.5% | $11,200 | 0 | 0 | |
| 2 | GREEN DREAM INTERNATIONAL LLC | $2,537,150 | +0.4% | -5.1% | $51,865 | 0 | 0 |
| 3 | DIGG COMMERCIAL, LLC | $2,589,015 | +2.5% | -3.1% | $878,985 | 0 | 0 |
| 4 | COLORADO MATERIALS, LTD. | $3,468,000 | +37.3% | 29.8% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
TOUCHSTONE RESOURCES, LLC vs GREEN DREAM INTERNATIONAL LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8000-7151 AGGR (TY D GR 4)(DEL)(ST11) | 8,000 TON | $75.00 | $71.50 | $72.02 | -$28,000 |
| 8000-7145 AGGR (TY D GR 4)(DEL)(ST5) | 4,750 TON | $70.00 | $71.50 | $77.04 | $7,125 |
| 8000-7149 AGGR (TY D GR 4)(DEL)(ST9) | 3,750 TON | $73.00 | $74.80 | $80.49 | $6,750 |
| 8000-7143 AGGR (TY D GR 4)(DEL)(ST3) | 5,500 TON | $56.00 | $57.20 | $62.78 | $6,600 |
| 8000-7147 AGGR (TY D GR 4)(DEL)(ST7) | 2,000 TON | $80.00 | $82.50 | $83.75 | $5,000 |
| 8000-7141 AGGR (TY D GR 4)(DEL)(ST1) | 3,500 TON | $75.70 | $77.00 | $82.64 | $4,550 |
| 8000-7148 AGGR (TY D GR 4)(DEL)(ST8) | 1,750 TON | $65.00 | $67.10 | $68.60 | $3,675 |
| 8000-7142 AGGR (TY D GR 4)(DEL)(ST2) | 4,000 TON | $62.00 | $62.70 | $69.07 | $2,800 |
| 8000-7144 AGGR (TY D GR 4)(DEL)(ST4) | 3,000 TON | $75.00 | $75.90 | $89.36 | $2,700 |
Positive: the low bidder was cheaper on that item. These 9 items account for $11,200 of the $11,200 gap.